1. Planning/Maintenance Day Activities
-
1.1 The pre-maintenance day meeting has been conducted according to standard meeting design
-
1.2 The team leader conducts a pre-shift meeting according to agreed meeting design
-
1.3 Cleaning activities documented and communicated (audited during pre-shift meeting)
-
1.4 The maintenance day kick-off meeting (07h30) has been conducted according to the standard meeting design as per Appendix B
-
1.5 Maintenance plan updated (audited at 08h30). Maintenance day plan is displayed on the maintenance planning board
-
1.6 Audited 09h00<br>The Packaging Engineer authorizes all changes to the maintenance day resource plan that have arisen due to unplanned maintenance activities on any line
-
1.7 Audited 09h00<br>All cleaning materials (tools and chemicals) are available
-
1.8 Maintenance day plan is updated during the maintenance day
-
1.9 Team leader plans his maintenance shift according to the start-up requirements
2. Maintenance Execution
-
2.1 The Unit Manager walk the line at 07h00 on the maintenance day and assess/audit cleaning and housekeeping done up to 07h00
-
2.2 Night shift Team Leader handed over to the MS Team Leader
-
2.3 Filler stopped according to the plan
-
2.4 Maintenance day permit to work, process complies with safety regulations
-
2.5 The Team Leader manage and audit cleaning activities as per plan
-
2.6 Maintenance Controller carries out inspections on planned work
-
2.7 Contractor cleaning
-
2.8 The Unit Manager and Team Leader conduct production related PJO's according to maintenance day plan
-
2.9 During maintenance day, the Maintenance Controller/Planner carry out PJO's on the agreed maintenance tasks and schedule durations
-
2.10 Maintenance schedules
3. Start-up Requirements
-
3.1 The morning shift Team Leader handed over to the afternoon shift Team Leader according to procedure
-
3.2 Team Leader, Controller and Planner follow the process as individual machines are started up
4. Schedule Returns
-
4.1 Operator acceptance sheets have been completed and signed
-
4.2 All schedules returned on the maintenance day
5. Post Maintenance Day Activities
-
5.1 The Unit Manager audits at least 2 machine areas the day after maintenance prior to the post maintenance day meeting
-
5.2 The post maintenance day meeting is conducted according to the standard meeting design
5.3 Total Score Maintenance Day Practices
-
Maintenance Day KPI's are achieved against agreed line targets:
-
Maintenance day machine efficiency 90%
-
Maintenance day volume adherence
-
Actual start-up time vs. planned start-up time
-
ZERO Maintenance Day Injuries