Title Page
-
Inspection No.
-
Organisation and Site
-
Conducted on
-
Inspector
-
Location
-
Project Team
-
Overall Project Performance
- Excellent - Exceeding current expectation
- Good- Meeting current expectations
- Fair - Improvements required
- Poor - Significant improvements required
-
Summary
-
Unless otherwise stated, all non conformances must be closed out in the following timeframe:
Major non-conformances - 3 days
Minor non-conformances - 7 days
Interim measures must be implemented to prevent the non conformance from causing harm whilst the corrective action is being completed.
A Corrective Action Report must be completed for all Major Non Conformances.
Perimeter and External
-
External clean, tidy and presentable portraying a professional image
-
Perimeter fencing / hoarding secure
-
Public protection sufficient (gantry, scaffold, shade cloth, barricading and signage etc.)
-
Pedestrians protected from vehicles entering and leaving site
-
Crossover and footpath clear, safe and free from slip hazards and defects
-
Correct signage - builders sign, PPE sign, danger sign, excavation sign
-
"Visitors Report to Site Office" sign displayed at site entrance.
-
Assembly Area sign displayed offsite
-
Other
-
Other
Overhead Powerlines
-
Tiger tails / flags in place
-
"Danger Overhead Powerlines" signage at entrance and exit
-
'No Go Zone' signage displayed at 6.4m and 3m
-
Other
-
Other
Access
-
Sign in Register / Attendance Board available upon access to site
-
Suitable access throughout
-
Two means of access wherever practicable
-
Ladder access as last resort.
-
Adequate lighting throughout
-
Other
-
Other
Housekeeping
-
Site clean and tidy and portrays a professional image
-
Skips available and regularly emptied
-
Means of getting waste to skips (hoist, crane bins, lift, rubbish chute etc.)
-
Bin lifter or other means of safely placing waste into skips
-
Contractors notified of housekeeping requirements and forewarned of potential back charges
-
Other
-
Other
First Aid
-
Level 2 First Aider onsite
-
First Aider's training up to date
-
Fully stocked first aid kit
-
Checklist on back of first aid kit door
-
First aid signage in place
-
First aid set up in accordance with Site Establishment Manual
-
Other
-
Other
Emergency Planning
-
Means of rescuing injured workers from all areas onsite
-
Emergency Information sign displayed throughout
-
Means of raising the alarm established
-
Fire points on every level
-
Fire extinguishers tested and tagged
-
Battery backup emergency lighting where required
-
Other
-
Other
PPE
-
Correct PPE worn by everyone onsite
-
Spare PPE available and locked away
-
Sunscreen available
-
PPE Register being used
-
Other
-
Other
Tools, Plant, Equipment
-
Logbooks being completed before each use
-
Plant maintenance up to date
-
Tools tested and tagged, in good condition with guards in place
-
Other
-
Other
Manual Handling
-
Lifting aids onsite (bin lifters, hoists, forklifts, trolleys, dollies, barrows etc.)
-
Materials delivered close to final locations wherever possible
-
Other
-
Other
Electrical
-
Certificate of Electrical Safety (CES) for all temp. Installations onsite
-
Temp. Installations re-inspected every 6 months
-
Construction wiring marked with warning tape and in conduit or at high level where it cannot become damaged.
-
Sufficient number of switchboards onsite
-
Switchboards compliant - lockable and fixed in position
-
RCDs tested and tagged monthly
-
Other
-
Other
Work at Height
-
All fall risks are controlled
-
All means of fall prevention are compliant (spacing, fixings, material etc.)
-
Guard rails fixed to entire capping beam if required
-
All penetrations secured with suitable cover boards or guard railed
-
Ladders used as last resort
-
Balcony guard rails high enough to prevent falls
-
Work at Height hierarchy followed
-
Other
-
Other
Cranes
-
Green sticker in date
-
Maintenance and inspection up to date
-
Crane Logbook completed daily
-
Lifting equipment tested and tagged and in date
-
Sufficient number of Doggers onsite
-
Doggers carry backup whistles
-
Other
-
Other
Precast Panels
-
Correct bracing
-
Panels grouted and plates bolted during installation
-
Plates welded ASAP
-
Other
-
Other
Precast Panel Installation
-
Experienced rigger on the truck rigging and inspecting panels
-
Rigger on the truck completing Precast Delivery register
-
Safe access to the panels on the truck
-
Experienced rigger landing the panels
-
Enough personnel assisting
-
No go zone established with sufficient barricading and signage
-
No go zone encompasses lift area, slew area and landing area
-
Third parties kept away from no go zone
-
Panels lifted from the truck only when footing is ready
-
Organised, systematic method of installation
-
Other
-
Other
Dangerous Goods / Hazardous Substances
-
Suitable storage
-
Signage displayed
-
Extinguisher nearby
-
Labelled containers
-
Other
-
Other
Excavations and Trenching
-
1.5m excavations benched or shored. If not, engineering completed by Geo Engineer or other competent engineer
-
Safe access into excavation
-
Spoil, plant etc. kept a safe distance from excavation to prevent surcharge
-
Loose material kept away from edge or suitable means of preventing falling materials (kick boards, screens etc.)
-
Fall prevention in place
-
Bunting / markers in place to identify edge of all excavations regardless of depth
-
SWMS in place
-
Other
-
Other
Scaffolding
-
Safely footed
-
Sufficient Ties (roughly every 2nd lift and 3rd standard)
-
Sufficient Bracing (top to bottom, first bays, ends of scaffold, no more than 3 unbraced bays in a run)
-
Tag in date
-
Rating sign and unauthorised alterations signage displayed
-
Other
-
Other
Asbestos
-
Survey onsite
-
Asbestos identified/protected onsite
-
Removed by competent contractor
-
Clearance certificate after removal where required
-
Other
-
Other
Amenities
-
Sufficient number
-
Clean, tidy and fully stocked
-
Condition of all amenities are to the extent that they portray a professional image to clients
-
Plumbed in Zip unit
-
Plumbed in water fountains
-
Other
-
Other
Notices and displays
-
Hazards board setup and updated daily
-
Notice boards as per Site Establishment Manual
-
Other
-
Other
General
-
Other
-
Other
-
Other
-
Other
-
Other
-
Other
Documentation
-
Documentation accessible via Dropbox
-
Hoarding engineering
-
Powerline Permit
-
Scaffold engineering
-
Guardrail stanchion documentation
-
Formwork design
-
Formwork sign off
-
Traffic Management Plan
-
Underground Service Plan
Folders
-
Forms Folder fully completed and up to date
-
Registers Folder fully completed and up to date
-
Checklists Folder fully completed and up to date
-
General Folder fully completed and up to date
-
SWMS Folder fully completed and up to date
-
Inductions Folder fully completed and up to date
-
MSDS Folder completed and up to date
Manuals
-
H&S Coordination Plan available and up to date
-
Site Establishment Manual available and followed
-
Electrical Manual available and up to date
-
Induction Manual available and up to date
Workplans
-
Crane Erection and Maintenance WorkPlan up to date
-
Precast Panel WorkPlan up to date including brace removal register
-
Winching Panels WorkPlan up to date
-
All documentation neatly filed in correct folders and readily available
-
All items actioned on most recent Summary Report
-
All items actioned on most recent Inspection Report
-
General
-
Items raised by site team
Sign Off
-
Add signature
-
Add signature