Title Page
PROJECT INFO
-
PROJECT NAME
-
CONDUCTED ON
-
PREPARED BY
-
LOCATION
-
Personnel (MINIMUM OF SUPER AND FOREMAN)
JOB STEPS AND SPECS LOOK AHEAD
-
LIST JOBS STEPS (AND LOCATION) BEING PERFORMED THIS WEEK
-
LIST JOB STEPS TO BE (AND LOCATION) PERFORMED NEXT WEEK
-
LIST SPECIFICATION NUMBER AND SECTION RELATED TO EACH JOB STEP
-
LIST PLAN SHEET NUMBERS RELATED TO EACH JOB STEP
TOOLS AND EQUIPMENT
-
WHICH SPEC SECTIONS HAVE TOLERANCES OR DETAILS RELATING TO QUALITY, COMPLETION, OR CONTROL OF THE WORK?
-
BY SPEC SECTION LIST TOLERANCES OR QC REQUIREMENTS
-
DOES THE SPEC REQUIRE ENGINEER APPROVAL FOR ANY PORTION OF THESE JOB STEPS
-
DETAILS
-
HAS ENGINEERS INSPECTION OR APPROVAL BEEN COORDINATED?
-
DOES THE SPEC REQUIRE TESTING FOR ANY OF THESE JOB STEPS?
-
HAS TESTING BEEN COORDINATED?
-
IS TESTER AWARE OF SPEC REQUIREMENT?
-
DO TESTS REQUIRE SAMPLING IN ORDER TO COMPLETE THE TEST? (e.g. compaction)
-
ALL GUARDS ARE INSTALLED AND WORKING PROPERLY?
-
LIST OTHER IMPORTANT NOTES FROM THE SPECIFICATIONS RELATED TO THESE JOB STEPS
MATERIALS
-
DO THESE JOB STEPS REQUIRE APPROVED MATERIALS?
-
LIST MATERIALS REQUIRING APPROVAL FOR EACH JOB STEP
-
ARE ALL OF THE MATERIALS REQUIRED TO COMPLETE THIS WORK ONSITE?
-
ARE ALL OF THE MATERIALS FOR THESE STEPS APPROVED?
-
LIST WHAT MATERIALS STILL NEED APPROVAL OR STILL NEED TO ARRIVE ONSITE
-
-
WHAT WON'T WORK AND WHY?
-
DO YOU HAVE ANY RECOMMENDATIONS FOR ALTERNATE MATERIALS?
-
DETAILS
-
DO THE ALTERNATES MEET THE SPECIFICATIONS?
-
HAVE THE ALTERNATES BEEN SUBMITTED?
-
HAVE THE ALTERNATES RECEIVED VERBAL APPROVAL?
-
ARE MATERIALS STORED CORRECTLY?
-
HAVE EMPLOYEES BEEN TRAINED ON HOW TO INSTALL THE MATERIALS?
-
WOULD A MANUFACTURERS REP BE HELPFUL TO OVERSEE YOUR APPLICATION?
-
DETAILS
CONFLICTS AND RFIs
-
DO NOTES OR DETAILS MATCH SPECIFICATIONS FOR THIS WORK?
-
Briefly Describe the conflict
-
HAS AN RFI BEEN SUBMITTED or Discussed?
-
HAS IT BEEN RESPONDED TO
-
DETAILS
-
WAS THE CONFLICT CLARIFIED
-
HOW?
-
ARE THERE RFIs RELATED TO CURRENT OR UPCOMING WORK
-
WHAT IS THE RFI
-
HAS IT BEEN RESPONDED TO?
-
IF YES, BRIEFLY DESCRIBE RESPONSE
-
IF NO, IS IT CAUSING DELAYS
-
What are the delays?
-
DO YOU HAVE QUESTIONS ON THE PLANS OR SPECIFICATIONS?
-
DETAILS
CHANGE ORDERS
-
ARE THERE CHANGE ORDERS RELATED TO UPCOMING JOB STEPS
-
HAS THE CO BEEN APPROVED?
-
IF NO: IS IT OR WILL IT CAUSE DELAYS?
-
HAS THE CO RECEIVED VERBAL APPROVAL?
-
DETAILS
-
DO YOU RECOMMEND ANY CHANGES FOR UPCOMING WORK?
-
IF YES, WHAT DO YOU RECOMMEND AND WHY?
SAFETY
-
HAS AN AHA OR JHA BEEN COMPLETED FOR EACH JOB STEP?
-
HIGHLIGHT SOME OF THE HAZARDS
-
HIGHLIGHT SOME OF THE CONTROLS FOR THOSE HAZARDS
-
HAVE EMPLOYEES BEEN MADE AWARE OF THE HAZARDS?
-
-
IS ADDITIONAL SAFETY EQUIPMENT REQUIRED?
-
IS ADDITIONAL EQUIPMENT REQUESTED OR ONSITE?
MANPOWER AND EQUIPMENT
-
DO YOU HAVE THE MANPOWER AVAILABLE TO MAINTAIN PRODUCTION WHILE MEETING THE SPEC REQUIREMENTS?
-
DO YOU HAVE THE MANPOWER/EQUIPMENT TO MAINTAIN QUALITY WHILE MAINTAINING PRODUCTION?
-
DO YOU HAVE THE EQUIPMENT AND MANPOWER TO ACCOMPLISH THE WORK SAFELY?
-
LIST REQUEST FOR ADDITIONAL MANPOWER OR EQUIPMENT
PROJECT PHOTOS
-
DO YOU HAVE PHOTOS OF WORK AREA PRIOR TO STARTING EACH JOB STEP?
-
-
DO YOU HAVE PHOTOS OF WORK AREA AFTER COMPLETING JOB STEPS?
-
-
DO YOU HAVE PHOTOS OF QC OR TESTING REQUIREMENTS BEING MET OR COMPLETED?
SIGNATURES (SUPER, FOREMAN, QCM, PM, ENGINEER, ETC)
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES
-
SIGNATURES