Site conducted
-
Document No. GYP 007 v1.0
-
Client / Site
-
Audit Title
-
Block/Plot No
-
Conducted on
-
Prepared by
-
Site Address
-
All other trades are complete and area left clean and tidy.
-
1st fix electrical completed and handed over.
-
1st fix mechanical completed and handed over.
-
Any damages from 1st fix boarding.
-
Noggins/Ply fitted as marked by M/E trades.
-
Insulation installed as allowed/drawings.
-
Plaster board specifications checked to all walls.
-
Ceiling grid lines checked Screw centres checked.
-
Ceiling in cupboard complete.
-
Hallway to plot mastic checked.
-
Access panels cut to size ready to receive panels.
-
Cut outs for electrical boxes formed as marked by the concerned sub-contractor.
-
Ceiling void handed over as complete.
-
Plasterboard close up complete.
-
Board fixed to manufacture spec.
-
All window boards fixed.
-
All Area 100% completed
-
Area left clean and tidy ready for the next trade.
-