Information
-
Location(s) of high hazard work inspection
-
Conducted on
-
Prepared by:
-
Location
-
Personnel
High Hazard
-
Time audit conducted
-
Track any corrective actions to closure. Identify owners of issues and due date. All issues should be documented with M+W EHS.
Working at Heights and Fall Protection
-
Working at Heights and Fall Protection
-
Are Method Statements / Submittals and Risk Assessments in place approved by M+W?
-
Is 100% Fall Protection in place for all WAH achieved by collective or personal measures
-
Is Collective (passive) fall protection given priority over personal (active) fall protection?
-
Are harness lanyards tied-off to suitable anchorage points with adequate load capacity per person?
-
Are mobile scaffolds or podium steps used in preference to straight, step, A-frame ladders?
-
Are mobile towers & scaffolds safely errected and "safe tagged"?
-
Are access points to work platforms on scaffolds / mobile towers protected by a gate, hinged hatch or trap door?
-
Are scaffolds fitted with a top and mid rail, toeboards and fully boarded? Free from rubbish?
-
Are harnesses with restraint lanyards attached to safe anchorage points within MEWP's?
Excavations
-
Excavations
-
Is an "excavation permit" in place for each excavation?
-
Are approved Method Statements / Submittals and Risk Assessments in place for all excavations?
-
Is edge protection around all excavations adequate to prevent fall by people, machines or material?
-
Are all excavations safely battered, stepped or supported regardless of depth?
-
Is there safe access to and egress from all excavations?
-
Are spoil heaps positioned at a safe distance away from the excavation?
-
Have all excavations been inspected by a Competent Person before person entry?
-
Is the work area well barricaded, protected and marked at day? Fenced or covered and lit at night?
-
Is the excavation a confined space or is gas monitoring required due to CO2 emissions?
Confined Space
-
Confined Space
-
Is the confined space work absolutely necessary? Are all required confined space permits in place?
-
Are approved Method Statements / Submittals and Risk Assessments in place for all confined spaces?
-
Is atmospheric monitoring undertaken before an during work with the atmospheric hazards tested?
-
Is rescue and emergency response equipment in place with trained personnel present?
-
Is at least one spotter stationed outside the confined space for the duration of the entry?
-
Are persons in the confined space attached to a retrieval line to enable "non-entry" rescue?
-
Is all required access, egress and communication equipment present and appropriate?
-
Has the confined space been isolated from electrical, mechanical, chemical, heat + hazards?
-
Are confined space danger signs posted at the entrance(s) to all known confined spaces?
Falling Object from Heights
-
Falling Object from Heights
-
Is the public / site personnel protected (scaffold netting / guards / fans, walk-ways, "no lift zones")?
-
Are "Lifting Plans" in place approved by M+W for works involving lifting of equipment and materials?
-
Are test and inspection records on file for all lifting appliances and lifting equipment? (cranes ans slings?)
-
Are lifting operations being undertaken by competent personnel using appropriate communication means?
-
Are all loads made secure before lifting i.e. steel banding to timber, banding to blocks, brick cages)?
-
Are all floor openings securely covered or protected by barriers with toe boards to prevent falling objects?
-
Are safety nets suspended beneath roofing activities to capture falling personnel, materials or tools?
Energized Electrical
-
Energized Electrical
-
Is live work necessary and are all required Energized Electrical Work Permits in place?
-
Are approved Method Statements / Submittals and Risk Assessments in place for all EEW?
-
Is all required Personal Protective Equipment (PPE) available, suitable and in good working order?
-
Have all conductive items been removed / covered when working by exposed energy electrical sources?
-
Are all required tools, equipment and testing instruments appropriate, available and in good order?
-
Is all appropriate safety equipment in place (body hook, CO2 fire extinguisher(s), barricades)?
-
Any other Energized Electrical Work safety issues?
Control of Hazardous Energy
-
Control of Hazardous Energy
-
Is a "Permit to Work" in place for each activity involving COHE?
-
Is an approved Method Statement / Submittal and Risk Assessment in place for each COHE activity?
-
Have hazardous energy sources been identified and are required hazardous energy isolations in place?
-
Are isolation records in the job documentation (on the PreTask Plan)?
-
Are all required Lock Out / Tag Out ( LOTO) devices in place and are they adequately secured?
-
Is LOTO being undertaken and controlled by an "Authorized Person" with affected persons notified?
-
Any other Control of Hazardous Energies related issues?
Corrective Actions
-
Corrective Action
-
Description of issue including names
-
Enter any corrective actions that will be undertaken (include ownership of CA)
-
Owner of Corrective action
-
Due Date of Corrective Action
-
Check if completed
Sign Off
-
Time completed
-
EHS Rep name