Title Page
-
Site conducted
-
Client
-
Site
-
SCOPE OF WORK
-
Contract Manager
-
Site Manager
-
Conducted on
-
Prepared by
EHS – SITE EHS INSPECTION
INTRODUCTION
-
All sites are audited against the group benchmark of 85%
Above 90% - Site is performing above the required standard
85.1% - 90% - Site is meeting Group Benchmark
81% - 85% - Site Requires Improvement
80% & below Site is non-compliant to group standards -
undefined
-
Have all items from previous inspections been closed out?
-
Are the Friday Packs (including weekly Supervisor Inspections) being submitted weekly and do they include all required documentation?
1. PUBLIC SAFETY & SIGNS
-
Complete Section
-
1. Hoarding erected / maintained?
-
2. Signage adequate for public / general safety?
-
3. Signs to welfare (offices, stores, first aid etc.)?
2. COVID -19 CONTROLS & PAPERWORK
-
Complete Section
-
1. Are staff adhering to the documented site COVID 19 controls?
-
2. Has the JB Structures COVID 19 addendum and risk assessment been populated and briefed to staff?
3. WORKPLACE ACCESS & WALKWAYS
-
Complete Section
-
1. Is there sufficient pedestrian segregation from plant and equipment?
-
2. Were adequate access and walkways provided?
-
3. Adequate lighting provided?
4. HOUSEKEEPING – TIDINESS & STORAGE
-
Complete Section
-
1. Site areas tidy?
-
2. Safe access to materials? Are materials stacked /stored safely
5. PERSONAL PROTECTIVE EQUIPMENT
-
Complete Section
-
1. PPE correct for the task at hand e.g. hard hat, hi-vis vest, gloves, boots, eye protection, hearing protection as identifies in the RAMS /Risk Assessment?
6. ELECTRICAL SAFETY
-
Complete Section
-
1. 110 volt system in use?
-
2. Extension leads in good condition?
-
3. Generators in good condition and placed properly?
-
4. Cables laid / suspended in a safe manner to remove any trip hazard?
-
5. PAT testing in date?
7. FIRE SAFETY
-
Complete Section
-
1. Staff assembly point provided?
-
2. Adequate number of fire extinguishers available? (Fire points adequate for site and levels, seperate JBS extinguishers for HOT WORKS only?)
8. TEMPORARY WORKS
-
Complete Section
-
1. Is there an appointed and qualified Temporary Works Co-ordinator & Temporary Works Supervisor?
-
2. Is the Temporary Works Register completed and up to date?
-
3. Are the Weekly Temporary Works Inspection sheets (JBS-H&S-FRM-0139) being completed by TWC/TWS and submitted with Friday Packs each week?
9. POWER TOOLS (PUWER)
-
Complete Section
-
1. Correct power tool for the job?
-
2. Power tools in good condition?
-
3. Have operatives using abrasive wheels (petrol saws, grinders) received Abrasive Wheels training?
-
4. Are staff aware of the HAVs related to the equipment they are using? Is HAVs being recorded?
10. WORK AT HEIGHT
-
Complete Section
-
1. Crash decks in place?
-
3. Exclusion Zone established and sufficient signage in place?
-
4. Are fans required?
-
5. Fall arrest, emergency rescue equipment & procedure in place?
-
7. Are the correct anchor points being used for any working at height involving harnesses & inertia reels? (no dywidag tie bars and nuts, no strops around GTs, no inertial reels hooked on props etc.)
-
8. Canti-Deck installed by a trained, competent person?
11. MEWPS
-
Complete Section
-
1. Trained operator?
-
3. Current certificates available for MEWP?
-
3. Pre-use inspection completed?
12. MOBILE SCAFFOLD TOWERS (PASMA)
-
Complete section
-
1. Towers erected/supervised by trained personnel?
-
2. Mobile scaffold tower suitable and sufficient for the task being undertaken?
13. PODIUMS / LADDERS / STEPLADDERS
-
Complete section
-
1. Correct podiums / ladders / stepladders in use?
-
2. Podiums / ladders / stepladders in good condition? (missing feet, bent rungs, not cut shorter)
-
3. Equipment used safely? (secured/footed/outriggers in place and extended)
14. LIFTING APPLIANCES (LOLER)
-
Complete Section
-
1. Chains / slings/ lifting aids in good working order?
-
2. Lift Plans in place?
-
3. Certified operators/slingers/signaller (CPCS / NPORS)?
-
4. Annual &/or 6 monthly inspection reports available?
-
5. Are loads secured and is the lift being controlled?
-
6. Are lifting accessories (slings, chains etc.) stored safely and tidily?
15.PLANT OPERATIONS - EXCAVATOR / DUMPERS / ROLLERS
-
Complete section?
-
1. Operated by trained personnel (CPCS / NPORS)?
-
2. Reversing aids - e.g. CCTV, mirrors? Is a banksman required? Is there an Exclusion Zone in operation?
-
3. Plant maintained in good condition and daily pre-use inspection completed?
16. EXCAVATIONS
-
Complete section?
