Title Page
-
Prepared by
Site Details
-
Address
-
Meter Number
-
Date and Time
Job Scoping
-
Is prestart scoping required? ie. Confirm site access, Check Phase Rotation
-
Is installation 3 phase
Record Phase Rotation RWB (L to R / T to B)
-
Recorded at Main Switch
-
-
Recorded at MIL
-
-
Take photo of Switches as found
-
Take photo of Switches as found
-
Proceed to next page
Setting the Scene
-
What are you doing?
- Are you ONLY Isolating a Service?
- Are you ONLY installing a Service and NOT connecting to the Consumer Mains?
- Are you Replacing an Existing OH Service?
- Are you doing an Initial Connection
LVCM 13.A - ISOLATION OF AN INSTALLATION
Step 1: At the Main Switchboard
-
Is Installation Three Phase?
-
Recorded at Main Switch RWB (L to R / T to B)
-
Recorded at MIL RWB (L to R / T to B)
Step 2: Advise
-
Advise customer supply will be interrupted
Step 3: At customers Main Switchboard
-
Record position of all Main Switches, CB’s and fuses
-
Turn off all Main Switches and CB’s
Step 4: At LV Mains
-
Remove all service fuses
Step 5: At the Main Switchboard
-
Using a proximity device Confirm Supply is De-energised
-
Test Consumer Mains Actives
-
Test Consumer Mains Neutral
Step 6: Disconnect/Isolate Installation from LV Network
-
ie: Remove OH Service and Hardware / Discoonect UG Consumer Mains from LV Pillar and Secure
Completion / Sign Off
-
Sign
LVCM 13.B: Testing an OH Service / Dedicated UG Service Cable
Step 1: Install the Service and Secure
-
DO NOT CONNECT TO NETWORK
Step 2: At the LV Mains
-
Check System Normal
-
Single Phase
-
Test between LV Mains Neutral and LV Mains Active
-
Test between Independent Earth and LV Mains Active
-
Test between Independent Earth and LV Mains Neutral
-
Test between Independent Earth and LV Mains Active
-
Multi Phase
-
Test between LV Mains Neutral and each LV Mains Active
-
Test between Phases A-B, B-C, C-A
Step 3: Connect Service to LV Mains
-
In accordance with construction standards
Step 4: At LV Mains
-
Visually Confirm all Service Actives are fused, and
-
That the Service Neutral is connected directly to the LV Mains Neutral
Step 5: At the LV Mains
-
Insert Fuses
Step 6: At Service Tails Customers End
-
Prove Correct Connections
-
Single Phase
-
Using a Voltmeter
-
Test between the Service Neutral and the Service Active
-
Using a Proximity Device
-
Test Service Active
-
Test Service Neutral
-
Test Neutral Bond Tail
-
Multiphase
-
Using a Voltmeter
-
Test between Service Neutral and each Service Active
-
Test between Phases A-B, B-C, C-A
-
Using Proximity Device
-
Test Neutral Bond Tail
Step 7: At the LV Mains
-
Remove Service Fuses
Step 8: At Service Tails Customers End
-
Confirm the Service Neutral is NOT fused or Energised and Actives are NOT Energised
-
Using Proximity Device
-
Test Service Active/s
-
Test Service Neutral
-
Test Neutral Bond Tail
Step 9: At Service Tails Customers End
-
Secure Service Tails
Completion / Sign Off
-
Sign
Replace an Existing Overhead Service - LVCM 13.A, 13.C & 13.D
Step 1: At the Main Switchboard
-
Is Installation Three Phase?
-
Recorded at Main Switch RWB (L to R / T to B)
-
Recorded at MIL RWB (L to R / T to B)
Step 2: Advise the Customer that Supply will be Interrupted
Step 3: At the Main Switchboard
-
Record position of all Main Switches, CB’s and fuses
-
Turn off all Main Switches and CB’s
Step 4: At the LV Mains
-
Remove all Service Fuses
Step 5: At the Main Switchboard
-
Using a Proximity Device, Confirm Supply has been De-Energised
-
MEN / Main Neutral as found
Step 6: At the Main Switchboard
-
Remove the MEN Connection and the Main Neutral/s from the Main Neutral Link and Secure
-
Place coloured cable ties in the removed conductors Neutral Link Terminals i.e. Black Main Neutral, Green MEN
-
MEN / Main Neutral removed
Step 7: At the Main Switchboard
-
Using a Multimeter on Ohms setting, Perform Continuity Test to confirm ALL Main Switches are OPEN. Test between LINE side of Main Switch and Neutral Link/s
-
If a reading other than (OL) is obtained re-check the installation:
- for additional Main Switches
- Main Switch/Switches that may have not operated correctly
- incorrect Neutral was removed or identified
- incorrect Switchboard wiring which may include un-switched circuits
If all above factors have been considered, then a reading above 60,000 Ohms (60K) would be considered acceptable.
