Title Page

  • Master Build Template

  • Environment Agency PUWER Inspection Pack
    Generated on 27/11/2023

  • Conducted on

  • Contractor

  • Prepared by

  • Your reference:

  • Location
  • Risk Assessment in place and signed

  • Method Statement in place and signed

  • Confined Space working

  • Any Changes in task

  • Correct Isolation in place

  • Working at Height

  • Work area free from trip hazards

  • Traffic / pedestrian segregation

  • Excavation / Services - plans available

  • Overhead Electrical Hazards

  • People working overhead / nearby

  • Scaffold suitable - inspected

  • Correct Tools

  • Permits in place

  • All equipment PAT tested

  • High Pressure Systems

  • Noise

  • Correct PPE

  • Chemical or Biological Hazard

  • Risk of Drowning or entrapment

  • Weather conditions

  • Have you completed a dynamic risk assessment?

Site Details

Site and Work Order

  • "SITE NAME"

  • Work Order: Missing

Asset PPM Report

  • Complete PPM schedules for all assets as per reference. Add photos where required.

Building Services External Lighting- S_BEX&00_12E_01A

  • PPM Schedule Ref: Annual Building Electrical Services

  • Task -

  • Check operation of access lighting and associated sensors.

  • Check lighting is labelled up sufficiently and labelling is correct.

  • Check there is safe access to the columns and no trees / branches affecting the lighting columns

  • Foundation Base Checks -

  • Check base for damage / condition

  • Column foundation bolts for tightness and corrosion.

  • Column foundation bolts ‘denso’ tape for signs of wear

  • Column hinge undertake detailed check for signs of wear and corrosion.

  • Verify Distribution board labelling

  • Circuit labelling (DB and final circuits).

  • EICR labelling is present and in date (report if not).

  • Light electrical supply check

  • Covers and seals are complete.

  • Presence and condition of labels and warning signs.

  • Vermin damage

  • Water ingress

  • Wiring for damage and any signs of overheating.

  • Inspect trunking, cable tray and conduit for damage and completeness.

  • Check earth bonding to ensure it is mechanically sound, correct, complete and undamaged.

  • If non LED lighting units are installed, identify unit and note in report.

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

Building Electrical Services - S_BE&00_12E_01A

  • PPM Schedule Ref: Annual Building Electrical Services

  • Inspect meter area

  • Check that it is accessible

  • Free from stored equipment

  • Correct warning signs are fitted

  • Inspect cables, meters and other associated equipment is free from damage and that there are no exposed live parts. Inform Asset Owner and/or Electricity supply company immediately and take action to prevent assess.

  • Obtain Ze & PFC at the Supply where applicable & Record

  • Inspect distribution boards for

  • Signs of damage

  • Spare ways have correctly fitted covers

  • Check that correctly rated fuses and MCB's are fitted and are complete

  • Test any RCDs, RCCBs and RCBOs using the test button

  • Check lightning / surge arrestors

  • Check operation of main switch (Isolator)

  • Inspect trunking and conduit for damage and completeness

  • Inspect all switches, sockets, connection units, blanking plates, junction boxes, for damage and completeness.

  • Visually inspect all permanently fixed equipment for damage and security of fixing.

  • Check operation of all lights. Ensure that correctly rated bulbs and fitting are being used.

  • Check operation of emergency lighting and fire exit signs.

  • Check operation of lighting on PIR or dawn to dusk lighting systems.

  • Check operation of all sockets. (All voltage ranges both ac and dc)

  • Inspect room heaters for signs of overheating, completeness and operation of associated thermostats/humidistats.

  • Inspect water heaters for damage, signs of overheating, completeness and operation of associated thermostats and electrical safety devices.

  • Inspect transformers and check for damage and operation.

  • Inspect all supplementary earth bonding both internal and external to the building and correct labels are fitted.

  • Inspect all equipment which is fed from and external to the building for damage and completeness.

  • Inspect generator connection sockets for damage and completeness.

  • Test the resistance to earth of each local earth electrode (with down conductor and earth electrode disconnected).

  • Test the resistance to earth of the complete earth termination system.

