Title Page
-
Client
-
Contractor
-
Conducted on
-
Prepared by
-
Location
-
Contractors Onsite (Name and Count)
-
Personnel Count (Total Onsite)
General Work Activities
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Worker(s) with proper PPE for activities
-
Plan to protect workers from recognized hazards
-
Worker trained for proper equipment use
-
Fall protection plan <br>
-
Qualified Equipment Operators
-
Workers using fall protection as needed
-
No unauthorized modifications of equipment
-
Equipment in use inspected, maintained, and used as required
-
No visible damage to equipment
-
Permit issued and posted in immediate work area as needed
-
Work area cleared and unobstructed
-
Trip/slip hazards controlled
-
Proper use of equipment as intended
-
Clearance from surrounding hazards maintained
-
Environmental hazards identified and controlled
-
Tool guards and safety features provided and maintained on all tools
-
Fire prevention and suppression provided
-
Adequate lighting provided for task
-
Construction waste properly controlled and disposed of
-
Measures provided to protect others in work area
-
Work area properly secured from unauthorized access
-
Proper containers for storage and handling of materials
-
Traffic Control devices
-
Public Fairways
-
Issues not currently identified in this section
-
Summary of Issues if needed
Confined Space
-
If observed check box (If not checked then it is N/A)
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Supervisor present during activities
-
Qualified equipment operators
-
Worker(s) with proper PPE for activities
-
Fall protection plan <br>
-
Workers using fall protection as required
-
Equipment in use inspected, maintained, and used as required
-
Type of confined space determined <br>
-
Permit space plan developed and communicated
-
Permit issued as needed
-
Air quality tested and continuously monitored
-
Alarms and warning devices functioning properly
-
All present hazards isolated or controlled
-
Illumination or work area provided
-
Ventilation provided
-
Warning/information and signage posted
-
Stand by worker trained and equipped for task
-
Entry worker(s) trained and equipped for task
-
Respiratory protection provided as needed
-
Portable equipment grounded and insulated as required
-
Work area controlled for access
-
Access/egress provided
-
Clearance from surrounding hazards manitained
-
Emergency plan provided
-
Emergency equipment provided
-
Means of communication provided
-
Issues not currently identified in this section
-
Summary of Issues if needed
Cranes and Hoisting Equipment
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Qualified Equipment Operators
-
Fall protection plan <br>
-
Workers using fall protection as required
-
Equipment in use, inspected, maintained, and used as required.
-
Worker(s) with proper PPE for activities
-
No visible damage to equipment
-
Annual inspection completed and documented
-
Daily inspections completed and documented
-
Labels and load chart in place and legible
-
Safety features of equipment operational and in use
-
Operator Manual provided
-
Alarms and Warning Devices functioning
-
No unapproved modifications of equipment
-
Additional ground support pads provided as required
-
Ground level, stable, unobstructed and able to support load
-
Anti Two block device provided and operational
-
Pathway of travel level, stable, unobstructed, and able to support intended load
-
Tag lines used on all lifts
-
Area below lift secured or overhead protection provided
-
Clearance of surronding hazards maintained
-
Swing Radius Barricaded
-
Means of overhead lift warning provided
-
Qualified Riggers identified and documented
-
Rigging Equipment inspected, tagged, maintained, and used properly
-
Base of tower crane secured from unauthorized access
-
Emergency shut down provided
-
Material layout and lift sequence controlled
-
Multiple (christmas tree) lifts are not being performed
-
Critical lift plan developed and communicated as needed
-
Summary of Issues if needed
Electrical
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Fall protection plan <br>
-
Workers using fall protection as needed
-
Workers trained for proper equipment use
-
Worker(s) with proper PPE for activities
-
Qualified equipment operators provided as needed
-
Labels in place and legible
-
No unauthorized modifications of equipment
-
Equipment in use, inspected, maintained, and used as required.
-
No visible damage to equipment
-
Permits issued and posted in the immediate work area as needed
-
Work area clear and unobstructed
-
Proper use of equipment as intended
-
Clearance from surrounding hazards maintained
-
Trip/slip hazards controlled
-
Electrical cord condition. Proper size for load?
-
Temporary panels installed and maintained.
-
Energized panels labeled, secured and controlled.
-
No storage in or around panels
-
Fire prevention and suppression provided
-
GFCI in use as required
-
Proper grounding of equipment
-
Lightening protection provided as required
-
High Voltage proximity plan
-
Lockout / Tagout procedures provided
-
Temporary lights installed and maintained
-
Engergized switches, receptacles, and outlets covered
-
Enclosures secured from unauthorized access
-
Portable tools grounded and insulated
-
Issues not currently identified in this section
-
Summary of Issues if needed
Excavation
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Competent person identified and documented
-
Competent person conducts duties as required
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Competent person present during activies
-
Worker(s) with proper PPE for activities
-
Fall protection plan <br>
-
Workers using fall protection as needed
-
Equipment in use, inspected, maintained, and used as required.
-
Qualified equipment operators provided as needed
-
Trench plan developed and communicated
-
Soil classification determined
-
Surface encumbrances removed or supported
-
Permits issued as needed
-
Excavation support system (shoring/benching) provided
-
Spoils, materials, equipment located appropriate distance from excavation
-
All present hazards isolated or controlled
-
Barriers provided and maintained around open sides
-
Walkway, bridging, or plates provided as needed
-
Soft barricades offset minimum 6 feet
-
Overhead protection provided for workers in excavation
-
Plan in place when location of underground installations not known
-
Underground installations protected, supported, or removed
-
Utilities/underground installations located prior to excavating
-
Clearance from surrounding hazards maintained
-
Proper access/egress provided
-
Accumulation of water controlled
-
Emergency equipment provided
-
Air quality tested/monitored as needed
-
Backfill of excavation conducted promptly
-
Emergency plan provided
-
Issues not currently identified in this section
-
Summary of Issues if needed
Fall Protection
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Competent person identified and documented
-
Competent person present during activies
-
Competent person conducts duties as required
-
JHA in place and reviewed with crew <br>
-
Workers trained for task
-
Worker(s) with proper PPE for activities
-
Qualified equipment operators provided as needed
-
Workers using fall protection as needed
-
Equipment in use, inspected, maintained, and used as required.
-
Appropriate anchorage for system
-
Anchorage points positioned above workers
-
Workers protection provided at all times
-
Fall protection plan <br>
-
Lifelines protected from damage
-
Fall protection system designed and approved by qualified person
-
Illustration of designed system provided
-
Appropriate lifelines provided as needed
-
Number of workers utilizing systems as desined
-
No visible damage of fall protection system
-
No excessive slack in system
-
All system components compatible
-
Labels in place and legible
-
Fall protection equipment properly worn
-
Fall protection system in use does not allow for pendulum swing
-
Clearance from surrounding hazards maintained
-
Systems installed as designed
-
Guardrails free of snag, puncture, or laceration hazards
-
Soft barricade/warning line offset minimum 6 feet
-
Cable guardrails installed properly and identified as required
-
Overhead protection provided as needed
-
Emergency plan provided
-
Guardrails systems properly installed and maintained
-
Impalement protection provided as required
-
Issues not currently identified in this section
-
Emergency equipment provided
-
Summary of Issues if needed
Fire Prevention & Suppression
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Equipment in use, inspected, maintained, and used as required.
-
No unapproved modifications of equipment
-
No visible damage to equipment
-
Permits issued and posted in the immediate work area as needed
-
Worker(s) with proper PPE for activities
-
Fire prevention/suppression plan provided
-
Clearance from surrounding hazards maintained
-
Site maintained to allow emergency response as needed
-
Fire extinguishers provided and maintained as required
-
Combustible/flammable materials in quantities for immediate use
-
Standpipe charged as construction progresses
-
Water supply provided, maintained and accessible for emergency use
-
Smoking areas designated
-
Gas cylinders stored and secured properly
-
Waste containers provided and maintained
-
Issues not currently identified in this section
-
Summary of Issues if needed
Ground supported Scaffold installation / use
-
If observed check box (If not checked then it is N/A)
-
Competent person identified and documented
-
Competent person present during activies
-
Supervisor present during activities
-
Workers trained for task
-
Qualified equipment operators provided as needed
-
JHA in place and reviewed with crew <br>
-
Fall protection plan <br>
-
Worker(s) with proper PPE for activities
-
Workers using fall protection as needed
-
Tag on scaffold indicating current status in place at access points
-
Proper base (base plate, rollers, sill plates) provided
-
Equipment in use, inspected, maintained, and used as required.
