Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Underground utilities marked/identified before digging?

  • Digging around assets with close approach tickets

  • Hand digging or pot holing to be performed before and during excavation at all time with a qualified spotter

  • Excavations/trenches over 1m deep must be either "benched" or "stepped" and/or require a "shoring" device

  • Spoil pile must be a minimum of 500mm from the edge of excavation/trenches

  • Temporary fencing must be used when excavation is unattended

  • All workers on site must have correct personal protective equipment "PPE"

  • Workers must be a minimum of 5m from plant equipment at all times

  • Audible alarms functioning properly on excavation equipment?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.