Welfare Facilities
-
Does the contractor have access to suitable welfare provisions?
Site Documentation
-
Has the supplier been subjected to formal evaluation and approval? (Leadec or Bosch)
-
Have documented RAMS including COSHH Assessments been produced for the works being undertaken?
-
Have the contractors undertaken a formal site induction delivered by the responsible Bosch person?
-
Does the contractor have in date training records for the works they are carrying out? (Gas safe; Electrical qualified; Legionella; Fire Warden / Extinguisher)
-
If carrying out any intrusive works on a building constructed before the year 2000, are they Asbestos Awareness Trained as a minimum?
-
If applicable (any building constructed before the year 2000) has the contractor been provided with a copy of the asbestos register?
-
Has the contractor signed in?
-
Are contractors wearing ID badges?
-
Has a permit been issued by a Bosch responsible person? If yes was the permit issued at the place of work by a person competent in the task that the permit is been issued for?
-
If applicable, has a fail safe isolation process been implemented?
-
If carrying out hot work activities, are a minimum of 2 x fire extinguishers located within arms reach? (one must be water or foam)
-
Does the contractor know the relevant Bosch emergency procedures for the site being worked at>
-
If portable mains fed electrical tools are in use, are they within an in date current Portable Appliance Test frequency?
-
Are the contractors neat in appearance?
-
If applicable, are calibration or service records available for the tools or equipment being used?
-
Are noise and vibration exposure details know for any power tools?
-
Are vibration exposure details being recorded for those people using high risk hand held vibrating equipment?
-
Are records available for weekly PUWER inspections?
-
Are records available on site for lifting equipment & accessories? (Lifting Equipment 12 x monthly; Lifting accessories 6 x monthly; Any lifting equipment used for persons 6 x monthly)
Work Area
-
Fully stocked and in date First Aid Box, Eye wash & Burns kit
-
Client’s authorisation to proceed / site access authorisation
-
Fire Extinguisher(s) adequate, correct locations, in date, signage?
-
Enough barriers of a sufficient standard to demark work area ensuring an exclusion zone is in place?
-
Adequate, secure storage containers (may include shipping containers/Plant safe/Strong boxes)
-
Adequate amount of Drip trays / Plant Nappies & Spill kits available in the correct locations. Locations of spill kits identified with signage
-
Gloves and goggles in each spill kit
-
Chemicals, liquids and lubricants stored on Storage Bunds
-
Gas Cylinder Cage in use where required
-
All HERAS fencing double clipped and correctly footed?
Work at Height
-
Are work at height activities being undertaken safely?
-
Is the correct work at height equipment being utilised following the work at height hierarchy? (i.e. Ladders as the last resort)
-
If ladders are being used are they the correct type? Tall enough for the task in hand? Records of weekly inspections? (Scaff Tag)
-
If working off a ladder, is the ladder being used safely? Is the person maintaining a minimum of 3 x points of contact?
-
If applicable, has scaffolding been erected following a design, or TG20 compliance sheet?
-
Has a scaffolding hand over certificate been issued?
-
Are formal weekly scaffolding inspections being carried out and records held on site?
-
Has a documented formal rescue plan been produced, held on site?
-
PASMA Towers - Has the mobile tower been installed correctly by a PASMA trained person?
-
Are the wheels locked on the mobile tower?
-
Is a tag attached to the tower identifying the date it was erected and the dates of the weekly inspections?
-
If using MEWPS / Scissor Lifts / Mobile Powered Access equipment has a suitable exclusion zone been implemented?
-
Is the MEWP within it's six monthly Thorough Examination?
-
Are users of MEWPS trained? (IPAF certificate?
-
If applicable are formal harness / lanyard inspection records available?
-
If working at height near overhead cranes etc have these been isolated (lock out/tag out)?
Personal Protective Equipment
-
Are contractors wearing the correct PPE for the tasks being undertaken? (Safety footwear; Impact Glasses; Gloves; Hard Hat; Hi-Viz; Hearing Protection; RPE Mask)
-
Persons using RPE (masks) have been fit tested?
Task Specific Inspection Checklist
Site permits in place and operational
-
Confined Space
-
Permit To Dig
-
Working at Height
-
Hot Works
-
Isolation Permit
-
Electrical Permit
-
DSEAR
Excavations
-
CAT & Genny scans completed using calibrated eqt (Ground Penetrating Radar on larger jobs/areas)
-
Soil, spoil, vehicles, plant and storage away from sides of excavation
-
Excavation battered back / stepped
-
Trench box / Shoring
-
Suitable access and egress
-
Fall arrest & rescue arrangements if significant depth
-
Arrangements for casualty evacuation
-
Excavation daily inspection
-
Signage / Barriers (edge protection)
Task Specific Inspection Checklist
Confined Space Entry
-
Permit to enter open, safety equipment operational
-
Harnesses, tripods, winches, gas monitors tagged and in date
-
Adequate Rescue Plan
-
Tripod & Winch LOLER certification
Traffic Management
-
Traffic / Pedestrian Plan if required
-
Pedestrian routes clearly demarcated including crossing points
-
Movement of plant controlled
-
Banksman appointed
Access & Egress
-
Adequate Lighting
-
General access and egress sufficient
-
Access stairways suitable and unobstructed
-
Protection of the public commensurate with location and risk
-
Overhead Obstructions – Power cables (Safe systems to GS6 standard implemented)
Lifting Operations
-
Lifting Plan
-
Signaller / Slinger Appointed / banksman
-
Lifting equipment LOLER certificated
-
For mobile cranes we are using a CPA Contracted Lift unless Stonbury has supplied an Appointed Person
Demolition
-
Demo Plan
-
Asbestos Refurbishment & Demolition Survey undertaken and acted upon
-
Temporary Works - Ensure stability of structure(s)
-
Disconnection of services Isolations in place and permits issued
Environmental Controls
-
Waste Carriers Licence available for vehicles carrying waste
-
Waste Transfer/ Consignment Notes available for vehicles carrying waste
-
Noise / Dust / Vibration / Contamination controls
Completion
-