Title Page
THIESS MBRL ITP#1013 UNDERGROUND CONDUIT
-
Station
- PETRIE
- KALLANGUR
- MURRUMBA DOWNS
- MANGO HILL
- MANGO HILL EAST
- ROTHWELL
- KIPPA RING
- STABLING YARD
-
ITPS RELEVANT FOR WORK AREA
-
Works carried out as per drawings and listed ITPS
-
Compliance Criteria - Drawings Electrical
-
Add signature
-
Comment
-
Area is installed
-
Compliance Criteria- measurement & Visual
-
Hold point- No
-
Method of inspection- Visual, measurement
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT KLIK Beam installed securely to brackets with Stainless steel bolts and washers
-
Compliance Criteria- measurement & Visual
-
Hold point- No
-
Method of inspection- Visual, measurement
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT KLIK beam installed level and parallel to purlin
-
Compliance Criteria- Drawings, measurement & visual
-
Hold point- Yes
-
Method of inspection- Visual, photographic
-
Insert photos as required
Photo
-
Photo detailing line of KLIK with purlin
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT KLIK beam installed into DB level and Center to allocated panels
-
Compliance Criteria- Drawings, measurement & visual
-
Hold point- Yes
-
Method of inspection- Visual, photographic
-
Insert photos as required
Photo
-
Photo detailing line of KLIK with purlin
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Covers installed correctly
-
Compliance Criteria- Drawings, measurement & visual
-
Hold point- Yes
-
Method of inspection- Visual, photographic
-
Insert photos as required
Photo
-
Photo detailing line of KLIK with purlin
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Area left clean and tidy
-
Compliance Criteria- Visual
-
Hold point- No
-
Method of inspection- Visual,
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT THIESS Station Supervisor / Engineer to sign off
-
Compliance Criteria- Electrical specification & drawings
-
Hold point- Yes
-
Person Responsible- THIESS Supervisor / Engineer
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Submit to Klenner Project Manager, including mark up of relevant area from Plan Grid
-
Compliance Criteria- Electrical specification
-
Hold point- No
-
Method of inspection- Visual, mark up plan
-
Location mark up
-
Person Responsible- Leading Hand
-
Add signature
-
Comment