Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

1) Applicable modules

  • System Design Module?

Enter Design Certificate number below.

  • Date of Certificate?

  • Installation Module?

Enter Installation Certificate number below.

  • Date of Certificate?

  • Commissioning and Handover (Inc Verification)?

Enter Commissioning Certificate number below.

  • Date of Certificate?

System Design

Specific Standards applied

  • BS5839 Category of system specified

Additional Standards Specified (eg HTM05-03)

General System Design Questions

  • Is the system addressable or non-addressable?

  • Is the category of system appropriate and as specified in the contract?<br>[Annex A]

  • Is the specified standby power supply period suitable for the category of system and the level of supervision? <br>[25.4(e)]

  • Does the system design proposal include all the required information? <br>[8.2]

  • Has the system design taken into account any building regs (eg Part M) or Equality Act requirements? <br>[18]

  • Is any cause/effect on the system documented? (inc single stage/phased evac etc) <br>[40.2(a1)]

  • Are design battery capacity calculations available? <br>[25.4(e) Annex D]

  • Have the correct quiescent and alarm currents been used? <br>[25.4(e) Annex D]

Category M/L- Quiescent at least 24 hours, or 6 hours with auto start generator

Category P- Quiescent at least period of unoccupation + 24 hours up to 72 hours, or at least 24 hours if supervised (every 6 hours) or fault monitoring by ARC

  • Assumptions/variations drawn to customer's attention at design/quotation stage?<br>[7.2(a)]

  • Is the battery capacity, as designed, adequate?<br>[25.4(e) Annex D]

System Design Comments-

Documentation

General Documentation Questions-

  • Are there satisfactory commissioning records?<br>[39.2(c)]

  • Have BS 5839 Certificates for design, installation, commissioning & acceptance been issued? (as applicable)<br>[39.2(c)]

  • Is there a record of agreed variations?<br>[40.2(e)]

  • Have suitable user instructions/manuals been provided to the customer?<br>[40.2(b)]

  • Are there satisfactory "as fitted" drawings?<br>[40.2(c)]

  • Have "as fitted" drawings been provided to the customer?<br>[40.2(c)]

  • Has a logbook been provided to the customer?<br>[40.2(d)]

  • Are insulation test results available and satisfactory? (ELV wiring only)<br>[38.2(a)]

  • Are test results for circuit parameters such as loop continuity available and satisfactory?<br>[38.2(d)]

  • Have 230V supply test records been supplied by the electrical contractor/client?

Documentation Comments-

Installation

General Installation Questions-

  • Are cables of a suitable type?<br>[26.2(b)(d)]

  • Are cables with "enhanced" fire resistance used where required?<br>[26.2(c)(e)]

  • Are cables adequately protected against mechanical damage?<br>[26.2(h)(k)]

  • Are methods of cable support satisfactory?<br>[26.2(f)]

  • Is there suitable segregation from other services and other fire alarm cables, where required?<br>[26.2(l)(m)(n)]

  • Are joints in cables terminated correctly? (applies only to joints external to FA&A system components)<br>[26.2(g)]

  • Are all junction boxes suitably labelled?<br>[26.2(g)]

  • Are all fire alarm cables a single common colour?<br>[26.2(o)]

  • Red Pirelli FP200 is not UV rated. Red Eland cable is UV rated.

Installation Comments-

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.