Information
-
Document No.
-
Audit Title
-
Client
-
Site:
-
Conducted on
-
Time:
-
Location
- Main House Curtilage
- River
- Lake
- Wetland
- Cascades
- Tip Area
- Helipad Field
- Stables Area
- Estate Workers Cottage 1
- Gate 3
- Estate Workers Cottage 2
- Service Yard
- Marquee Area
- Road
-
Define
-
Excavation Description
- Trenching <600mm
- Trenching >600mm
- Bulk Excavation
- Reduce Dig to Formation
- Key or Bench forming
- Cut & Filling
- Formation Trim
- Foundations
- Stockpile
-
Prepared by
-
Personnel in attendance
Inspection Certification
-
Plan Location
-
Excavation Permit Available?
-
Scan/Picture of Permit
-
Excavation Permit Number:
Inspection Purpose
-
Daily required inspection prior to begining
-
Routine inspection during work
-
After storm *rain, snow, etc
-
After hazardous condition
-
Other
-
Please Describe
Current Conditions
-
Terrain
-
Ground Conditions
-
Weather
-
Water accumulation
-
Please define
-
Is Pumping required
-
Traffic conditions
-
Heavy equipment location
-
Heavy materials location
-
Spoils location
-
Building proximity to spoils
-
Possible vibration sources
-
Previously disturbed soil
-
Excavation Type
- Trenching <600mm
- Trenching >600mm
- Bulk Excavation
- Reduce Dig to Formation
- Key or Bench forming
- Cut & Filling
- Formation Trim
- Foundations
- Stockpile
-
Excavation length
-
Excavation width
-
Excavation depth
-
Other trench characteristics
-
Access/egress conditions
-
Toxic or hazardous atmosphere source
-
Other
-
Changing Conditions/change of plan:
Site Survey
-
The excavation is within the original scope of the excavation permit
-
Excavation permit conditions for disposal, shielding, & training are being adhered to
-
Utility survey markings are complete, accurate, & legible
-
Storm drains are adequately protected from sediment
-
Excavated materials are at least 1m from the edge of excavation
-
Shoring equipment is damaged<br>(If yes please describe below)
-
Nature of damage:
Protective Systems
-
Check one of the following
-
No System Required
-
Sheet Pile
-
Trench Box
-
Slope is 1.5:1
-
Slope is __________ based on soil type (Please fill in below)
-
Degree of slope:
-
Stepped Excavation minimum 1m by 1m
-
Stepped Excavation is ___________based on soil type (Please fill in below)
-
Steps formed to:
Soils Analysis/Classification
-
Note: soil does not need to be reclassified every inspection but should be reviewed & updated if conditions change - Describe Soil as found
-
SOIL CLASSIFICATION AND IDENTIFICATION Visual soil classification
- Stable Rock
- Loose, Fragmented, Layered or Shale Rock
- Firm Clays
- Loams, Silty Clays
- Soft Wet Clays
- Gravels
- Sands
- Running Sand
- Hardcore or other buried material
- Granular Sub-bases, Foundations or Surfaces
- Previously Disturbed Ground
- Organic Material or Peat
- Topsoil
Soil Characteristics (check all that apply)
-
Describe Soil Characteristics
- Cemented
- Firm
- Hard
- Soft
- Cohesive
- Layered
- Dry
- Damp
- Wet
- Saturated
- Granular
- Submerged
- Undisturbed
- Disturbed
Soils Analysis Method(s)
-
Visual
-
Manual
Excavation Sign Off
-
Is the Protective System safe and all barriers in place
-
Cease works immediately and make the work area safe as appropriate, prevent any access or further works until appropriate action is agreed
-
Comments:
-
Are there any signs of wall or slope failure, slippage, shearing , trench collapse, water ingress or unstable ground that require attention or change in method
-
Cease works immediately and make the work area safe if appropriate, prevent any access or further works until appropriate action is agreed
-
Comments:
-
Are the Excavations sound and safe for works to continue
-
Signed:
-
Name:
- Barry Pace
- Colin Henley
- Graham Humphries
- Jim Price
- Jamie Ormerod
- Jack O'Leary
- Ton Van Vuuren
-
Date: