Title Page

  • Conducted on

  • Prepared by

Details

  • Address
  • Date of inspection.

  • Locations

Grid work inspection

  • Have the setting out been carried out as per the GA drawings?

  • Have the correct mullions and transoms installed as per the location drawing?

  • Have the mullions been installed at correct levels and datum heights?

  • Are there any defects or scratches to mullions or transoms?

  • Is the finished paint in accordance with spec and the correct Ral colour?

  • Photos.

Bracketry

  • Have the correct base plates spigot brackets been installed in the right positions?

  • Are there any damages to the brackets?

  • Have the brackets required cutting on site?

  • Have the correct fixings been used as per the detail?

  • Have all the brackets torqued and sprayed?

  • Is the fixings in the factory holes - if not are there enough space in between? Have the drilling holes been treated on site?

  • Did the brackets require shimming?

  • Photos.

EPDM

  • Have the correct membrane been used?

  • Have all the correct adhesives been used?

  • Is the EPDM installed correctly as per the approved drawings?

  • Are there any tears or rips on the membrane? If so have the correct overlapping been applied?

  • Have the correct overlapping been carried out on site? Minimum of 150mm!

  • Is the clamp bar fixed with the correct fixings and paste adhesive?

  • Have the internal VCL done correctly as per the drawing with the correct product?

  • Photos

Internal pressings and backing panels

  • Are all the internal pressings installed as per detail?

  • Are all the backing panels installed as per detail?

  • Are all pressings and panels free from damages?

  • Have the correct fixings been used?

  • Photos

Glazing and gaskets

  • Inside and out

  • Are all the correct gaskets installed?

  • Are all gaskets free from damages?

  • Have the correct sealant been used on the gaskets?

  • Have the correct drain chute been installed?

  • Have the drain chute been sealed in its correct positions 6mm below the thermal break?

  • Have the glass been installed correctly?

  • Is the glass free of scratches?

  • Is the glass free from imperfections?

  • Was the glass installed as per the location drawings?

  • Photos

Cill and head pressings

  • Have the correct cills and head pressings installed?

  • Is the pressings the correct colour?

  • Has the holes been cut for the soffit lights?

  • Have all the pressings been fitted with the correct method and fixings?

  • Photos

Pressure plates and cover caps

  • Are all the pressure plates installed?

  • Have the correct fixings been used?

  • Have the fixings been torqued?

  • Is the cover caps installed?

  • Is the cover caps free from scratches or imperfections?

  • Have all caps been used in the correct locations?

  • Photos

Door inserts

  • Have the correct doors been installed at its location?

  • Is the support bracket Installed with the correct fixings?

  • Are all the fixings torqued?

  • Are doors free from damages or imperfections?

  • Are doors operating correctly?

  • Are the locks and handles fitted and working?

  • Is the glass installed to the door?

  • Is the glass free from scratches or imperfections?

  • Is the glass packed correctly?

  • Are all beads and wedge gaskets installed?

  • Is all keys identified as per plot number and door location?

  • Photos

Signatures

  • Checked on behalf of M Price Ltd

  • Checked on behalf of SGDL (Deemed acceptable if not returned within 2 days)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.