Information
-
Chandos project and job number
-
Conducted on
-
Prepared by
Describe the current construction phase.
-
Add media
-
Add drawing
If "No" is answered to and of the following questions please indicate corrective measures takes.
HVAC
-
Are HVAV materials protected from weather?
-
Are the HVAC materials kept covered and dry before and after installation?
-
Are filter media is maintained in good condition?
Source Control
-
Are work practices not create air borne dust in minimum condition?
-
Are liquid material keep closed when not use?
-
Are low emitting materials being used? (paints, adhesives, caulking)
Pathway Interruption
-
Are temporary mats being used to protect areas from dust and overspray?
-
Are barriers placed within boundary of excavation and finished floor?
Housekeeping
-
Are trash bins provided throughout the site?
-
Are area clean from debris?
-
Are Smoking area sign available and sighted easily?
Scheduling
-
Conduct activities with high pollution during off hours or limit the impact to surrounding workers.
Inspection Comments:
Inspection Sign Off
-
Add signature
-
Add signature