-
No visible damage to scaffold components
-
Ground support appears level stable, unobstructed, and able to support intended load
-
Scaffold secured from movement
-
Structural Components in place and secure
-
All work levels completely decked
-
Scaffold capacity documented
-
Guardrails and toe boards installed
-
Scaffold does not appear to be overloaded
-
Access ladders provided at each level
-
No apparent fall exposures from gaps or openings
-
Work platform does not appear to be in excess of 8" from work face
-
Materials not stacked above height of toe boards
-
Rolling scaffold locked from movement during use
-
Overhead protection provided as required
-
Pathway of rolling scaffold level, clear, unobstructed, and able to support intended load
-
Scaffold inspected and Green Tag provided once completed
-
Rolling scaffold not occupied during movement
-
Issue not currently identified in this section
-
Summary of Issues if needed
Housekeeping
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Worker(s) with proper PPE for activities
-
Plan to protect workers from recognized hazards
-
Worker trained for proper equipment use
-
Equipment in use, inspected, maintained, and used as required.
-
JHA in place and reviewed with crew <br>
-
No unauthorized modification of equipment
-
No visible damage to equipment
-
Qualified operators provided as needed
-
Workers trained for task
-
Trip/slip hazards controlled
-
Work area cleared and unobstructed
-
Clearance from surrounding hazards maintained
-
Signs posted to warn of hazards
-
Floor penetrations covered, secured, and identified
-
Adequate lighting provided in all areas
-
Construction waste properly controlled and disposed of
-
Anti-slip flooring provided as needed
-
Aisle unobstructed and clearly marked
-
Exit signs posted and maintained as needed
-
Spills, leaks, and water accumulation cleaned properly
-
Waste containers provided and maintained
-
Proper containers for storage and handling of materials
-
Storage areas maintained and accessible
-
Materials stacked and stored properly
-
Round stock managed properly
-
Powder shots managed properly
-
All access/egress points maintained and unobstructed
-
Dust control measures provided
-
Pathway to emergency equipment maintained and unobstructed
-
Barricades and/or signage poseted as required
-
Steps/ramps provided at walkways w/ 19" elevation changes
-
Areas outside of building(s) free of weeds, debris, and trash
-
Issues not currently identified in this section
-
Summary of Issues if needed
Ladder Usage
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Competent person identified and documented
-
Workers trained for task
-
Workers trained for proper ladder usage
-
JHA in place and reviewed with crew <br>
-
Worker(s) with proper PPE for activities
-
Fall protection plan <br>
-
Workers using fall protection as needed
-
Equipment in use, inspected, maintained, and used as required.
-
Labels provided and legible
-
No visible damage to equipment
-
Permits issued and posted in the immediate work area as needed
-
No unauthorized modification of equipment
-
Work area cleared and unobstructed
-
Ladder properly positioned and secured from movement
-
Proper use of equipment as intended
-
No metal ladder in use
-
Clearance from surrounding hazards manitained
-
Proper ladder in use for task
-
Workers maintaining proper positioning on ladder
-
Ladder support appears level, stable, unobstructed, and able to support intended load
-
Approach path to access ladder guarded
-
Proper extension of access ladder to work platform
-
Hoist rope provided at all access ladder
-
Issues not currently identified in this section
-
Minimum of two (2) independent means of access/egress provided from each work level
-
Summary of Issues if needed
Motorized Equipment
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
Qualified operators identified and documented
-
JHA in place and reviewed with crew <br>
-
Worker(s) with proper PPE for activities
-
Equipment in use, inspected, maintained, and used as required.
-
Labels in place and legible
-
No unapproved modifications of equipment
-
Alarms/warning devices functioning properly
-
No visible damage to equipment
-
Operators manual provided
-
Proper use of safety features by operator
-
Proper use of equipment as intended
-
Operator remains in control of equipment at all times
-
Trained flagman/Spotter provided as needed
-
Travel path or base appears level, level, stable, unobstructed, and able to support intended load
-
Clearance from surrounding hazards maintained
-
Permit issued and maintained as needed
-
Whip checks provided at all connections on compressed air hoses
-
All safety features on equipment functioning
-
Issues not currently identified in this section
-
Summary of Issues if needed
Project oversight
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Project Safety coordinator and/or Project Safety assistant(s) present during work activities
-
Project safety management plan for current conditions
-
Plan(s)to protect workers from recognized hazards
-
Persons responsible for safety document maintenance
-
Emergency action plan maintained for current conditions
-
Means to ensure supervision present for all tiered contractors during work
-
Means to ensure that equipment in use inspected, maintained, and used as required
-
Means to ensure all workers are orientated and badges issued prior to work start
-
Means to ensure daily development and submission of JHAs
-
Means to communicate/re-enforce disciplinary policy
-
Current chemical inventory and appropriate SDS
-
Site specific safety plan for each tiered contractor
-
Competent person(s) documentation for all tiered contractors
-
Subcontractor safety representative (SSR) identified for each contractor
-
Return to work Policies for all tiered contractors
-
Project safety meeting(s) attendance
-
All tiered contractors enrolled/exempted in ROCIP
-
Maintenance of contractor's insurance policies
-
Emergency contact information as needed
-
Contact information for safety representatives and supervision for all tiered contractors
-
Maintenance of minutes for all safety related meetings
-
Equipment operator qualifications
-
Trench safety plans
-
Incident/injury reports
-
Arrangements for medical treatment on site and off
-
Safety related signs and posters posted as required
-
First-aid equipment and supplies provided and maintained
-
Drinking water management
-
Sanitation management
-
Perimeter fencing, gates, and public protection provided and maintained
-
Vehicle paring and traffic management
-
Street, curb, and sidewalk protection
-
Adequate access/egress provided and maintained from all work areas
-
Project visitor entry management
-
Exterior lighting management
-
Issues not currently identified in this section
-
Summary of Issues if needed
Scissor And Aerial Lift Operation
-
If observed check box (If not checked then it is N/A)
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Worker(s) with proper PPE for activities
-
Qualified operators provided as needed
-
Workers using fall protection as needed
-
Fall protection plan <br>
-
Equipment in use, inspected, maintained, and used as required.
-
No visible damage to lift
-
Labels in place and legible
-
Safety features of lift operational and in use
-
Alarms and warning devices functioning properly
-
Operator manual provided
-
Basket and ground controls functioning properly
-
Workers positioned in lift as required by manufacturer
-
No unapproved modifications of equipment
-
Pathway of travel clear and unobstructed
-
Ground support appears level, stable, and able to support intended load
-
Materials in lift secured from falling
-
Area below lift secured or overhead protection provided
-
Clearance from surrounding hazards maintained
-
Materials not stacked above height of toe baords
-
Platform clear of slip/trip hazards
-
Issues not currently identified in this section
-
Summary of Issues if needed
Suspended scaffold
-
If observed check box (If not checked then it is N/A)
-
Competent person identified and documented
-
Competent person present during activies
-
Supervisor present during activities
-
Workers trained for task
-
JHA in place and reviewed with crew <br>
-
Qualified operators provided as needed
-
Worker(s) with proper PPE for activities
-
Fall protection plan <br>
-
Workers using fall protection as needed
-
Equipment in use, inspected, maintained, and used as required.
-
Labels on scaffold and outriggers provided and legible
-
Counterweights installed per manufacture's requirements
-
No visible damage to scaffold components
-
Tie back cables installed and properly anchored
-
Structural components in place and secure
-
Lifelines protected from damage
-
Guardrails and toe boards installed
-
Independent lifelines provided for each worker on scaffold
-
Scaffold does not appear to be overloaded
-
Scaffold capacity documented
-
Proper access provided to scaffold
-
Work platform clear and unobstructed for worker movement
-
No apparent fall exposures from gaps or openings
-
Overhead protection provided as required
-
Material not stacked above height of toe board
-
No additional work being performed below suspended scaffold
-
Scaffold insepcted and green tag provided at outrigger and scaffold platform once complete
-
Issues not currently identified in this section
-
Means to secure scaffold from movement after work hours
-
Summary of Issues if needed
Welding & Cutting Operations
-
If observed check box (If not checked then it is N/A)
-
Qualified operators identified and documented as needed
-
Supervisor present during activities
-
Workers trained for task
-
Fall protection plan <br>
-
Workers using fall protection as needed
-
Worker(s) with proper PPE for activities
-
Equipment in use, inspected, maintained, and used as required.
-
JHA in place and reviewed with crew <br>
-
Labels provided and legible
-
No visible damage to equipment
-
No unauthorized modification of equipment
-
Workers trained for fire prevention and suppression provided
-
Permit issued and posted in immediate work area
-
Portable fire protection provided
-
Gas cylinders properly handled, maintained and stored
-
Flash back arrestors installed at gauges
-
Means to prevent sparks/heat from leaving immediate work area
-
Clearance from surrounding hazards maintained
-
Proper means to ignite cutting torch provided
-
All safety features on equipment installed and functioning
-
Proper eye protection for welding/cutting provided
-
Welding machines properly grounded and insulated
-
Flash screens provided as needed
-
Issues not currently identified in this section
-
Summary of Issues if needed
-
Reviewed with
-
Auditor