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Incomer & Distribution - S_CI&00_12E_01A

  • PPM Schedule Ref: S_CI&00_12E_01A - Incomer distribution annual maintenance

  • Isolate the incomer section before opening doors. Check that the incomer section is not combined with a generator or UPS. If so isolate the generator/UPS

  • Visually inspect and record

  • general condition of the incomer section

  • cables are undamaged and correctly identified

  • there are no exposed sections of conductors

  • all covers and insulators are undamaged and complete.

  • general condition of the equipment i.e. isolators indicators etc

  • primary and secondary bonding in mechanically correct

  • panel heaters and fans

  • ventilation louvers and filters

  • covers and seals are complete with all fasteners

  • water ingress

  • condition of labels and warning signs

  • vermin damage

  • Internal distribution boards - Inspect

  • check operation of disconnectors

  • test operate all RCDs, RCCBs and RCBOs Report all faulty units and replace as necessary

  • record time and trip current on adjustable units

  • check that all MCBs and MCCBs are undamaged and can be operated

  • check all fuses are the correct type, rating and are undamaged.

  • surge protectors are undamaged and active.

  • plug-in components have no signs of visible damage i.e. timers, relays etc

  • Isolator switches - Inspect

  • if fuses are inside switch enclosure check that they are the correct type, rating and are undamaged.

  • Check that all the electricity supplier's equipment is undamaged and firmly fixed. Report any problems.

  • TT systems only. Check that the TN-C-S (PME) earth conductor has not been reconnected back to the site earth.

  • Check operation of all protective systems i.e. phase failure relays, power failure relays, earth fault protection etc

  • Check operation of all timers and record settings. (if fitted)

  • Check indication lamps and replace as necessary (if fitted)

  • Check indicators, voltmeters, ammeters and power meters are operating. (if fitted)

  • Check operation of mechanical interlocks (if fitted)

  • Lubricate door hinges and locks as necessary

  • Clean enclosures internally and ensure free from debris

  • Clean panel front including indicators

  • Ensure that generators and UPS have been returned to their normal operating condition.

Observations

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Common Controls - S_CC&00_06E_01A

  • PPM Schedule Ref : S_CC&00_06E_01A - Common controls 6M maintenance

  • - general condition of common control section

  • - general condition of the equipment i.e. contactors, relays, overloads, transformers etc

  • - primary and secondary earth bonding is mechanically sound and correct

  • - panel heaters and fans

  • - ventilation louvres and filters

  • - presence and condition of labels and warning signs

  • - operation of all switches, push buttons, safety interlocks, HMI's and indicators. Replace indicators as necessary

  • - function of all emergency stop devices.

  • - 20% of all electrical connections. (on larger panels thermal imagery should be used)

  • - mechanical operation of MCB's, RCBO's etc

  • - fuses for correct rating

  • - plug in components i.e. relays, timers etc. are seated correctly and have no visual signs of damage

  • - mechanical operation of interlocked isolator / other type of isolators

  • Measure primary and secondary earth bonding resistance reading with calibrated device, report and rectify if greater than 0.1 ohm

  • Measure control voltage and report if not within +/- 6%

  • UPS - check system is on line and not indicating a fault condition

  • Trip amplifier - check calibration and trip setting by injecting current source or carry out at the same time as primary controller.

  • Level indicators - check calibration and trip setting by injecting current source or carry out at the same time as primary controller.

  • Operate controls in all modes of operation, check for correct operation. Check indicators, voltmeters, ammeters and instrumentation.

  • Check operation of all protective systems i.e. low / high level alarms etc

  • Telemetry - Check in conjunction with EM to ensure correct operation and signal status at outstation terminals

  • Lubricate door hinges and locks as necessary.

  • Clean panels internally and ensure free from debris

  • Clean panel front including indicators

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Star delta starter annual maintenance - S_CW&00_12E_01A -

  • PPM Schedule Ref: S_CW&00_12E_01A - Star delta starter annual maintenance

Work Schedule

  • Isolate the starter section and earth the system and allow capacitors (if fitted) to discharge

  • Visually inspect and record

  • general condition of the starter section

  • general condition of the equipment i.e. contactors, capacitors indicators etc

  • primary and secondary bonding in mechanically correct

  • panel heaters and fans

  • ventilation louvers

  • covers and seals are complete

  • condition of labels and warning signs

  • water ingress

  • Check the below -

  • operation of all switches, pushbuttons, safety interlocks and indicators

  • function of emergency devices

  • 20% of all electrical connections (check all if 5% are found faulty and use thermal imagery on larger panels)

  • fuses are correct rating and undamaged

  • plug in components have no signs of visible damage i.e. timers, relays etc

  • mechanical operation of interlocked isolator / other type of isolator

Inspections -

  • Inspect both sets of contactors for general condition, overheating, and mechanical interlocks are functioning correctly.

