Information
-
Audit Title
-
Site
-
Location
-
Contractor/s
-
Conducted on
-
Audit Conducted By
-
Other Personnel Present
Kerb Base Proof Roll
-
What is the location of the kerb base to be tested?
-
What plant is being used to proof roll the kerb base?
-
Has area 150 mm behind the back of kerb been compacted?
-
Is the kerb base preparation approved?
Kerb Pre-Pour Inspection
-
Where matching into existing kerb and channel, are levels and alignment as required by the design?
-
Is line of kerb as required by design and providing the correct road width?
-
Is the grade on the kerb and channel as required by the design?
-
Are pits in correct locations?
-
If required by the design, have lay-back locations for pram and vehicle crossings been identified and allowed for?
-
Have underground services been identified for kerb stamping?
-
Insert photos of soft spots?
-
Contractor to sign:
-
Council Representative to sign: