Title Page
-
Conducted on
-
Site
-
Prepared by
-
Contractor Performing Work
-
CXP Segment Information
-
Page #'s of CXP being worked at this excavation site
-
Location of Work Performed
-
Do you have all CXP prints associated with the excavation area and are they at a suitable scale to be understood? (Approved design drawing for construction, Permitting CXP and GIS data )
-
Contact leadership and do not proceed with any excavation of the area!
-
What known utilities are in the vicinity of the excavation area?
- Blue: Potable Water
- Green: Sewer and Drain Lines
- Purple: Irrigation and Slurry Lines, Reclaimed Water
- Red: Electrical Power Lines, Cables, Conduit and Lighting Cables
- Yellow: Gas, Oil, Steam, Petroleum or Gaseous Materials
- Orange: Communications, Alarm or Signal Lines, Cables or Conduit
- Pink: Temporary Survey Markings
- White: Proposed Excavation
-
Provide 811 ticket number
-
Have all known utilites been located at the excavation site?
-
Contact leadership and do not proceed with any excavation of the area!
-
Provide photos of all locates within the excavation site.
-
Have you identified all areas that need to be pot-holed?
-
What is the current state of the proposed work area?
-
Is the area traffic sensitive?
-
Do you have all of the required signage, cones, flaggers or other equipment for proper traffic mitigation?
-
Contact leadership and do not proceed with any excavation of the area!
-
Were all yard signs and door hangers placed at least 48 hrs prior to excavation?
-
Will the required work cause you to go beyond normal working hours of 8am-5pm
-
Are there any access restrictions?
-
Are there any SED's (Special Engineering Difficulties)?
-
Have all hazards been identified and risk assessed? ( Photo of Risk Assessment)
-
Photo of Risk Assessment required
-
Review risks and implement control measures required - can the works safely continue?
-
Consult with your manager and don't proceed with the works!
-
Photo of Risk assessment.
-
Are there residents to inform of the work?
-
Have they been informed?
-
Are there any Specific requirements from the Primary Contractor?
-
Please specify?
-
Name and Signature of person completing form
-
Management Approval