Fenix Green Light No.
-
Client
-
Site Name/Reference
-
Site Location
-
Operating Organisations
-
Prepared by
Changes in the working context or stakeholder expectations
-
Have there been any changes in working context or stakeholder expectations?
-
Describe changes and which assessments, plans, processes and procedures have been affected.
-
Check that all affected assessments, plans, processes and procedures have been updated.
Checks to be carried out before giving Permission to work
-
Site Safety Assessment complete and OK?
-
Environmental aspects OK?
-
Munition Risk Assessment OK?
-
All essential personnel are present and fit?
- Yes
- No
- N/A
-
All personnel qualified and authorised for their roles?
-
All personnel blood types, allergies, special requirements held by site medic?
-
Valid Medical Emergency Response Plan in place?
-
All CASEVAC vehicles serviceable and ready?
-
Emergency communications tested and correct?
-
All required equipment available and in working order?
-
Lifting equipment available and in satisfactory condition
-
Site organisation OK?
-
Mobile phone, electronic items and flammable materials policy in force?
-
Safety and quality brief provided to all staff?
-
Are there any additional site-specific checks required?
-
Describe additional site-specific checks that must be confirmed prior to agreement to Green Light
-
All site-specific checks OK?
-
Name and signature of Site Manager
-
Date and Time at which Green Light in force
-
Have there been any significant changes in circumstances, conditions or context during the day and/or have any decisions been taken that are significant for quality, environmental or safety reasons?
-
Provide detail of changes and/or decisions
Withdrawal of Green Light on completion of operations
-
All operations complete?
-
All explosive items removed/secure?
-
All personnel accounted for?
-
Name and signature of Site Manager
-
Date and time at which Green Light was withdrawn
-
Once this record is completed ensure it is exported to PDF and saved
Suspension of Green Light
-
When was PTW suspended?
-
Why was PTW suspended?
-
Nonconformity Reference if any
-
Name and signature of site manager
-