  • Check settings of overload protection devices and record settings.

  • Measure primary and secondary earth bonding resistance with calibrated instrument, record and rectify if greater than 0.10.

  • Measure control voltage and report if not within +/- 6%.

  • Trip amplifier (if fitted) - check calibration and trip setting by injecting with calibrated current source or carry out the same time as primary controller.

  • Operate controls in all modes of operation, check for correct operation.

  • Check operation of all protective systems i.e. voltage measuring relays and record settings.

  • Check operation of all timers and record settings.

  • Check indication lamps and replace as necessary.

  • Check indicators and meters are operating.

  • Lubricate door hinges and locks as necessary.

  • Clean panels internally and ensure free from debris.

  • Clean panel front including indicators.

  • Record hours run

Observations

  • Observation Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

DOL starter annual maintenance - S_CD&00_12E_01A

  • PPM Schedule Ref: S_CD&00_12E_01A - DOL starter annual maintenance

Work Schedule

  • Isolate the starter section and earth the system and allow capacitors (if fitted) to discharge

  • Visually inspect and record

  • general condition of the starter section

  • general condition of the equipment i.e. contactors, capacitors indicators etc

  • primary and secondary bonding in mechanically correct

  • panel heaters and fans

  • ventilation louvers

  • covers and seals are complete

  • condition of labels and warning signs

  • water ingress

  • Check the below -

  • operation of all switches, pushbuttons, safety interlocks and indicators

  • function of emergency devices

  • 20% of all electrical connections (check all if 5% are found faulty and use thermal imagery on larger panels)

  • fuses are correct rating and undamaged

  • plug in components have no signs of visible damage i.e. timers, relays etc

  • mechanical operation of interlocked isolator / other type of isolator

Inspections -

  • Inspect contactor for general condition, overheating, and mechanical interlocks are functioning correctly.

  • Check settings of overload protection devices and record settings.

  • Measure primary and secondary earth bonding resistance with calibrated instrument, record and rectify if greater than 0.10.

  • Measure control voltage and report if not within +/- 6%.

  • Trip amplifier (if fitted) - check calibration and trip setting by injecting with calibrated current source or carry out the same time as primary controller.

  • Operate controls in all modes of operation, check for correct operation.

  • Check operation of all protective systems i.e. voltage measuring relays and record settings.

  • Check operation of all timers and record settings.

  • Record hours run

  • Check indication lamps and replace as necessary.

  • Check indicators and meters are operating.

  • Lubricate door hinges and locks as necessary.

  • Clean panels internally and ensure free from debris.

  • Clean panel front including indicators.

Observations

  • Observation Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Variable Speed Starter annual maintenance - S_CV&00_12E_01A

  • PPM Schedule Ref: S_CV&00_12E_01A - Variable Speed Starter annual maintenance

Work Schedule

  • Isolate the starter section and earth the system and allow capacitors (if fitted) to discharge

  • Visually inspect and record

  • general condition of the starter section

  • general condition of the equipment i.e. contactors, capacitors indicators etc

  • primary and secondary bonding in mechanically correct

  • panel heaters and fans

  • ventilation louvers

  • covers and seals are complete

  • condition of labels and warning signs

  • water ingress

  • Check the below -

  • operation of all switches, pushbuttons, safety interlocks and indicators

  • function of emergency devices

  • 20% of all electrical connections (check all if 5% are found faulty and use thermal imagery on larger panels)

  • fuses are correct rating and undamaged

  • plug in components have no signs of visible damage i.e. timers, relays etc

  • mechanical operation of interlocked isolator / other type of isolator

Inspections -

  • Variable Speed Starter Unit -

  • general condition

  • overheating

  • terminations

  • heat-sink for cleanliness and clean as necessary

  • fan (if fitted) operation and cleanliness of filtration. Clean/ replace filter media as necessary.

