Information
-
Document No. REV Aug102023
-
EnergyCo HTP compliance observation
-
HTP REZ Site:
-
Conducted on
-
Prepared by:
-
Location
-
Select date
undefined
General Pre-Commencement
-
Site access controlled. Pre-start conducted for inspection team, visitor or sign on's etc
-
Verify work activity is documented correctly on WAP, WAPRA, site plan/s, daily pre start work briefing, SWMS etc.
-
Pedestrian / traffic protection is adequate for activities undertaken.(fencing, barricading, traffic control) under the Pedestrian /Traffic management plan documented for the work being conducted)
-
Confirm all workers have been inducted and signed on to worksite briefings / pre-starts. (Check controls are applied).
-
Check PPE is worn and adequate for current activities. Complies with HTP requirements.
-
Check work permits and approvals are in place, Ensure all appropriate personnel have signed on and understand the procedures.
-
Check council permit for metered water supply standpipe connection permit or written approval from private landholder for dam where applicable. Have they completed a log recording volume of water taken
Working on or over water
-
Does the work crew have adequate PFD's
-
Do they have an effective rescue and emergency response plan
-
Has there been an assessment of weather conditions as part of the prestart
Working at heights
-
Fall risks of 2m or more(including voids, pits & trenches)
-
Check if there’s sufficient edge protection
Plant & Equipment
-
Are all interlock working on Drill rigs
-
Check Certificates of Competency, correct qualifications to carry out the work in relation to the scope of works. (Safe Approach etc)
-
Pre-starts conducted on plant, exclusion zones established, Permits in place etc
-
Check if plant is compliant with project requirements. (Quackers, flashing beacon, SWL, fire extinguishers, guarding, quick hitch, log books, servicing & maintenance regime.
Scaffolding
-
Scaff tag in place and checked monthly, Licensed persons erecting scaffold above 4m
-
Scaffold components compatable (no mix & match) and suitably placed base plates (no undermining etc)
-
Check if all components are in place as per manufactures instructions and COP/AS for erection ( handrails- top, mid and toe boards, braces, tie-backs, base plates etc.)
-
SWL not exceeded (duty - used for access or work platforms), clear of materials.
Lifting Equipment
-
Loads lifted over persons, close proximity to obstacles including OHW and other services.
-
SWL information displayed, meets Australian standards.
-
Licensed VOC'd operators including Dog- man.
Harness & Equipment
-
Formal training for operators, Height Safety and Rescue approved qualifications
-
Certified anchor points being utilised
-
Work at Height Permit to work in place
-
Incompatible equipment / hooks, inspection protocol for equipment, damaged or unsafe equipment
Ladders
-
Unsafe or damaged ladders, unsafe positioning, ladders not secured properly, appropriate ladders for the task.
Hazardous Manual Tasks
-
Identification of hazardous manual tasks, risk assessment and adequate risk controls(no job rotation, trolleys, lifting equipment)
-
Training in Manual Handling, risk controls, safe lifting / team lifting techniques.
Hazardous Chemicals (including fuel & oil)
-
Suitable storage location (flammables near ignition sources, spills, near stormwater drains or water ways, etc)
-
Chemicals stored near each other are compatable (seperation of incompatable chemicals)
-
Adequate spill containment equipment or bunds.
-
Safety Data sheets accessible on site
-
Emergency procedures for injury/spills/fire etc.
-
No Excessive quantities stored on site or in vehicles, adequate bunds in place.
-
If enclosed sufficient ventilation, PPE available etc.
Emergency Response
-
Emergency plans for specific site developed and relevant
-
Emergency procedures displayed at site or noted / briefed at pre-starts.
-
Training & rehearsal of emergency plans/ evacuation conducted within last 6mths
-
Adequate first aid equipment on site / trained nominated first aiders on site.
Traffic Management
-
Adequate traffic management Plan (TMP) in place (pedestrians protected)
-
Adequate communication of TMP for all persons on site (contractors, visitors etc.)
-
Adequate controls for TMP ( physical barriers, bollards, speed limits, flashing lights, spotters)
Personal Protective Equipment (PPE)
-
PPE in use as per SWMS & HTP Stakeholder requirements/tasks etc.(including sun protection)
Work Environment
-
Adequate amenities( toilets, wash areas, lunch rooms etc)
-
Sufficient lighting, housekeeping etc.
Electrical Hazards
-
240V plant - leads, tools etc (damaged lead, tested tagged in date)
-
Quarantine area for damaged, Out Of Service equipment / plant
-
Leads placed on ground, work surfaces or on metal structures (Lead stands/ isolating hooks).
-
RCD protection or overloading outlets
-
Electrical leads/equipment near water, flammables, chemicals or that may be damaged from contact with moving machinery or plant.
-
Plant Close proximity to OHW or underground assets.(SADS known)
-
Machinery Lack of lock-out /tag-out (LOTO) procedures for electrical equipment.
General Hazards
-
Surrounding Streets to site are kept clear of parked up trucks vehicles etc
-
Dust suppression and PPE utilised where appropriate
-
Adequate systems to prevent site run off / mud etc entering stormwater, waterways or exiting site onto roads etc. (wheel wash / sed controls)
-
Site Perimeter secure & professional (no graffiti, shadeclothe etc)
-
Air monitoring if required ( ACM removal, Dust etc)
Administrative Procedures
-
Adequate Site Safety Plans( demolition plan, Asbestos control & removal plan etc)
-
Appropriate work permits ( council, EPA- minor works, RMS, hot works, confined space etc)
-
Adequate induction & consultative arrangements( pre-starts, start cards etc) with workers, contractors, visitors etc.
-
Adequate training in SWMS for planned activities (High risk works) for all workers, contractors on site and appropriate review of SWMS as needed.
-
Adequate supervisory arrangements, training, skills, experience and licenses.
-
Adequate routine monitoring of activities, site inspections and audits.
-
Adequate incident notification procedures / processes as per HTP requirements.
Demolition
-
Adequate plans in place, WorkSafe notification, licensed operator etc.
Unexpected Finds (ACM) Management
-
Appropriate plans (removal & control) in place. Qualified workers. Clearance certficates.
Maintenance
-
Maintenance plan in place addressing - SWI, Frequency,Access,Load shifting & Manual Handling
Corrective Actions
-
List corrective actions
-
Add media
Site Positives
-
List what the site is doing well
-
Add media
Attendees to sign
-
Add signature
-
Add signature
-
Add signature
-