Title Page
-
Conducted on
-
Prepared by
Details
-
Address
-
Date of inspection.
-
Locations
- Level 1
- Level 2
- Level 3
- Level 4
- Level 5
- Level 6
- Ground floor
Grid work inspection
-
Have the setting out been carried out as per the GA drawings?
-
Have the correct mullions and transoms installed as per the location drawing?
-
Have the mullions been installed at correct levels and datum heights?
-
Are there any defects or scratches to mullions or transoms?
-
Is the finished paint in accordance with spec and the correct Ral colour?
-
Photos.
Bracketry
-
Have the correct base plates spigot brackets been installed in the right positions?
-
Are there any damages to the brackets?
-
Have the brackets required cutting on site?
-
Have the correct fixings been used as per the detail?
-
Have all the brackets torqued and sprayed?
-
Is the fixings in the factory holes - if not are there enough space in between? Have the drilling holes been treated on site?
-
Did the brackets require shimming?
-
Photos.
EPDM
-
Have the correct membrane been used?
-
Have all the correct adhesives been used?
-
Is the EPDM installed correctly as per the approved drawings?
-
Are there any tears or rips on the membrane? If so have the correct overlapping been applied?
-
Have the correct overlapping been carried out on site? Minimum of 150mm!
-
Is the clamp bar fixed with the correct fixings and paste adhesive?
-
Have the internal VCL done correctly as per the drawing with the correct product?
-
Photos
Internal pressings and backing panels
-
Are all the internal pressings installed as per detail?
-
Are all the backing panels installed as per detail?
-
Are all pressings and panels free from damages?
-
Have the correct fixings been used?
-
Photos
Glazing and gaskets
-
Inside and out
-
Are all the correct gaskets installed?
-
Are all gaskets free from damages?
-
Have the correct sealant been used on the gaskets?
-
Have the correct drain chute been installed?
-
Have the drain chute been sealed in its correct positions 6mm below the thermal break?
-
Have the glass been installed correctly?
-
Is the glass free of scratches?
-
Is the glass free from imperfections?
-
Was the glass installed as per the location drawings?
-
Photos
Cill and head pressings
-
Have the correct cills and head pressings installed?
-
Is the pressings the correct colour?
-
Has the holes been cut for the soffit lights?
-
Have all the pressings been fitted with the correct method and fixings?
-
Photos
Pressure plates and cover caps
-
Are all the pressure plates installed?
-
Have the correct fixings been used?
-
Have the fixings been torqued?
-
Is the cover caps installed?
-
Is the cover caps free from scratches or imperfections?
-
Have all caps been used in the correct locations?
-
Photos
Door inserts
-
Have the correct doors been installed at its location?
-
Is the support bracket Installed with the correct fixings?
-
Are all the fixings torqued?
-
Are doors free from damages or imperfections?
-
Are doors operating correctly?
-
Are the locks and handles fitted and working?
-
Is the glass installed to the door?
-
Is the glass free from scratches or imperfections?
-
Is the glass packed correctly?
-
Are all beads and wedge gaskets installed?
-
Is all keys identified as per plot number and door location?
-
Photos
Signatures
-
Checked on behalf of M Price Ltd
-
Checked on behalf of SGDL (Deemed acceptable if not returned within 2 days)