  • External cooling fan (if fitted) - Inspect

  • General Condition

  • functionality

  • cleanliness of filtration. Clean/ replace filter media as necessary.

  • Choke / Line Reactor / Transformer - Inspect

  • general condition

  • overheating

  • breakdown of insulation

  • terminations

  • EMC filters - Inspect

  • general condition

  • outer casing / shield

  • overheating

  • terminations

  • earth bonding

  • HMI’s and external key pads (if fitted) - Inspect

  • general condition

  • functionality

  • Connections to soft start drive

  • indication

  • Tasks -

  • Measure primary and secondary earth bonding resistance with calibrated instrument, record and rectify <br>if greater than 0.1Ω.

  • Operate controls in all modes of operation, check for correct operation check operation of voltmeters, <br>ammeters etc

  • Check operation of all protective systems i.e. earth fault relays, voltage sensing relays etc and record settings

  • Record Hours Run

  • Check indication lamps and replace as necessary

  • Check indicators and meters are operating

Observations

  • Observation Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Soft Start annual maintenance - S_CS&00_12E_01A

  • PPM Schedule Ref: S_CS&00_12E_01A - Soft Start annual maintenance

Work Schedule

  • Isolate the starter section and earth the system and allow capacitors (if fitted) to discharge

  • Visually inspect and record

  • general condition of the starter section

  • general condition of the equipment i.e. contactors, capacitors indicators etc

  • primary and secondary bonding in mechanically correct

  • panel heaters and fans

  • ventilation louvers

  • covers and seals are complete

  • condition of labels and warning signs

  • water ingress

  • Check the below -

  • operation of all switches, pushbuttons, safety interlocks and indicators

  • function of emergency devices

  • 20% of all electrical connections (check all if 5% are found faulty and use thermal imagery on larger panels)

  • fuses are correct rating and undamaged

  • plug in components have no signs of visible damage i.e. timers, relays etc

  • mechanical operation of interlocked isolator / other type of isolator

Inspections -

  • Soft Start Unit -

  • general condition

  • overheating

  • terminations

  • heat-sink for cleanliness and clean as necessary

  • fan (if fitted) operation and cleanliness of filtration. Clean/ replace filter media as necessary.

  • External cooling fan (if fitted) - Inspect

  • General Condition

  • functionality

  • cleanliness of filtration. Clean/ replace filter media as necessary.

  • Choke / Line Reactor / Transformer - Inspect

  • general condition

  • overheating

  • breakdown of insulation

  • terminations

  • EMC filters - Inspect

  • general condition

  • outer casing / shield

  • overheating

  • terminations

  • earth bonding

  • HMI’s and external key pads (if fitted) - Inspect

  • general condition

  • functionality

  • Connections to soft start drive

  • indication

  • Tasks -

  • Measure primary and secondary earth bonding resistance with calibrated instrument, record and rectify <br>if greater than 0.1Ω.

  • Operate controls in all modes of operation, check for correct operation check operation of voltmeters, <br>ammeters etc

  • Check operation of all protective systems i.e. earth fault relays, voltage sensing relays etc and record settings

  • Record Hours Run

  • Check indication lamps and replace as necessary

  • Check indicators and meters are operating

Observations

  • Observation Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Resistance Starters annual maintenance - S_CR&00_12E_01A

  • PPM Schedule Ref: S_CR&00_12E_01A - Resistance Starters annual maintenance

Work Schedule

  • Isolate the starter section and allow capacitors (if fitted) to discharge

  • Visually inspect and record:

  • - general condition of the starter section

  • - general condition of the equipment i.e. contactors, capacitors indicators etc

  • - primary and secondary bonding is mechanically sound and correct

  • - panel heaters and fans

  • - ventilation louvers

  • - covers and seals are complete

  • - presence and condition of labels and warning signs

  • - water ingress

  • Check:

  • - operation of all switches, pushbuttons, safety interlocks, voltmeters, ammeters and indicators

  • - function of emergency devices

  • - 20% of all electrical connections. (check all if 5% are found faulty and use thermal imagery on larger panels)

  • - fuses are correct rating and undamaged

  • - plug in components have no signs of visible damage i.e. timers, relays etc

  • - mechanical operation of interlocked isolator / other type of isolator

  • Dry resistance starter - Inspect resistor banks checking for

  • damage /breakdown of insulation

  • overheating

  • cleanliness

  • ALL Contactors - Inspect for

  • general condition

  • overheating

  • Check settings of overload protection devices and record settings

  • Measure primary and secondary earth bonding resistance with calibrated instrument, record and rectify <br>if greater than 0.1Ω.

