Information
-
Audit Title
-
Rig Number
-
Conducted on
-
Prepared by
-
Location / Well
-
Personnel
BOP, choke manifold and gas buster
-
1. properly installed?
-
2. All Valves on choke manifold in working condition?
-
3. HCR valve working properly?
-
4. Casing side pressure gauge tested and working properly?
-
5. Drill pipe pressure gauge tested and working properly?
-
6. Drilling standpipe pressure gauge on floor tested and working properly<br>
-
7. All Valves on Choke manifold function tested by opening up full and closing then one quarter back turn?
-
8. Accumulator air and electric hooked up and in proper working condition.
-
9. Flair stack and panic line installed and connections tight.
-
10. Accumulator Hydraulic Bottle
-
11. Flex hose 2” Kill line installed and with safety cable
-
12. Flex hose HCR valve to Choke manifold installed and with safety cable.
-
14. Cellar covered
-
13. Hydraulic hoses hook up with no leaks
-
15. Are all bolts and nut installed on flow line dresser sleeves
-
16. Check valve installed
-
17. Is Blind rams open & close handle protected with a locking device.
-
18. Casing valve closed.
-
Comments:
-
Add media
-
Signature: inspected by
-
On site representative