Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
General
-
Posted OSHA & other Jobsite posters
-
Safety program & substance abuse manual
-
First aid supplies immediately available/adequate
-
SDS Manual
-
Federal and State posters
-
First aid/CPR trained personnel on site
-
Daily Take Two Completed
-
Jobsite warning signs posted as necessary
Housekeeping & Sanitation
-
General neatness of working areas & walkways
-
Waste containers provided
-
Adequate lighting
Fire Prevention
-
Required fire extinguishers in equip properly charged and inspected
-
Fire watch/fire tarps used while doing hot work
-
Travel distance within 100' with at least one extinguisher per floor
Electrical Safety
-
GFCI's used on every power tool
-
Proper guards on temporary lights
-
Extension cords have ground pins and no visible damage
-
Terminal boxes equipped with cover
-
All electrical equip grounded, ext cords 3-wire type
-
Lockout/tagout procedures in place
-
Cords routed to prevent safety dangers & damages
Hand Tools
-
Proper tools and operator for the job task
-
Damaged tools repaired or replaced
Power Tools
-
Properly guarded
-
Properly grounded
-
PPE used
-
Proper tool and operator for the job task
-
Damaged tools repaired or replaced
Hoist, Cranes, & Derricks
-
Competent person rigging, using proper rigging
-
Lift areas barricaded & secured
-
Equipment alarms functioning
-
Qualified signal person demonstrating proper signaling practice
-
Outriggers being properly used with adequate blocks
-
Overhead power lines deactivated or marked
-
Rigging in proper working condition
Ladders
-
Ladders free of defects
-
Proper use of step ladders
-
Extension ladders secured 1/4 slope, 3' above landing
Heavy Equipment
-
Lights, brakes, & warning signals operative
Excavation
-
Barricading in place during & after work hours
-
Egress provided within 25 ft
-
Atmospheric testing completed (if required)
-
Utility lines located: soil type identified
-
Proper shoring, benching, sloping at 5' or deeper
-
Materials stored at least 2 feet from edge
Flammable Gasses & Liquid
-
Approved containers used & clearly identified
-
Proper storage / Oxy & acetylene tanks separated
Personal Protective Equipment (PPE)
-
Hard hats
-
Safety glasses/face shields/goggles
-
Hearing protection
-
Safety footwear
-
Respirators
-
Gloves (if needed)
-
Safety harnesses & lanyards (if needed)
-
High visibility clothing
Fall Protection
-
100% tie off above 6 ft & retrieval plan created
-
Proper anchorage points
-
Floor/wall openings covered or guarded
-
Guardrail systems in place & properly installed
-
Roof edge protected
Concrete Construction
-
Forms properly installed & braced
-
Proper PPE in use
-
Rebar capped as necessary
Confined Space
-
Atmospheric testing completed
-
Permit completed & posted
-
On-site rescue provided (if needed)
-
Off-site rescue provided (if needed)
Stairways
-
Handrails on all stairways as needed
-
Stairways blocked if unusable
Scaffolds
-
Scaffold inspections completed
-
No damaged components