Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Quality
-
Have all backfill materials been compacted to the HAUC specifications
-
Have excavated materials been separated to prevent contamination of backfill and for re-use
-
Marker tape/tile place over pipe/cable
-
Suitable blinding material being used
-
Are excavations the correct depth for the work being carried out
-
Has backfill been carried out to NRSWA specification
-
Is reinstatement temporary or permanent
-
Does reinstatement meet NRSWA specification
Cabling
-
Are the subducts labelled with the PIANO number
-
Are Gel Wraps present on duct
-
Are end caps placed on ducts
-
Are gas seals installed correctly
-
Does duct management in chambers meet BT specifications
-
Are cables IDs in place and correct
Splicing
-
Has the OLT been confirmed prior to work commencing
-
Is equipment in good condition and within calibration (splicing machine, cleaver, OTDR, live fibre identifier etc.)?
-
Is work bench adequate for splicing activity?
-
Are joint clamps in good working order
-
Are fibre shards been disposed of correctly in sharps bin
-
Do splitters look in good condition
MDU Build
-
Has catenary wire been installed correctly
-
Are there metal cable clamps every 3m
-
Are there sufficient eye bolts in place, approximately 3m spacings
-
Does the fibre colour match the premises
-
Has a sufficient amount of cable been left to allow install of MDU/SDU
-
Has galvanised boots and capping been installed correctly
-
Have splitter/PBO been installed correctly
Environmental
-
Are vehicles parked away from drains
-
Is dust suppression available/in use
-
Are noise levels acceptable and not causing a nuisance
-
Is the site free of evidence from diesel/substance spills
-
Is plant in good condition with no leaks
-
Is there an unopened spill kit available
-
Is there a CoSHH assessment available for the chemicals on site
-
Are chemicals stored in correctly labelled containers
-
Is the vehicle kept in a clean and tidy condition
Site Management
-
Work instructions and all utility plans
-
Site specific risk assessment completed and signed
-
Does the site meet the highways permit conditions
-
NRSWA, Plant operator, First Aider etc. Check validity
-
Gang pack up to date
-
Do barriers confirm to NRSWA including safety zone
-
Does oncoming traffic know where to go
-
Correct pedestrian walkway around site
-
Sandbags or alternative on signs to prevent them falling
-
Welfare facilities available
-
Cable avoidance tools available and in good order. Check expiry dates and plant number
-
Gas Detection Unit available, in use and within calibration
Health and Safety
-
All correct PPE being worn, is there any signs of damage?
-
Evidence of safe digging being carried out
-
Are excavations safe to work in, is there a requirement for shoring or is shoring adequate
-
Is materials stored safely within barriers
-
Are trench edges clear of excavated spoil
-
Are all vehicles safely and suitably parked
-
Has the drum been set up correctly and winch been positioned safely
-
Is there communication between winch operator and drum
-
Is there a fully stocked first aid kit available
-
Is there eye wash available with a valid date
-
Is there a fire extinguisher available and within service date
-
Are all tools and work equipment in a visually sound conditin
-
Have plant inspections been carried out
-
Have the operatives been trained to operate the plant being used
-
Are certificates and inspections available for lifting equipment
-
Has the last toolbox been issued, ask team for subject
-
Correct manual handling techniques being carried out
-
Are vibration trigger times being completed
-
Are site conditions and working practices free from hazards
-
Comments
-
Auditee