  • SITE CONDUCTED

  • CONDUCTED ON

  • PREPARED BY

  • LOCATION

  • PLOT NUMBER

  • SUBCONTRACTOR

LASER 2ND FIX QA SHEET

2ND FIX INSTALLATION

  • Downlights cut out and installed correctly, in a straight line, with heats/smokes where applicable

  • Are all lighting accessories ( pendants, batten holders, feature lights, downlighters, switches, fan isolators, joint boxes, etc.) Installed

  • All Fire and CO detection accessories (smoke detectors & bases, heat & bases, carbon monoxide detectors and bases ) Installed

  • All alarms operational and interlink ?

  • All (sockets outlets, spurs, cooker switches, grids, doorbell chime etc) Installed

  • All TV accessories, ( TV outlet, euro plates, & media plates, euro brushes ) Installed

  • All BT accessories, ( BT outlets, euro plates, media plates, data modules, BT modules) Installed

  • All ventilation equipment, ( extract fans, diffusers, MVHR & MEV units etc.) Installed correctly

  • All loft roof accessories, batten holders, sockets, Installed

  • All consumer units ( breakers, blanks, busbar covers, labelling) Installed correctly

FINALS (2ND AND SUBSEQUENT VISITS)

  • All Lamps are fitted

  • All heating controls, ( thermostatts, cylinder statts, motorised valves, programmers, pumps, junction boxes, wiring centers, immersion supplys) Installed correctly

  • Energising and functional testing ( connect tails, check installation, energise ccu, and perform functional testing in advance of testing )

  • kitchen pelmet lighting installed (choc boxes fitted)

  • Earthing & bonding installed, clamps fitted where applicable

  • All external lighting ( external lights, pir's, photocells, etc) Installed

  • All extract grills ( extract grills, soffit vents, roof cowl joints, slinkys to lofts, etc) Installed correctly

CML Requirements (FINAL CHECK)

  • Smoke/heat/Co2 alarms are installed 300mm away from fittings and walls

  • Ducting in loft spaces installed correctly, Ducting is supported and tort

  • All External fixtures and fittings are fitted

  • All External grills are fitted

  • Bonding clamped installed

  • Heating on, zones operational

  • Garage complete, armoured cleated, spurs, switches, sockets and batten holders fitted

  • Name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.