Daily Checklist for Pile Driving
I-5 North Coast Corridor Project -
Prepared by
-
Competent Person?
-
Conducted on
-
Segment:
- Segment 1
- Segment 2
- Segment 3
- Segment 4
- Segment 6
- Segment 7
-
Location Details:
CHECKLIST:
-
Has the Daily Start Card been reviewed with the crew?
-
Is the Work Danger Zone clearly delineated around pile driving operation?
-
Crane is level and soil conditions are good under each out-rigger or track?
-
Crane swing protection radius is up?
-
Power lines, overhead obstructions and utilities (USA) are identified?
-
All fall protection, including what is attached to leads has been inspected?
-
Inspected bolts, guides, welds, rigging on the hammer, primary & follower?
-
An additional visual inspection for cracks has been made?<br>
-
Correct pins in place (8" for 32" leads or 10" for 26" leads)?
-
Daily inspections for support equipment have been completed?
-
A spill kit is on-site, housekeeping complete and obstructions removed?
-
All pinch points have been identified in the Daily Start Card?<br>
-
Holes are covered and uneven ground has been leveled out?
-
Rigging has been inspected and capacity tags are in place and legible?<br>
-
Unused rigging has been properly stored?
-
A fire extinguisher is present and in working order?<br>
-
All vehicles, company and personal, are safely parked?<br>
-
Rebar caps are on pile rebar dowels and extra caps are available?<br>
-
Is hearing protection being utilized?<br>
CORRECTIVE MEASURES:
-
Specify any corrective measures required related to this operation:
Photos
-
Photos of Pile Driving Operation
Photos
-
Description
-
Photo
Sign Off
-
Inspected by
Person
-
Add signature