  • Measure control voltage and report if not within +/- 6%

  • Operate controls in all modes of operation, check for correct operation

  • Check operation of all protective systems i.e. earth fault protection, voltage sensing relays and record <br>settings

  • Check operation of all timers and record settings.

  • Check indicators and meters are operating.

  • Record Hours Run

  • Lubricate door hinges and locks as necessary

  • Clean panels internally and ensure free from debris

  • Clean panel front including indicators

Observations

  • Observation Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Submersible Pump Maintenance - S_PE&00_12E_01A

  • PPM Schedule Ref: S_PEL00_12E_01A - Electric submersible pump annual maintenance

Checks

  • 1. Identify and isolate the pump

  • - water in motor casing

  • - water in seal

  • - water in terminal box

  • - motor temperature thermistors

  • Check Motor Winding Resistance (continuity)

  • L1 - L2 (ohms)

  • L1 - L3 (ohms)

  • L2 - L3 (ohms)

  • Check Motor Insulation Resistance (IR)

  • L1 - E (Mohms)

  • L2 - E (Mohms)

  • L3 - E (Mohms)

  • hours run

  • Open sump (dewater sump if possible) and without entering the space visually inspect:

  • - lifting chains or ropes

  • - guide rails

  • - discharge pipework

  • - power and instrumentation cables

  • - junction boxes

  • Visually inspect supporting steelwork, access ladders, steps, platforms and edge protection for

Pump Inspection

  • What is the motor running current?

  • Is there excessive vibration or noise in the casing and associated pipe work?

  • Have the control and protection equipment been visually inspected and functionally tested?

  • Are the low-level protection settings correct?

  • Are the overload settings correct? Record Readings

  • Are the restart timers working properly?

  • Are the discharge inhibit timers working properly?

  • Is the discharge pipe system visually inspected?

  • Are the siphon breakers and NRVs in good condition?

  • Is the weed screen visually inspected?

  • Is the weed screen mechanically secure?

  • Are the bars on the weed screen evenly spaced and straight?

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Vertical spindle pump annual maintenance - S_PV&00_12E_01A -

  • PPM Schedule Ref: S_PV&00_12E_01A - Vertical spindle pump annual maintenance

Work Schedule

  • If permitted operationally run the pump and check for noise and excessive vibration from the pump and pipework, check the operation of siphon breakers, NRV's, etc. Look for excessive leaking from gland packing, adjust or replace as necessary when the pump is isolated.

  • Check holding down bolts are tight and undamaged.

  • Visually inspect pump casing, structure interface, fixings, and fastenings, check for corrosion, cracks, looseness, and leaks. Check intake pipework, discharge pipework, and fixings for leaks, cracks, damage, and corrosion.

  • For each spindle section, inspect all couplings for looseness, wear, damage to coupling and elements/bushes. Check alignment.

  • Tighten / repack / lubricate gland packing as necessary.

  • Check that any air release holes are clear

  • Oil lubricated bearings only

  • take oil samples for analysis

  • change oil as necessary.

  • ensure that oil is fed to moving parts as required

  • Grease lubricated bearings only

  • inspect lubricator /system checking for correct operation

  • check correct quantity of grease is being delivered at all bearings

  • all pipes are complete, undamaged and unblocked.

  • check grease levels and replenish as necessary.

