Dig Wet Weather / Short Dump Options
Short Dump Options / Priority & Enablers
-
Please provide detail of short dump options / priority and enabling tasks for each option (can be provided in the form of Supt. / Coordinator Wet Weather Pack)
-
Dozer Wet Weather Enablers
Wet Weather Preparation (completed by Supervisor PRIOR to rain event)
-
HSEC
-
Are all sumps identified, delineated and protected with adequate bunds?
-
Have high/low walls been remediated?
-
Are there hazards not identified above that require additional controls?
-
ACCESS & RAMPS
-
Is there adequate drainage points installed?
-
Ramps - is cross fall adequate (less than 4%, max 8% with controls?)
-
Is ramp surface adequate for trucks?
-
DUMPS
-
Is there adequate bunding with drainage points installed?
-
Have all low spots been identified and filled?
-
Is the dump built to design with adequate fall for water runoff?
-
DIG FLOOR
-
Is there adequate bunding with drainage points installed?
-
Have all low spots been identified and filled?
-
Is the dig area built to design with adequate fall for water runoff?
-
PLANNED MAINTENANCE OPTIONS
-
Machine - Planned Date - NEW date & time
-
EQUIPMENT FUELLING AND PREPARATION
-
Service trucks fuelled and parked in pit?
-
Graders parked at short dumps / top of ramps?
-
Diggers / dozers / trucks / graders fuelled?
-
Trucks parked and lanes blocked / deactivated with dig units / at applicable dumps when rain starts? (consider 793 at each location)
Wet Weather Operation Checklist (completed by supervisor during wet weather)
-
Normal haul circuits closed off from traffic?
-
Training opportunities identified (i.e. SWIs, operating diggers, dozers)
-
Emergency access maintained for operating - preferably without without driving on haul circuits
-
Only authorized CMWs in pit and driving in centre of road?
-
Dozers complete wet weather enablers - ALL dozers hotseated?
-
Diggers complete wet weather enablers - ALL diggers hotseated?
Wet Weather Recovery Checklist (completed by supervisor after wet weather)
-
Rain stopped
-
Supervisor inspects circuit (confirms access) - supervisor to remain on circuit until at full operation
-
Operators taken to dig units / dozers to complete pre-start inspections
-
AH5 / supervisor collaborate on speed / traction zone areas (based on circuit condition)