Title Page
-
Conducted on
-
Prepared by
-
Development Site
-
Development Application Reference
-
Did the person preparing the report inspect the building/premises concerned?
Demolition
-
Does the development application include the demolition of a building?
-
Clause 92(1)(b) requires the consent authority to consider the provisions of AS 2601-1991: The Demolition of Structures in determining a development application that is for the demolition of a building.
-
Does any of the documentation provided reference AS 2601?
-
Is a work plan provided?
-
Has any audit to determine the presence of hazardous substances or conditions in the structure and site been carried out?
-
Notes on demolition work (as required)
-
The rest of this section is not relevant to this development.
Clause 93 - Change of Building Use
-
Is this a development application for a change of building use for an existing building where the applicant does NOT seek the rebuilding, alteration, enlargement or extension of a building?
-
Clause 93(2) of the EP&A Regulation requires consideration of the fire protection and structural capacity of the building.
-
What is the current building class?
-
What is the proposed use?
-
What is the proposed new building class?
Fire protection
-
What fire protection measures are currently present?
-
What fire protection measures are proposed?
-
Which of the following fire safety provisions are required for the proposed use (if any)?
-
Do the plans and specifications adequately demonstrate that the building will comply with the applicable category 1 fire safety provisions?
-
Is there any exemption in force under clause 187 or 188 of the EP&A Regulation 2000?
-
The requirement for compliance with the Category 1 fire safety provisions does not apply to the extent of the exemption (subject to any condiitons to the exemption).
-
Either the applicant should be advised of this requirement and given opportunity to amend the documentation, or a condition placed on the consent that these be compied with prior to any occupaiton certificate being issued.
The former is preferred. -
Is the fire protection of the building appropriate to the new building class?
-
What is required to make the fire protection appropriate to the proposed use?
Structural Capacity
-
Does the documentation certify or otherwise quantify the structural capacity of the building?
-
Can the strucutral capacity of the building be adequately assessed by inspection?
-
Certification of the strucutral adequacy of the building (as proposed to be used) should be required as a condition of consent.
-
Does the structural capacity of the building appear to be appropriate to the propsed use?
-
-
Does this demonstrate that the structural capacity is appropriate to the proposed use of the building?
-
Certification of the strucutral adequacy of the building (as proposed to be used) from a qualified structural engineer should be required as a condition of consent.
-
Consideration of Clause 93 provisions is not required.
Clause 94 - Upgrade of existing buildings
-
Is this a Development application for development involving the rebuilding, alteration, enlargement or extension of an existing building?
-
Clause 94 does not apply to this development.
-
Does the proposed building work, together with any other building work completed or authorised within the previous 3 years, represent more than half the total volume of the building, as it was before any such work was commenced, measured over its roof and external walls?
-
What fire safety measures are contained in the building?
-
What fire safety measures would be required to be provided in the building if it were a new building?
-
Are the existing measures in the building adequate to protect persons using the building and to facilitate their egress from the building, in the event of a fire?
-
Are the existing measures in the building adequate to restrict the spread of fire from the building to other buildings nearby?
-
Would it be appropriate to require the existing building to be brought into total or partial conformity with the Building Code of Australia.
-
Provide details of requirements to be met and reasons for decision.
-
Provide reasons for decision not to require upgrade.
-
Would it be appropriate to require the existing building to be brought into total or partial conformity with the Building Code of Australia.
-
Provide details of requirements to be met and reasons for decision.
-
Provide reasons for decision not to require upgrade.
-
Would it be appropriate to require the existing building to be brought into total or partial conformity with the Building Code of Australia.
-
Provide details of requirements to be met and reasons for decision.
-
Provide reasons for decision not to require upgrade.
Clause 94A - Temporary Structures
-
Is this a development application for the erection of a temporary structure?
-
The provisions of clause 94A do not apply to this development application.
-
What is the proposed use of the structure?
-
If it were a permanent structure, what building class(es) would it be?
-
What fire protection measures or provisions are proposed for the structure?
-
Will the fire protection of the structure be appropriate to its proposed use?
-
What addiitonal/altered fire protection measures would make it appropriate?
-
Will the structural capacity of the structure be appropriate to its proposed use?
-
What additonal/altered measures or informaiton is required to make the structural adequacey appropriate?
-
On what basis has this been assessed?
-
Is the ground (or other surface) on which the structure is to be erected sufficiently firm and level to sustain the structure while in use?<br><br>Note: Either appropriate 3rd party certification or physical inspection will be required to determine this.
-
What is required to make the ground/surface sufficiently firm and level (or demonstrate that it is)?
General matters
-
What class(es) of building are involved in the development?
-
Are there issues regarding fire separation or fire safety that should be raised before the DA is determined?
-
Are there issues regarding disability access and discrimination that should be raised before the DA is determined?
-
Is the development BASIX affected development?
-
Are all the matters required by the BASIX certificate(s) to be shown on the DA plans/specs present?
-
General notes/comments