This Hot Work Permit is required for any operation involving open flame or producing heat and/or sparks.
-
Site conducted
-
Area Hot Work is being performed at
-
Type of Hot Work being performed
- Welding
- Brazing
- Cutting
- Grinding
- Soldering
- Pipe Thawing
- Torch-Applied Roofing
- Chemical Welding
- Other
-
List type of Hot Work
-
Conducted on
-
Name of person(s) doing Hot Work
-
THIS PERMIT IS VALID FOR 12 HOURS ONLY
-
Time Hot Work started
-
Time Hot Work completed
-
I verify that the above location has been examined, the precautions marked on the checklist below have been taken, and permission is granted for this work.
-
Name of Permit-Authorizing Individual
Checklist (Check the box after reviewing and if the hazard applies)
-
Available sprinklers, hose streams, and extinguishers are in service and operable.
-
Hot Work equipment is in good working condition in accordance with manufacturer's specifications.
-
Special permission obtained to conduct Hot Work on metal vessels or piping lined with rubber or plastic
-
Permission received from?
Requirements within 35 ft (11 m) of Hot Work
-
Flammable liquid, dust, lint, and oily deposits removed
-
Explosive atmosphere in area eliminated
-
Floors swept clean and trash removed
-
Combustible floors wet down or covered with damp sand or fire-resistive / noncombustible materials or equivalent
-
Personnel protected from electrical shock when floors are wet
-
Other combustible storage material removed or covered with listed or approved materials (welding pads, blankets, or curtains, and/or fire-resistive tarpaulins), metal shields, or noncombustible materials
-
All wall and floor openings covered
-
Ducts and conveyors that might carry sparks to distant combustible material covered, protected, or shut down
Requirements for Hot Work on walls, ceilings, or roofs
-
Construction is noncombustible and without combustible coverings or insulation
-
Combustible material on other side of walls, ceilings, or roofs is moved away
Requirements for Hot Work on enclosed equipment
-
Enclosed equipment is cleaned of all combustibles
-
Containers are purged of flammable liquid and vapors
-
Pressurized vessels, piping, and equipment removed from service, isolated, and vented
Requirements for Hot Work fire watch and fire monitoring
-
Fire watch is provided during and for a minimum of 30 minutes after Hot Work, including any break activity
-
Fire watch is provided with suitable extinguishers and, where practical, a charged small hose
-
Fire watch is trained in use of equipment and in sounding alarm
-
Fire watch can be required in adjoining areas, above and below
-
Per the Permit-Authorizing Individual, does the fire watch need to be extended beyond 30 minutes?
-
How much longer has the fire watch been extended?
Additional Comments
-