  • remove excess grease from pump

  • check that individual mechanical lubricators (if fitted) are functioning correctly

  • Inspect top bearing assembly checking for adequate lubrication and shaft nuts are tight /locked

  • Refit guards and covers and confirm completeness and security

  • Turn pump isolator back on if permitted operationally test run pump, check for excessive vibration and noise and operation of siphon breakers, NRV's and associated pumping system components

  • Measure motor running current using calibrated test equipment and compare with panel meter and record hours run

  • Visually inspect and where possible functionally test control and protection equipment control

  • Hours Run

  • start level

  • stop level

  • low level protection

  • overload settings

  • inhibit timers

  • Visually inspect main and supplementary bonding to the pump system

  • Visually inspect weed screen is mechanically secure.

  • bars are evenly spaced and straight

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Pump horizontal centrifugal annual maintenance - S PC&00_12M_01

  • PPM Schedule Ref: S PC&00_12M_01- Pump Horizontal Centrifugal pump annual maintenance

Work Schedule

  • bars are evenly spaced and straight

  • Run pump and check the motor, pump, casing and the associated pipe work for leaks, excessive noise and vibration

  • Isolate the pump

  • Inspect structure: checking for corrosion and security of holding down bolts

  • Take oil samples for analysis. Report to Regional MEICA Engineer (if applicable)

  • Ensure grease is being fed to moving parts as required. Remove excess grease & oil spills from pump

  • Drain voids between bearing and pump housings

  • Check shaft seals and/or gland packing, adjust as necessary

  • Control Panel (if fitted and is not identified as part of Automation General Maintenance Schedule)

  • visually inspect and record the condition of the panel for general condition of enclosure, signs of water ingress, internal equipment, earth bonding

  • check operation of MCB's and RCD's.

  • check for correct fuse rating

  • check operation of all switches, pushbuttons, safety interlocks, and indicators.

  • check function of all emergency stop devices.

  • check operation of interlocked isolator / other type of isolator.

  • check operation and settings of motor overloads.

  • check all motors for continuity of resistance

  • check all motors for continuity of resistance between phase and earth..

  • check cables for vermin damage

  • visually inspect motor casings for damage

  • check operation of motor heaters (if fitted)

  • clean motor cooling fan and vents

  • lubricate motor bearings as required

  • check bearings and seals for looseness.

  • visually inspect and where possible functionally test control and protection equipment

  • inspect couplings and confirm alignment is correct and bolts are tight. Adjust as necessary

  • check all guards are in position and complete

  • turn pump isolator back on

  • if possible, run pump and measure motor running current using test equipment and compare with the panel ammeter

  • visually inspect pipe system, valves, penstocks, siphon breakers, NRVs and associated pumping components

  • visually inspect main and supplementary bonding to the pump system

Test Results & Recordings

Motor Tests

  • Windings - L1 – L2 (Ω)

  • Windings - L1 – L3 (Ω)

  • Windings - L2 – L (Ω)

  • IR L1 to Earth (MΩ)

  • IR L2 to Earth (MΩ)

  • IR L3 to Earth (MΩ)

  • Panel Ammeter (Amps)

  • Hours Run

  • Voltage (Volts)

  • Resistance (Ω)

  • Overload Setting (Amps)

  • Timer Settings (Min/Sec)

  • Thermistor (Ω)

  • Thermocouple (Ω)

  • RTD (Ω)

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Positive displacement pump annual maintenance

  • PPM Schedule Ref: S_PP&00_12M_01A - Positive displacement pump annual maintenance

Motor

  • IR Phase to Phase L1 – L2 MΩ

  • IR Phase to Phase L1 – L3 MΩ

  • IR Phase to Phase L2 – L3 MΩ

  • IR Phase to Earth L1 MΩ

  • IR Phase to Earth L2 MΩ

  • IR Phase to Earth L3 MΩ

  • Motor Heater Resistance Ω

  • Overload Setting (Amps)

  • Motor Running Current (Amps)

  • Panel Ammeter Reading (Amps)

Pump

  • Pressure Readings (Bar)

Controls

  • Restart Timer Settings (Sec/Min)

  • Inhibit Timer Setting (Sec/Min)

  • Start Setting (m)

  • Stop Setting (m)

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Motor LV AC annual maintenance S_M&&00_12E_01A

  • PPM Schedule Ref: S_M&&00_12E_01A - Motor LV AC annual maintenance

Work Schedule

  • If possible, run motor to check for excessive noise or vibration, hot spots in casing. On slip ring motor observe brushes and slip rings for arcing while running

  • Isolate the motor and allow any capacitors or other equipment to discharge prior to commencing removal of covers.

