Drywall
-
All ceiling heights are correct in accordance with the most up-to-date contract drawings?
-
Gypsum board is hanging a minimum of 1" below dropped ceiling for proper taping
-
Gypsum board is ran from underside of ceiling to top of floor in fire rated partitions behind tape?
-
All acoustical caulking is complete at the top and bottom track of corridor and demising walls?
-
All insulation has been installed in exterior (foil faced), corridor (unlaced) and demising walls (unfaced)?
Low Voltage
-
Low voltage inspection has been performed and approval stamp from COA is in he permit book?
-
All permissions through fire rated partitions have been made with conduit?
-
Fire protection has been installed around all LV conduit and inside the conduit around the LV wiring at ceiling?
-
All wall grommets that are in fire rated partitions have been packed with the fire protection?
-
Spacing between LV conduit and drywall is not excessive?
-
All boxes are in the correct location and secure?
-
Any apparent damage to the gypsum board in the fire rated partitions due to LV installation?
-
All blocking used by subcontractor is fire treated wood?
Electrical
-
Electrical inspection has been performed and approval stamp from COA is in the permit book?
-
Fire Protection has been installed around all conduit/MC cable above ceiling?
-
At least one electrical box has fire rated putty pack when in the same stud cell with another electrical box?
-
Spacing between electrical conduit/MC cable n drywall is not excessive?
-
Any apparent damage to gypsum board in fire rated partitions due to electrical conduit/MC cable installation?
-
Any and all blocking used by subcontractor was done so using fire rated wood?
-
All line set holes in the floor of the of the mechanical rooms have fire protection properly installed?
-
All boxes have the proper support ears for the partition type they are in, secure, and in the right location?
Plumbing
-
Plumbing inspection has been performed and approval stamp from COA is in the permit book?
-
Gas inspection has been performed and approval stamp from COA is in the permit book?
-
All water lines have been air tested at 100 PSI, passed and results have been provided to JMW?
-
All gas lines have been air tested at 60 PSI, passed and results have been provided to JMW?
-
Fire protection has been installed around all plumbing and gas lines above ceilings in fire rated partitions?
-
All holes in concrete slab not in use have been properly sealed?
-
Spacing between plumbing pipe or gas lines in drywall is not excessive?
-
Ant apparent damage to gypsum board in fire rated partitions due to piping and gas line installation?
-
Any and all blocking used by subcontractor was done using fire rated wood?
-
All piping through metal studs has been installed properly? Any cut studs need to be repaired on the spot?
-
After testing lines with water, all track has been cleared of any standing water?
Sprinkler
-
Sprinkler inspection has been performed and approval stamp from COA is in the permit book?
-
All penetrations through fire rated partitions above ceiling level have had fire protection installed?
-
All sprinkler lines ave been air tested at 40 PSI, passed, and results provided to JMW?
-
All sprinkler heads have been capped off?
-
Any and all blocking used by subcontractor was done using fire rated wood?
-
Water has been placed into the system, tested at 200 PSI for 2 hours and holding?
HVAC
-
HVAC inspection has been performed and approval stamp from COA is in the permit book?
-
All penetrations through fire rated partitions above ceiling level have had fire protection installed?
-
All duct penetrating the exterior walls have been properly sealed?
-
All duct supply drops and returns are in the correct area?
General
-
All trade inspections have been accounted for?
-
All blocking and/or strapping in fire rated partitions is fire rated wood?
-
All windows have been waterproofed?
-
Review
-
Follow up Notes
-
Plumbing Contractor Signature
-
Select date
-
Electrical Contractor Signature
-
Select date
-
Low Voltage Contractor Signature
-
Select date
-
Sprinkler Contractor Signature
-
Select date
-
Drywall Contractor Signature
-
Select date
-
HVAC Contractor Signature
-
Select date
-
JMW Representative Signature
-
Select date