Frame Report Details
-
Site conducted
-
Conducted on
-
Prepared by
-
Framer's Name
Frame QA
-
Bottom plates have less than 10mm overhang.
-
Bottom plates fixed down correctly (1200mm c/c & 70mm in from slab edge)
-
Meter box is in the correct location, plumb and framed out.
-
Internal frame layout as per plans. Mark all openings and noggins for fixtures using spray paint.
-
Ceiling Heights are correct
-
Walls and structural steel plumb (Tolerance is 4mm over 2m).
-
All external wall intersections have been nailed off straight
-
Load point studs laminated correctly (300mm C-C) and supporting girder trusses.
-
Bulkheads and plaster openings installed as per plans, plumb and level
-
Wet area noggins for NCC Accessibility completed (detailed on plans)
-
Soap niche framed out as per plans
-
Stair nib walls are the correct height, plumb, straight and braced accordingly.
-
All plumbing waste and stack points located in correct location
-
All bracing nailed off correctly (check against engineering)
-
L-Brackets installed (max 1800c/c) and not nailed home
-
Shear blocks installed as required.
-
I Beam/Possies installed correctly
-
Joist hanger brackets installed flush to bottom cord
-
Solid beams installed correctly including connections
-
Stair void wall line up plumb and straight (Critical )
-
Manhole trimmers have been installed. Mark location on floor.
-
All truss and change of direction noggins installed & flush with bottom chord
-
Trusses installed correctly, level and plumb (50mm tolerance for plumb Trusses)
-
Windows and sliding doors are installed level/plumb and opening from the correct way
-
External doors flashed correctly (refer detail for any sliding door, timber sill requires DPC)
-
10mm Bulb seal on windows/doors installed to expansion join location on plans
-
Overlooking windows installed as per plans (if not required, select pass)
-
Sumps in box gutters have been framed out correctly (min sump size = width of box gutter x 450mm L x 150D )
-
Parapet walls to finish min 75mm above roof sheet height
-
Parapet walls are plumb
-
Lear gutter boards installed 300mm up the rake of roof
-
Site swept, rubbish placed in cage, material stacked neatly in garage
-
Other items to be rectified