Information
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Underground utilities marked/identified before digging?
-
Digging around underground utilities performed with active 1st call dig ticket?
-
Sask 1st Call Dig Ticket
-
Hand digging performed within 2' of marked lines, or hand digging performed until marked utilities identified before machine digging?
-
Excavations, adjacent areas and protective systems inspected by a "competent" person daily prior to the start of work and after each rain?
-
Excavations/trenches over 4' deep proper sloping applied (1-1/2' W to 1' V), or trench box used?
-
If trench boxes are used, is tabulated data on site?
-
Workers working within trench box at all times?
-
Ladders placed within 25' of workers?
-
Spoil banks at least 1m away from edges of cut?
-
Barriers installed protecting unattended and remote excavations/trenches?
-
Warning vests or highly visible clothing worn by workers exposed to traffic?
-
Workers not exposed to overhead suspended loads and maintaining safe distance from vehicles loading/unloading?
-
Audible alarms functioning properly on excavation equipment?
-
Workers wearing appropriate PPE? Ex. Hard hats and safety glasses.
-
Inspection completed by