  • Clean any accumulation of dust or fibres on the frame or around the cooling fan inlet.

  • Visually inspect the motor for cracking, signs of significant damage, corrosion of the lifting lugs/eyebolts and loose fasteners and fixings

  • Visually inspect all cables to the motor checking for cracking, rips, twisting, degradation and vermin damage. Ensure glanding is correct and tight

  • Inspect and remove covers for motor terminal box and any other terminal box in the cable run

  • Check internal cables and terminations for signs

  • Check and record :

  • cracking or fretting of insulation

  • insulation breakdown

  • flashover

  • tightness

  • Slip ring motors remove brushgear covers and check:

  • brushes for wear and tensioning vacuum out carbon dust, renew as necessary

  • terminations

  • slip rings for arcing/heat damage, patina

  • brushgear holder fixings for tightness

  • brushgear posts insulation for damage, tracking etc.

  • If motor heaters are fitted check for operation.

  • Check thermistors (if fitted) check resistance and record

  • Check thermocouples (if fitted) check resistance and record

  • Check RTDs (if fitted) check resistance and record

Test Results & Recordings

Motor Tests

  • Windings - L1 – L2 (Ω)

  • Windings - L1 – L3 (Ω)

  • Windings - L2 – L (Ω)

  • IR L1 to Earth (MΩ)

  • IR L2 to Earth (MΩ)

  • IR L3 to Earth (MΩ)

  • Panel Ammeter (Amps)

  • Voltage (Volts)

  • Resistance (Ω)

  • Hours Run

  • Overload Setting (Amps)

  • Timer Settings (Min/Sec)

  • Thermistor (Ω)

  • Thermocouple (Ω)

  • RTD (Ω)

Operating Readings

  • Refit terminal covers and ensure that all seals and glands are complete and correctly fitted.

  • Visually inspect main and supplementary bonding.

  • Rotate rotor and listen to bearings. Inspect for excessive grease on shaft at bearing seals, remove any excessive old grease and re grease as necessary. If rotor is mounted on plumber blocks open and inspect bearings, clean and re-grease as necessary .

  • Inspect automatic greasers (if fitted) adjust and replenish as necessary.

  • Remove drain plug (if fitted) and ensure any water is thoroughly drained off. Ensure all drain holes are clear.

  • Vacuum out any internal dust / debris. If necessary clean cooling fan

  • Check all holding down bolts and coupling fitting for tightness and that they are complete.

  • Turn the motor isolator back on. (only if driven equipment is available to run)

  • If possible run motor to confirm correct operation

  • Measure running current using test equipment and compare with the panel ammeter. (if fitted) and voltages.

  • Visually inspect and where possible functionally test control and protection equipment (if not part of the MCC / control maintenance)

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Automation Relay Control Annual Maintenance - S_TR&00_12E_01A

  • PPM Schedule Ref : S_TR&00_12E_01A - Automation Relay Control Annual Maintenance

  • If you find any item is not in an acceptable condition, please provide full details on report sheet. The range of operating tests is limited to the permitted operation of the equipment, any restrictions are to be noted.

  • Isolate power to the relay compartment and allow any capacitors or other equipment to discharge prior to commencing removal of covers.

  • Panel inspection check for: general condition of the relay compartment.

  • general condition of panel heaters and fans (if fitted).

  • general condition of ventilation louvers and filters (if fitted).

  • covers and seals are complete.

  • presence and condition of labels and warning signs.

  • vermin damage.

  • water ingress.

  • wiring for damage and any signs of overheating.

  • all terminals are adequately shrouded to IP2X and all shrouding is secure.

  • operation of all switches, pushbuttons, safety interlocks, HMI's (where fitted) and indicators, replace indicators as necessary.

  • function of emergency devices.

  • Integrity of all main current carrying terminations and 20% of all other electrical connections. (Check all if any are found faulty).

  • fuses and MCB's check for damage and check against drawings they are correct size, type, rating.

  • plug in components i.e. relays, timers etc. are seated correctly and have no visual signs of damage.

  • mechanical operation of interlocked isolator / other type of isolator.

