Title Page

THIESS MBRL ITP#1013 UNDERGROUND CONDUIT

  • Station

  • ITPS RELEVANT FOR WORK AREA

  • Works carried out as per drawings and listed ITPS

  • Compliance Criteria - Drawings Electrical

  • Add signature

  • Comment

  • Area is installed

  • Compliance Criteria- measurement & Visual

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT KLIK Beam installed securely to brackets with Stainless steel bolts and washers

  • Compliance Criteria- measurement & Visual

  • Hold point- No

  • Method of inspection- Visual, measurement

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT KLIK beam installed level and parallel to purlin

  • Compliance Criteria- Drawings, measurement & visual

  • Hold point- Yes

  • Method of inspection- Visual, photographic

  • Insert photos as required

  • Photo
  • Photo detailing line of KLIK with purlin

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT KLIK beam installed into DB level and Center to allocated panels

  • Compliance Criteria- Drawings, measurement & visual

  • Hold point- Yes

  • Method of inspection- Visual, photographic

  • Insert photos as required

  • Photo
  • Photo detailing line of KLIK with purlin

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Covers installed correctly

  • Compliance Criteria- Drawings, measurement & visual

  • Hold point- Yes

  • Method of inspection- Visual, photographic

  • Insert photos as required

  • Photo
  • Photo detailing line of KLIK with purlin

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Area left clean and tidy

  • Compliance Criteria- Visual

  • Hold point- No

  • Method of inspection- Visual,

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

  • INSPECTION / TEST POINT THIESS Station Supervisor / Engineer to sign off

  • Compliance Criteria- Electrical specification & drawings

  • Hold point- Yes

  • Person Responsible- THIESS Supervisor / Engineer

  • Add signature

  • Comment

  • INSPECTION / TEST POINT Submit to Klenner Project Manager, including mark up of relevant area from Plan Grid

  • Compliance Criteria- Electrical specification

  • Hold point- No

  • Method of inspection- Visual, mark up plan

  • Location mark up

  • Person Responsible- Leading Hand

  • Add signature

  • Comment

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.