Information
-
Project # and Project Name
-
Audit Month & Year
-
Location
-
Prepared by
-
For the Client/Project Manager:
-
Conducted on
Construction Site Safety Inspection Checklist
-
Contractor and Contract #
-
There is a copy of the Construction Safety Management Plan available on site?
-
There are records of inductions for all employees, contractors and sub-contractors
-
Emergency procedures and contacts are readily available and posted in site offices
-
First aid facilities are available, including first aid kits and trained first aid officers
-
Fire Extinguishers are tested and well signed
-
Workers on site are observed to be wearing all required personal protective equipment
-
Work site is generally clean and tidy with minimal rubbish/refuse laying around
-
Power leads on site are tested with current tags in place
-
There are safe work method statements and risk assessments for working at heights
-
There is evidence that scaffolding is erected by competent persons (ie. certificate/tag)
-
There is no obvious damage to ladders or other steps and equipment
-
There are safe work method statements and risk assessments for asbestos work
-
Work method statements do NOT allow asbestos cutting with power equipment
-
There is a list/register or all substances being used on site
-
Material Safety Data Sheets are available for hazardous substances and dangerous goods
-
All energy sources including electricity, water and air are isolated
-
Locks are fitted as part of isolation procedures by all stakeholders
-
There are safe work method statements and risk assessments for confined spaces
-
Where there are workers in a confined space, observers are present
-
There are safe work method statements for working near identified services
-
There is evidence that buried services have been identified prior to excavation
-
There are safe work method statements and risk assessments for work near traffic
-
There are work zone traffic management plans in place when working near roads
-
Traffic management plans include safety of pedestrians
-
There is a process for managing plant (excluding hand tools)
-
There is evidence that daily inspections are carried out on load shifting plant
-
There is evidence that plant operations have appropriate licenses or training
-
There are safe work method statements and risk assessments for working over water
-
All people woking over water are required to wear personal floatation devices
-
There are safe work method statements and risk assessments for excavation work
-
Shoring, benching or battering is being used where excavations are over 1.5 metres deep
-
Contractor Representative / Position
-
SAWater Representative / Position
-
Date