Step 8: For a Service
-
Disconnect and remove existing service line
-
Ensure that any Neutral Bonding Conductor is DISCONNECTED from metallic parts and secured
-
Install the Service and Connect to the Consumer Mains
Step 9: CONFIRM THE SWITCHBOARD IS PREPARED FOR CONNECTION and TESTING AT THE SWITCHBOARD IS IMMINENT
Step 10: At the LV Mains
-
Check System Normal
-
Single Phase
-
Test between LV Mains Neutral and LV Mains Active
-
Test between Independent Earth and LV Mains Active
-
Test between Independent Earth and LV Mains Neutral
-
Test between Independent Earth and LV Mains Active
-
Multi Phase
-
Test between LV Mains Neutral and each LV Mains Active
-
Test between Phases A-B, B-C, C-A
Step 11: Connect Service / Consumer Mains to the LV Network
-
In Accordance with Construction Standard - Visually Confirming - All Actives are fused, and - The Neutral is Connected to the LV Mains Neutral
Step 12: At the Service, Point of Supply or Switchboard
-
Confirm the Consumer Mains are NOT Energised
-
Using a Proximity Device
-
- Test Consumer Mains Active/s
-
- Test Consumer Mains Neutral
Step 13: Confirm the Switchboard is prepared for Testing
-
At the LV Mains
-
Insert Service Fuse/s
Step 14: At the Main Switchboard
-
Prove Connections (Polarity)
-
Single Phase
-
Test between the Main Neutral and Line Terminal of the Main Switch
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Independent Earth and the Main Neutral
-
Test between Independent Earth and the Customer's MEN
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Multi Phase
-
Test between the Main Neutral and Line Terminal of the Main Switch
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Independent Earth and the Main Neutral
-
Test between Independent Earth and the Customer's MEN
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Phases A-B, B-C, C-A
Step 15: At the Main Switchboard
-
Perform Neutral Integrity Test (NIT) =< 1 Ohm
-
Record Value
-
Confirm that:<br>1. There is no high resistance connections to the network.<br>2. Supervisor has been contacted. <br>3 The high reading is due to conductor size/lengths. <br>Appropriate process followed if leaving energises.
-
Record Value
-
ABANDON TEST, ISOLATE SUPPLY, DISCONNECT ALL SERVICE TAILS FROM LV NETWORK
Step 16: At the Main Switchboard
-
Reconnect the Main Neutral and then the MEN to the Main Neutral Link
Step 17: At the Main Switchboard
-
Perform MEN Integrity Test - Test between an Earthed component and the Line Terminal of the Main Switch =< NIT
-
Accepted MEN Integrity Test points: Earth Bar, Earthed Switchboard Enclosure, Earth Electrode. Or where the previous options are not available the Neutral Link where the MEN is connected.
-
=<NIT
-
Take photo of Main Neutral Link with Main Neutral and MEN Connected
-
Have you confirmed that:<br><br>1. The Main Neutral and MEN are connected to the Main Neutral Link and Secured correctly<br>2. The Test Point is effectively Earthed<br>3. You have a good connection between test instrument leads<br><br>If all factors have been considered, then a reading within 0.1 Ohms of the NIT would be considered acceptable.
-
Take photo of Main Neutral Link
-
Move to next Step
-
ABANDON TEST, ISOLATE SUPPLY, DISCONNECT ALL SERVICE TAILS FROM LV NETWORK
Step 18: At the Main Switchboard
-
If applicable, Check Phase Rotation is correct previously recorded in Step 1
Step 19: Neutral Bond
-
Test to ensure that the disconnected bonding conductor is NOT connected to the Service Active
-
Using a Proximity Device
-
Test Neutral Bond Tail
-
Test Service Attachment Point
-
Connect the Bond to the Service Attachment Point
-
Test Bonded Metalwork
-
Bonding Completed by
Step 20: At the Main Switchboard
-
Return all Main Switches / Circuit Breakers to the position noted prior to work being carried out
Step 21: At the Main Switchboard
-
Conduct Final Test and visually confirm that the Main Neutral and MEN are connected to the Main Neutral Link
-
Using Proximity Device
-
Test Main Neutral Link and the MEN connection
-
Take photo of Secured Switchboard
Completion / Sign Off
-
Sign
LVCM 13.C - INITIAL CONNECTION
Step 1: At the Main Switchboard
-
Turn off all Main Switches, CB’s and Alternate Supplies
-
Using a Proximity Device, Confirm there is NO Supply
-
Switches on OFF Position
Step 2: At the Main Switchboard
-
Remove the MEN Connection and the Main Neutral/s from the Main Neutral Link and Secure
Step 3: At the Main Switchboard
-
Using a Multimeter on Ohms setting, Perform Continuity Test to confirm ALL Main Switches are OPEN. Test between LINE side of Main Switch and Neutral Link/s
-
If a reading other than (OL) is obtained re-check the installation:
- for additional Main Switches
- Main Switch/Switches that may have not operated correctly
- incorrect Neutral was removed or identified
- incorrect Switchboard wiring which may include un-switched circuits
If all above factors have been considered, then a reading above 60,000 Ohms (60K) would be considered acceptable.
