Title Page
-
Conducted on
-
Prepared by
-
Location
-
Project Number
Safety Audit
-
Safety/HR posters or binders on site
-
SDS binders on site or readily available
-
Pre-Task forms being completed daily
-
JHA's being completed as necessary
-
Toolbox talks being reviewed
-
Duro employees new to project have been through site-specific orientation
-
First Aid Kits are available and stocked
General Safety
-
General Housekeeping
-
Access and egress points clear of debris and marked
-
Isles and hallways free of clutter and debris
-
Material storage areas clean and orderly
-
Access/egress lighting sufficient
-
Task lighting being provided for areas where Duro employees are working
-
Flammable chemicals stored properly
-
Fire extinguishers available and in good condition (inspected monthly)
Personal Protective Equipment
-
All Duro employees wearing PPE as required
-
All Duro PPE is in good condition free from damage or defects
Tools and Equipment
-
All Duro tools in good working order and free from damage or defects
-
All Duro corded power tools have cord in good condition
Material Handling
-
Duro employees following safe and sound lifting practices when carrying or moving materials
-
Materials stacked properly to prevent collapse and damage
-
Mechanical devices available to assist in moving materials (ex. pallet jack, forklift, chain fall, tugger, etc.)
-
Forklifts have been inspected and are free from damage or defects
-
Employees have been trained and are authorized to operate the equipment
-
Duro employees utilizing carts and/or tri-vices to hold and secure materials when cutting
Electrical
-
Extension cords in good condition, no missing ground prongs and damage
-
Temporary lighting adequate and cages/bulbs in place
-
Temporary power devices in good condition
-
LOTO in place and being used properly
-
Employees performing LOTO have been trained and are authorized to perform such work
-
Electrical panels secured and adequately protected
-
Energized Electrical Permit has been completed and safety notified of energized work
-
Electrical rooms are secured and signed
Fall Protection
-
Fall protection equipment available to Duro employees
-
Fall protection equipment in good condition free from damage or defects
-
Fall protection systems available for falls 6' or more
-
Fall protection harnesses and lanyards/yo-yo's being used properly
-
Anchor devices installed properly
-
Guard rails installed properly (42" top rail +/- 3", mid-rail and toe boards)
-
Horizontal lifelines installed properly
Scaffold/Stairs/Ladders
-
Scaffold has been inspected by a competent person (for the day being used)
-
Scaffold in good condition free from damage or defects
-
Stairs are accessible and free of clutter or debris
-
Stair pans are filled and safe for use
-
Duro ladders are available for use and adequate for work being performed
-
Duro ladders have been inspected and are free from damage or defects
Heavy Equipment
-
Scissor Lift have been inspected and free from damage or defects
-
Duro employees have been trained and are authorized to use the scissor lift
Trenching/Excavations
-
Competent Person on site
-
Safety notified of excavation work
-
Soil classification determined and protective system provided (for trenches/excavations greater than 5' in depth)
-
Access/egress (ladder) provided for trenches/excavations greater than 4' in depth
-
Spoil piles and equipment set at least 2' back from edge of excavation
Cranes/Rigging
-
Crane Pick Plan completed and safety notified of pick
-
Duro employees trained and qualified for rigging
-
Duro employees trained and qualified for signaling crane
-
Review of crane pick discussed with crane company and crew performing work
-
Rigging equipment inspected and free from damage or defects
Other Safety Concerns
-
Additional Safety Hazards
-
Additional Safety Hazards
-
Additional Safety Hazards
Summary/Follow-Up
-
Any action items following this audit?
-
List/describe action item(s) and person responsible for addressing
-
Signature