Title Page
-
Project Name
-
Location
-
Inspection Location
-
Date
-
Client
-
Project Manager
-
Prepared By
-
Design brief of sheet piles, trench box / manhole box is in TW file?
-
TW design check certificate of sheet piles is in TW file?
-
Which codes and practice used for design?
-
What category is the TW design?
-
Designer calculation of sheet piles is in TW file?
-
Is TW drawing of excavation support issued for construction?
-
Is the construction drawing recorded in TW register log?
-
Sheet piles, trench box or manhole box were setup as per construction drawing or manufacturer guides and specifications on site?
-
Has barrier been setup around the trench min 1m high and min 1m away from excavation edge to protect against the risk of people, plant, materials or components falling in excavation area?
-
Has safety plan organised (safe access and harness system)?
-
Is permit to dig was issue and signed by TWS?
-
TW inspection checklist daily – Visual Inspected and weekly- written recorded is in TW file?
-
Permit to strike issued before the strike?