Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Area to be energised
Untitled Page
Initial Energisation
-
Company Requesting Power
-
ESSW TBT Issues?
-
Equipment to be made live
-
Purpose for energisation
-
Time and date proposed
-
Duration if not permanent supply
-
Dead Test results issued and reviewed
-
Cable verifications complete
Pre Power Checklist
-
AP appointed
-
Permanent lockable doors installed
-
‘Live Switch Room’ warning notices fitted
-
‘Entry via Permit’ signage fitted to switch room door
-
Switch Room keys in CIL possession
-
Permanent lighting & emergency lighting available
-
Builders work complete
-
Fire stopping around cable & containment complete
-
Is the Switch Room Door Lockable and the key controled by CIlantro AP?
-
Is the Switch Room ESSW Signage in place on the Door
-
Permit system in operation
-
SAT/ FAT of the switch panel
-
Main supply installed
-
Main supply tested
-
Earthing system installed Inc. bonding and lighting protection
-
Earthing system tested Inc. bonding and lighting protection
-
EPO system installed & Tested
-
EPO system operational
-
Main switch locked with tag ‘Open’
-
All output devices locked ‘Closed’
-
All keys secured within key box
-
Protective devices labelled
-
MET labelled
-
Mains & sub main cables labelled
-
Earthing conductors labelled
-
Torque settings confirmed
-
Have all ACB & MCCB protection settings been confirmed?
-
Framed schematic displayed
-
Electrical Regs. poster displayed
-
Fire extinguisher available
-
Insulated matting fitted
-
Rescue hook, Flash visor and suit available?
-
Housekeeping (all plant / materials/ dust removed)
-
Earth pits properly sealed and free of debris and water
-
Sign off
-
Duty Holder
-
Cilantro AP
-
Project Manager