-
1. Method Statements and U/G surveys available?
-
2. Permit to Dig in place?
-
3. Inspections carried out daily and recorded?
-
4. U/G services located and marked i.e. CA Tool on site?
-
5. Access/egress provided?
-
6. Adjacent structures protected?
-
7. Sides guarded – barriers, stop blocks?
-
8. Shoring provided/sides battered or stepped/trench box?
-
9. Edge protection erected along excavation edges?
-
10. Is excavation warning signage displayed prominently?
-
11. Are materials (steel, timber etc.) and excavated muck stored safely away from excavation edge?
17. STEEL FIXING
-
Complete Section
-
1. Is steel fixing taking place is accordance with the RAMs?
-
2. Is the correct level PPE being worn?
-
3. Is there safe access (boards across mesh, steps etc._?
-
4. Is exposed metalwork / rebar protected?
18. FALSEWORK/FORMWORK
-
Complete Section
-
1. Is formwork being erected in accordance with the RAMs? Is the correct fixing being used for shutter installation?
-
2. Are design drawings available?
-
3. Is the falsework (decking) being erected in accordance with the appropriate RAMs (Alshor / Skydeck / GT deck)?
-
4. Are harnesses being worn, in good condition, tagged and in date and is there a fall arrest system or appropriate anchor point in use?
-
5. Are staff harness-trained to work on the leading edge?
-
6. Are the leading edges installed as per the manufactures guidance?
19. STRIKING
-
Complete Section
-
1. Is the striking taking place in accordance with the RAMs?
-
2. Is there an exclusion zone in place and signage?
-
3. Are staff working safely near or on the building edge (tool tethers used, materials stored away from the edge)
20. CONCRETE
-
Complete Section
-
1. Is concrete being pumped / poured as per the RAMs?
-
2. Are all members of staff involved with the concrete wearing the correct level of PPE?
-
3. Have the COSHH assessments for concrete/cement been briefed to the concrete team?
-
4. Is the pump line secured (if required) and are "R" clips fitted?
-
5. Is the concrete lorry set up so as to cause no additional hazard to the site or general public?
-
6. Is there means for disposal of any washout?
21. MANUAL HANDLING
-
Complete Section
-
1. Is the hierarchy of control being used i.e. Task, Individual, Load, Environment?
-
2. Mechanical means in use?
-
3. Has manual handling training taken place?
22. ENVIRONMENTAL
-
Complete Section
-
1. Is waste segregated into correct skips?
-
2. Is dust being managed (suppression/extraction)? Is RPE available? Have staff been trained for the RPE?
-
3. Are suitable COSHH storage facilities available? (fire point and suitable spill kit nearby (universal or chemical, not 'oil only).
-
4. Are COSHH assessments available for all chemicals on site?
-
5. Are spill kits available and adequate?
23. OCCUPATIONAL HEALTH
-
Complete Section
-
1. First aid kits and eyewash available?
-
2. Trained first-aiders on site sufficient for the number of operatives?
-
3. Sufficient space for the number of personnel on site?
-
4. Kept clean – floors, sinks, tables, appliances etc.?
-
5. Suitable drinking water supply?
-
6. Method for drying clothes provided?
-
7. Hot & cold running water? Means of heating food?
24. DOCUMENTATION / INDUCTION
-
Complete Section
-
1. Method statements & risk assessments available?
-
2. Are sub-contractors working to their documented RAMs? Have the RAMs been reviewed and signed off?
-
3. Regular site safety meetings/daily activity briefings?
-
4. Induction information on site?
-
5. Is the correct and latest documentation being used by the site team?
-
6. Emergency procedures displayed?
-
7. Regular toolbox talks taking place?
-
8. Are all mandatory weekly inspections being completed and logged I.E. PUWER, LOLER, ladder inspections etc.
TRAINING RECORDS / TASK SPECIFIC TRAINING
-
1. Are the training records in place and available in the site files / HSEQ Dropbox?
-
2. How many operatives on site are trained in Working at Height / leading edge on site?
-
Please complete training booking request form JBS-H&S-FRM-0078 and send to Training@jbstructures.co.uk
-
Please state the names of operatives trained in Working at Height / Leading edge on site?
-
3. How many operatives on site are trained in the safe use of a MEWP 3a (scissor lift) on site?
-
Please complete training booking request form JBS-H&S-FRM-0078 and send to Training@jbstructures.co.uk
-
Please state the names of operatives trained in Safe use of a MEWP 3a (Scissor Lift) on site?
-
4. Is there adequate numbers trained in First Aid on site?
-
Please complete training booking request form JBS-H&S-FRM-0078 and send to Training@jbstructures.co.uk
-
Please state the names of operatives trained in First Aid on site?
-
5. Is there adequate numbers trained in Temporary Works on site?
-
Please complete training booking request form JBS-H&S-FRM-0078 and send to Training@jbstructures.co.uk
-
Please state the names of operatives trained in Temporary Works on site?
-
6. Is there an adequate number of trained slinger /signallers on site?
-
Please complete training booking request form JBS-H&S-FRM-0078 and send to Training@jbstructures.co.uk
-
Please state the names of operatives trained in NPORS / CPCS Slinging / signaller on site?
COMPLETION
-
Auditor's name and signature:
-
Site manager's name and signature:
CLOSE OUT
-
undefined
-
Select date