Title Page
-
Document No.
-
Edgewater HSEQ Audit
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Safe system of work
Safe system of work
-
Construction Phase Health & Safety Plan produced and available on site?
-
Statutory notices displayed NI10 / F10 / AF2
-
Law poster displayed with name and phone numbers displayed. (Not required in Ireland - to be replaced with a safety poster)
-
Method statements and risk assessments in place for Edgewater works on site?
-
Method statements, risk assessments and competency records in place for sub-contractor works on site? RAMS must be reviewed using RAMS Review Checklist and logged on RAMS register.
-
Induction records in place for all operatives on site? As part of the audit a sample will take place to confirm compliance.
-
Asbestos survey / register on site along with a copy of the site managers Asbestos Awareness training cert?
Health & Safety Management
Health & Safety Management
-
Health and Safety policy statement in site file and in date?
-
Edgewater insurance on file?
-
Time sheets completed for the project?
-
Daily safety briefings completed with all personnel? Both sides must be completed.
-
Plant & Equipment certificates in place along with weekly inspections?<br>(e.g: FLT / MEWP / Tipping Skips)
-
Table saw RAMS in place, signed, weekly checks taking place. Photo of table saw to be included. (Must be mounted on a stand, push stick / Riving knife / guard / fence must all be in place and in good condition)
-
Evidence that portable appliance testing has been completed for tools and equipment on the project?
-
Work at height controlled? Adequate access equipment suitable for environment / trained operators (PASMA / iPAF) / permit to work / inspections.
-
Hot works controlled? Combustibles removed or covered / fire extinguisher in place / PPE in use / permit issued.
-
H&S Toolbox talks being completed? Note: minimum of 1 relevant toolbox talk per fortnight required.
-
Accident investigation records (if applicable?)
-
Accident illness monitor completed for previous month and emailed to H&S dept. Copy to be retained in site file.
-
Site management weekly inspection records completed and evidence available on request during audit inspection?
-
Vehicle management record completed for Edgewater vehicle on site?
-
Site rules on file / displayed?
-
Training records available for operatives on site to include Safepass, CSR, CSCS, PASMA, PAL etc
-
Welfare facilities compliant with the project requirements?
-
Full list of Tools and equipment on site?
-
Site diary either hard copy or electronic being completed?
Environmental Management
Environmental Management
-
Environmental site rules on file?
-
CoSHH risk assessments and MSDS on file. Subcontractors to be checked, e.g Painters (paint / filler etc)
-
Site Waste Management plan on file?
-
Skip dockets on file?
-
Environmental toolbox talk completed? E.g waste management
-
Noise pollution?
-
Light pollution?
-
Dust managed? (Hoovering over brushing, dust extraction connected to saws etc)
-
Skip secured to prevent unauthorised access / waste blowing out?
Quality Management
Quality Management
-
Project Drawings & drawing register available?
-
Delivery dockets available and signed?
-
Certificates in place for completed works? (gas, fire, concrete etc)
-
Quality check sheets completed for relevant areas / completed phases?
-
Actions closed from last H&S visit?
Site Conditions
Site Conditions
-
Access & egress controlled?
-
7' x 4' Site Entrance Information board displayed?
-
Sign in book mounted on site entrance information board and in use?
-
First aid kit & eye wash station mounted on site entrance information board? (Including a trained 1st Aider and weekend cover)
-
PPE - does it follow the RAMS? Note: Protective footwear is mandatory on ALL sites at all times by ALL trades.
-
Site security / fencing sufficient?
-
Fire plan displayed showing escape routes and muster point?
-
Fire exits marked, unobstructed and adequately lit?
-
Fire extinguishers in place, clean, unobstructed & serviced? (Sample to be checked to confirm service)
-
Fire alarm - means of raising the alarm in place and agreed with all parties if working in a live environment?
-
Adequate Lighting?
-
Housekeeping (cable management, waste, clear walkways)
-
Site compound maintained?
-
Parking / Delivery area identified / sufficient?
-
Company branding (Signage, hoarding, Polo shirts, high viz vests etc)
-
Suitable designated smoking area?
Audit acceptance
-
Site Manager
-
Select date
-
Auditor
-
Select date