Title Page

THEISS MBR ITP#1013 UNDERGROUND CONDUIT

  • Station

  • Location- Ie Station building, main switch room

  • Does this Switch board require further ITPS for completion

  • Chassis relevant for this ITP

  • Chassis / cabinets requiring additional ITPS.

  • INSPECTION / TEST POINT Check for latest drawings and co-ordinates

  • Compliance Criteria - Electrical Drawings and Klenner main switchroom layout

  • Hold point- No

  • Method of inspection- Visual, Administrate

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Fix Switchboard in place using suitable fixings to match mounting service. No damage to external baord has occurred during instalaltion.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- Yes

  • Method of inspection- Visual, measurement

  • Insert photos as required

  • Photo
  • External photos as required.

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Cut out and install cable glands / cable protection. Ensure glands / cut outs match IP rating & fire rating of cables. No sharp edges left within Switchboard.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Ensure adequate pathways exist within board to accommodate all circuits and allow for future expansion.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Install and loom in all circuits into correct cabinets.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Ensure cable labels match switchboard schedule and construction drawings.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Label all cables correctly within specified requirements.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Terminate all cables as per specified drawings and control documentation. Ensure no loose cables are left within cabniets. All circuits not to be connected are suitably covered and labelled.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Check all tightness of all terminals on all breakers and bars.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Check all tightness of all terminals on all breakers and bars.

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Carry out final tidy on board, vacuum all debris from board. FInal cable ties as required.

  • Compliance Criteria- Drawings, electrical specification

  • Hold point- Yes

  • Hold point- Yes

  • Method of inspection- Visual, photographic

  • Method of inspection- Visual, photographic

  • Insert photos as required

  • Photo
  • Internal board photos of internal board as required.

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT THIESS Station Supervisor / Engineer to sign off

  • Compliance Criteria- Drawings and electrical specification

  • Hold point- Yes

  • Method of inspection- Visual, measurement

  • Person Responsible- Thiess Supervisor / Engineer

  • These works are installed as per current construction drawings, approved shop drawings and specification.

  • Comment

  • INSPECTION / TEST POINT Submit to Klenner Project Manager, including mark up of relevant area from Plan Grid. Plan grid image must be a screen shot referencing the drawing number.

  • Compliance Criteria- Electrical specification

  • Hold point- Yes

  • Method of inspection- Visual, mark up plan

  • Location mark up

  • Person Responsible- Supervisor

  • Add signature

  • Comment

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.