Information
-
Document No.
-
Rig No:
-
Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel on site at time of Inspection
***NOTE*** this inspection report is to be considered uncontrolled unless printed out and original signatures of all participants are next to iPad signatures
Before entering site
-
Is a Emergency Evacuation Point sign visible?
-
Are access tracks clear of obstructions?
-
Are vehicles parked within drill site boundaries?
Site Housekeeping
-
Worksite is free from obstructions? (Slips, trips, fall hazards & rubbish)
-
Picture of the Site set up
-
Tools & Equipment is being stored correctly?
-
Walkways & Platforms clean & free of oil, grease & tools?
-
Hazardous wastes are stored separately to general rubbish?
Rig Emissions (dust, water & cutting control)
-
Dust is being adequately suppressed where practical?
-
Water & Cuttings are routed to sumps and are contained within the channels?
-
Sumps are containing all water & cuttings ( no leaks/overflow)
-
Spill kit is on-site and readily accessible?
-
Spill kit is adequately stocked?
Guarding
-
Adequate guarding in place for all rotating engine/drivetrain components, exhausts etc?
-
Adequate rod guarding in place and being used properly?
-
Guard lockouts are fitted and working?
-
Sumps have bunding, barricading or some other form of guarding in place?
Fluid Leaks
-
Are there any obvious fluid leaks from engine, drivetrain or hydraulic system including rod handler?
Fire Fighting Equipment
-
Does the rig have a fire suppression system fitted?
-
Is the system charged and ready for use
-
Details
-
Fire extinguishers in current test & tag
-
Are all portable fire extinguishers firmly secured?
-
Fire extinguisher test tags are fitted and legible?
-
All persons on site have an understanding of how to use all the fire fighting equipment?
First Aid Equipment
-
Are first aid kits easily accessible?
-
Kits are stocked and clean?
-
Are there trained first aiders on site?
"E" Stops
-
"E" Stop(s) have been checked and are all in working condition?
Equipment Tag out & Isolation
-
Do all the isolation/lock-out points have an identification sticker?
-
Are correct procedures being followed when equipment needs to be isolated and/or tagged out?
-
Do the isolation switches work?
Equipment Inspections
-
Daily pre-starts for each vehicle is being conducted as required?
-
Daily pre-starts for the rig is being conducted?
-
Manufacturers recommended inspections are being completed within the correct timeframe? (as per the operators manual)
Servicing of Equipment
-
Rig is being serviced as required?
High Pressure Hoses, Pressure vessels & Relief Valves
-
Do all hoses appear to be structurally sound through a visual inspection?
-
Do all hose fittings appear to be structurally sound through a visual inspection?
-
Do all hose fittings appear to be fitted correctly?
-
Are any of the fittings or hoses showing signs of leakage?
-
Are whipchecks placed on all pressure hoses and a secured correctly?
-
Are pressure vessels registered? (If applicable)
-
Are pressure vessels tested and tests are current?
Winches, Ropes & Rod/Plug threads
-
Main winch rope is free from bird nesting, kinks, frays, twists etc?
-
Wireline rope is free from bird nesting, kinks, frays, twists etc?
-
Haul plug is in good operating condition?
-
Plugs and rods have serviceable threads?
-
Sheaves & Blocks are in good condition?
-
Shackles are rated and in good condition?
Visual Inspection
-
Walkway railings are secure and in a serviceable condition?
-
Walkway steps/rungs have non-slip treads?
-
Walkways have securing pins and are being used?
-
Rod handler is in good operating condition?
-
Foot clamps are operating correctly?
-
Foot clamp jaws are secured correctly?
-
Breakout tool is in good serviceable condition?
-
Slips table is in good operating condition?
-
Stilsons are in good working condition?
-
Visual inspection of the mast; are there any?<br>* cracks, warps, bends or other visual defects?
-
Mast locks are in place and in good condition?
-
Hydraulic jacks are in good condition?
-
Work platforms are secured and free from obstructions?
-
Mandatory, Caution, Prohibition, Danger, Fire, First Aid, Traffic, HAZCHEM signage is present, visible and legible at all required locations?
Gauges and Controls
-
All gauges are working?
-
All gauges are easily readable?
-
All controls are in good working order?
-
All controls are easily identifiable?
Power/Hand tools
-
Equipment seems to be in good working order when visually inspected?
-
Tools are stored correctly when not in use?
Documentation
-
Have all workers been inducted & the correct paperwork has been completed for the site?
-
Are all contractors, visitors or client representatives inducted for the site?
-
Are toolbox meetings held as required?
-
Are the company policies, procedures (SWPs), SOP's on-site?
-
Are MSDS documents available for all products on-site?
-
Are MSDS documents current?
-
Are the SLAMs completed by crew members
-
Picture of Slam example...
-
Are all persons on-site aware of where to find all the documentation?
-
Workers are competent in filling out the required paperwork?
Personal Hygiene
-
Fresh, clean and cool drinking water is available?
-
Food is being stored in a hygienic manner?
-
Hand cleaning products are available?
-
Waste food products are being disposed of in the correct manner?
Personal Protective Equipment (PPE)
-
Site has adequate supplies of company issued PPE?
-
Is further PPE required to ensure safety on this site?
-
Workers are using the supplied PPE?
-
When not in use, is PPE being stored correctly?
-
Disposable PPE is being discarded correctly? (gloves, earplugs, etc in bins)
-
Is UV protection being used? (hats, sunscreen, long sleeve shirt/pants)
Personnel Attitudes
-
All personnel on-site are displaying a positive attitude towards Health, Safety & Environmental protocols?
Comments
Client/Geologist Representative comments:
-
Add comments:
- yes
- no
-
Comments:
-
Name & Sign
-
Name & Sign
Company HSE Safety Advisor comments:
-
Add comments:
- yes
- no
-
Comments:
-
Name & Sign
-
Name & Sign
Actions
Issues Raised
-
Issues raised that need actioning:
Issue:
-
Issue status:
-
Assigned to:
-
Completion date:
-
Issue has been closed out appropriately:
-
Time and date action closed out
-
ID of person closing out action