Title Page

  • Conducted on

  • Prepared by

  • Location
  • Has a risk assessment and method statement been prepared

  • Is the specialist subcontractor operating quality procedures or a quality plan

  • Is the area prepared for this element and any builders work complete

  • Have other relevant trades been co-ordinated

  • Are works progressing to programme

  • Is the specialist subcontractor completing his own quality control records

  • Have consultants visited site and any actions arising been carried out

  • Are plant rooms, switch rooms, and distribution board locations complete, weather tight and secure

  • Are all inspection and maintenance points accessible

  • Have arrangements been made for commissioning and witnessing of tests

  • Are inspections and tests complete, results and certificates received

  • Have all necessary approvals been granted

  • Have relevant services been protected, insulated and identified

  • Have all smoke and fire barriers been installed

  • Have all work areas been left tidy for following trades

  • Have relevant keys and spare components been provided

  • Does the Clients Maintenance Engineer require any on site tuition

  • Have O & M manuals and as-built drawings been received

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.