Step 4: Bonding
-
Is Bonding Required?
-
Ensure that any Neutral Bonding conductor is disconnected from metallic parts and Secured
-
Move to next Step
Step 5: CONFIRM THE SWITCHBOARD IS PREPARED FOR CONNECTION and TESTING AT THE SWITCHBOARD IS IMMINENT
Step 6: At the LV Mains
-
Check System Normal
-
Single Phase
-
Test between LV Mains Neutral and LV Mains Active
-
Test between Independent Earth and LV Mains Active
-
Test between Independent Earth and LV Mains Neutral
-
Test between Independent Earth and LV Mains Active
-
Three Phase
-
Test between LV Mains Neutral and each LV Mains Active
-
Test between Phases A-B, B-C, C-A
Step 7: Connect Service / Consumer Mains to the LV Network
-
In Accordance with Construction Standard - Visually Confirming - All Actives are fused, and - The Neutral is Connected Directly to the LV Mains Neutral
Step 8: At the Service, Point of Supply or Switchboard
-
Confirm the Consumer Mains are NOT Energised
-
Using a Proximity Device
-
- Test Consumer Mains Active/s
-
- Test Consumer Mains Neutral
Step 9: Confirm Switchboard is prepare for Testing
-
At the LV Mains
-
Insert Service Fuse/s
Step 10: At the Main Switchboard Prove Connections
-
Single Phase
-
Test between the Main Neutral and Line Terminal of the Main Switch
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Independent Earth and the Main Neutral
-
Test between Independent Earth and the Customer's MEN
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Multi Phase
-
Test between the Main Neutral and Line Terminal of the Main Switch
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Independent Earth and the Main Neutral
-
Test between Independent Earth and the Customer's MEN
-
Test between Independent Earth and the Line Terminal of the Main Switch
-
Test between Phases A-B, B-C, C-A
Step 11: At the Main Switchboard
-
Perform Neutral Integrity Test (NIT) =< 1 Ohm
-
Record Value
-
Confirm that:<br>1. There is no high resistance connections to the network.<br>2. Supervisor has been contacted. <br>3 The high reading is due to conductor size/lengths. <br>Appropriate process followed if leaving energises.
-
Move to Next Step
-
ABANDON TEST
Step 12: At the Main Switchboard
-
Reconnect the Main Neutral and then the MEN to the Main Neutral Link
Step 13: At the Main Switchboard
-
Perform MEN Integrity Test - Test between an Earthed component and the Line Terminal of the Main Switch =< NIT
-
Accepted MEN Integrity Test points: Earth Bar, Earthed Switchboard Enclosure, Earth Electrode. Or where the previous options are not available the Neutral Link where the MEN is connected.
-
=< NIT
-
Take photo of Main Neutral Link with Main Neutral and MEN Connected
-
Have you confirmed that:<br><br>1. The Main Neutral and MEN are connected to the Main Neutral Link and Secured correctly<br>2. The Test Point is effectively Earthed<br>3. You have a good connection between test instrument leads<br><br>If all factors have been considered, then a reading within 0.1 Ohms of the NIT would be considered acceptable.
-
Take photo of Main Neutral Link
-
Move to next Step
-
ABANDON TEST
Step 14: At the Main Switchboard
-
If applicable, Check Phase Rotation is correct previously recorded in Step 1
Step 15: Neutral Bond
-
Test to ensure that the disconnected bonding conductor is NOT connected to the Service Active
-
Using a Proximity Device
-
Test Neutral Bond Tail
- No Indication
-
Test Service Attachment Point<br>
-
Connect the Bond to the Service Attachment Point
-
Test Bonded Metalwork<br>
-
Bonding Completed by
Step 16: At the Main Switchboard
-
As per Processes -
Turn of Main Switch/es and CB's
or
Leave Main Switch/es and CB's turned OFF with Sticker over Main Switch/es
Step 17: At the Main Switchboard
-
Conduct Final Test and visually confirm that the Main Neutral and MEN are connected to the Main Neutral Link
-
Using Proximity Device
-
Test Main Neutral Link ant the MEN connection
-
Take photo of Secured Switchboard
Completion / Sign Off
-
Sign