Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Civil Snag List

Exterior

  • Indira Gandhi graphic to be provided.

  • Outside furniture vertical portion finish is to be done and all panel markings to be removed.

  • Lifting holes in verticals of all tables to be filled.

  • All furniture legs have to be grouted.

  • Grout filling of furniture leg should match to the existing slab level

  • Water tank covers to be installed

  • Floors to be smoothened

  • Grade slab corner chip offs to be rectified.

  • Chip off portion in floor panels to be rectified.

  • Floor sill near entrance chip off to be rectified.

  • Core packing to be done where rain water and plumbing lines were taken (on floor)

  • Backfilling to be done

  • Bathroom cutouts to be covered

  • DB box side finish to be completed.

  • Staircase to be fixed

  • Overhead tank concrete panel to be fixed

  • Waterproofing to be done

Interior

  • Grouting marks on all panels to be removed/covered.

  • Cracks on wall panels to be rectified.

  • Blow holes on wall panels to be rectified.

  • Missing glass in windows to be fixed.

  • Bottom corner chip offs for interior tables to be rectified.

  • Filling to be done between walls and grade slabs

  • Plumbing box packing to be done in toilet area.

  • Bathroom doors to be installed (2 nos)

  • Door handles to be installed

  • Grade slab undulations to be rectified as much as possible

  • Ceiling slab joints to be filled with grout properly from inside

  • Extra rods and hanging hooks to be trimmed off and finished neatly.

MEP Testing

  • Fans working

  • Lights working

  • Handwash taps water running

  • Bathroom leakages

  • Water tank motor running

MEP Snags

  • MEP testing to be done

  • Exhaust fans to be fixed in toilets.

  • All taps to be fixed.

  • Dining area fan cups (top) to be fixed properly.

  • Handwash drainpipe to be packed with grout

  • Toilet spout pipes should be vertical

  • Bathroom tiling completed

  • Electrical second fix to be positioned square

  • All plumbing openings to be neatly finished

  • DB to be weathered correctly

Additional snags (please add)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.