Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Audit Details
-
Site/Job
-
Date & Time
1.0 PREVIOUS INSPECTION
-
1.1 Has the last Inspection / Audit been reviewed?
-
1.2 Are there any outstanding issues or actions from the last Audit
-
1.3 What is the current area of works?
2.0 GENERAL HEALTH AND SAFETY
-
2.1 Have operatives been signing in and out?
-
2.2 Are all scaff tags in date and handover on site?
-
2.3 Safety netting in date and handover on site?
-
2.4 Are all groundworks safe and accessible?
-
2.5 Is all equipment/mewps in good working order?
-
2.6 How is working relationship with site agent, any issues to report?
3.0 SCOPE OF WORKS / SPECIFICATION / PROGRAM
-
3.1 Are all works being installed to specification requirement's?
-
3.2 Are all drawings on site , electronically and hard copies?
-
3.3 Are there any new variations?
-
3.4 Are there any issues on site that are effecting CRS program, either by us or others?
-
3.5 Current program / dates?
-
3.6 Estimated completion date?
-
3.7 Are there any additional materials needed on site?
4.0 ITP - METAL STRUCTURAL DECK
-
4.1 Is the steel correctly installed and suitable for CRS installation?
-
4.2 Is the cladding installed to manufactures instructions?
-
4.3 Are there any damaged pannels and by who?
-
4.4 Have the decking sheet end laps achieved 50mm minimum bearing onto steel
-
4.5 Is the fixing pattern being followed? 1 fixing into every pitch
-
4.6 Are all stitchers in place to all laps were required?
-
4.7 Are all cuts consistent and straight?
-
4.8 Are the decking sheets perpendicular to structural steel beams?
5.0 ITP - Euroclad elite 5 build up
-
5.1 Have the glavanised tophats been fixed with 4W rivets? 4no. per tophat
-
5.2 Is there a consistent coverage on the acoustic insulation?
-
5.3 Does the VCL layer have taped joints and is it free from tears or punctures?
-
5.4 Have the eurobond brackets got the correct fixings installed to each opposite corner?
-
5.5 Do the centres of the brackets not exceed 1200mm?
-
5.6 Does the centres of the rails meet the maximum of 1800mm?
-
5.7 Is the correct depth of insulation being met (300mm)
-
5.8 Is the insulation consistent in coverage accross the roof area
-
5.9 Have the closure flashings been installed at eaves level to prevent slippage of insulation?
6.0 ITP - Membrane coated valleys
Membrane valley check
-
6.1 Is there consistent insulation packed beneath the valley liners ?
-
6.2 Do the valley liners have fixings on the wings at 500mm ctrs ?
-
6.3 Is there a 3mm gap joint between each end of gutter ?
-
6.4 Are the weld straps installed without creases or over heating ?
-
6.5 Have the laps of welds been probed ?
7.0 ITP - Euroclad elite 5 seam install
-
7.1 Have the halters been installed to the rails at 402mm centres ?
-
7.2 Do the halters align from ridge to eaves ?
-
7.3 Have the seams been lifted correctly with a lifting beam and free of damage ?
-
7.4 Are any loaded seams secured sufficiantly before installation ?
-
7.5 Have the installed seams seated correctly over the halters ?
-
7.6 Have the starter clips and retention bars been installed to secure the first seam correctly ?
-
7.7 Are subsequent seams correctly lapped over the previous seam and halter ?
-
7.8 Are all installed seams zipped together prior to the next seam being installed ?
-
7.9 Are all perimeter profile fillers installed and sealed under the junction flashings ?
8.0 ITP - Flat roof Bauder install
-
8.1 Are ALL rolls of felt and Insulation and general materials stored correctly?
-
8.2 Primers applied correctly
-
8.3 Underlays/vapour layers installed correctly?
-
8.5 Is the Flat roof System being installed correctly with staggered laps and joints per layer?
-
8.5 Are all up-stand details weathered and sealed correctly?
-
8.6 Is the Deck in good condition and where applicable repaired/replaced correctly
-
8.7 Are Rooflights sealed and weathered correctly? If applicable.
-
8.8 Is the Flat Roof finished properly and so the job looks neat and "right"
-
8.9 Is the Building Water tight - NO LEAKS?
6.0 ADDITIONAL NOTES / PICTURES
-
6.1 Additional notes / pictures
7.0 SIGN OFF
-
7.1 CRS Supervisor
-
7.2 CRS Manager
-
7.3 Site Manager