  • panel cubicle lock(s) are installed; section(s) are locked. Tool or key stored in a central secured cabinet.

  • Inspect wiring for -

  • damage.

  • signs of overheating.

  • Main and supplementary earth bonding -

  • visually inspect all main and supplementary earth bonding to ensure it is mechanically sound, correct, complete and undamaged.

  • measure main and supplementary earth bonding connections resistance with calibrated instrument, record and rectify if greater than 0.050.

  • Lubricate door hinges and locks as necessary.

  • Clean panel compartment(s) internally and ensure free from debris.

  • Clean or replace ventilation filters (if fitted).

  • Clean panel front including indicators.

  • Check mechanical operation of MCB's / switches supplying the control system and its associated equipment.

  • Check and record timer settings. (if fitted).

  • Level probe control relays (if fitted) check for correct operation and record sensitivity setting(s).

  • Inspect surge and Lightening Protection Units (LPU's) (if fitted) for signs of damage and ensure they are correctly connected and earthed.

  • Fit all earthing connections that may have been removed as part of the maintenance inspection.

  • Refit all covers, guards and follow manufacturers recommended procedure for preparing for operation.

  • Restoration of power -

  • Ensure closing and tripping circuits are reinstated. Re-establish power in accordance with SSoW. Check and confirm that the system is live and safe to operate.

  • If operationally permitted, start the plant to confirm correct operation.

  • Live tests - with power supply reinstated measure and record -

  • running current

  • supply voltage

  • UPS voltage (if fitted).

  • control voltage (report if not within +10% and - 6%).

  • UPS (if fitted). Check system is on line and unit indicates fault-free.

  • Check operation of compartment anti-condensation heater and control thermostat (if fitted), check temperature is set as per drawing.

  • Upon completion of maintenance works ensure: the equipment / site is left in a fully operational state. The site is left clean and tidy. all waste arising from maintenance activities is cleared from site. the site is secured on departure.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Level ultrasonic - S_ILU00_06E_01A

  • S_ILU00_06E_01A - Level ultrasonic 6M maintenance

  • Take careful note of all original settings and switch positions. Where applicable, locate and place all automatic control functions to hand / local

  • Visually inspect for damage and security of installation the head and associated cabling.

  • Where fitted check stilling tube and signal path. Clean stilling tube and ensure signal path is clear. (Entry into any stilling chamber that is designated as a confined space requires a separate and specific risk assessment and safe system of work)

  • Locate the ultrasonic unit and, having checked the details against the database, place unit into program mode. Refer to the manufacturer instruction manual where necessary. Report any parameters that are not as per the site data sheet.

  • Where fitted, check the voltage across the memory protection battery. If found to be below 3.00V DC, then replace the battery.

  • Verify level reading in metres ODN, either by reading gauge board or from dipping at a known datum point.

  • Make note of the dipped level and check telemetry reading to ensure that the telemetry reading matches the real value from the field. If there is a discrepancy, alter the relevant parameter to make telemetry reading equal to the dipped / gauge board value. Check the alteration has had the desired effect. Record the new value of the parameter on the site data sheet

  • If no further adjustment is required, return unit to run mode and ensure that reading is correct and stable.

  • Check that any secondary current loops and isolation amplifiers fed by instrument are reading correctly

  • Make note of level and check telemetry reading is correct.

  • Place all automatic equipment back in operational mode as found on arrival

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Level probe - S_ILP00_06I_01A

  • S_ILP00_06I_01A - Level probe float switch 6M maintenance

  • Level Probes

  • Where applicable, locate and place all automatic control functions to hand / local.

  • Clear probes and stilling well of weed, spiders web and any other debris

  • Where necessary flush out stilling well to ensure free flow of water. (entry into any stilling chamber that is designated as a confined space requires a separate and specific risk assessment and safe system of work)

  • Remove probe covers and check that wiring is securely connected and that the termination fittings are complete, free of corrosion and undamaged.

  • Refit probes and verify start, stop settings by reading gauge board or from dipping at a known datum point and measuring probe distance above or below water level.

  • Refit covers and wiring as necessary

  • Check the operation of the conductivity level controller and check that the sensitivity adjustment (if fitted) is suitable for the application

  • Place all automatic equipment into operational mode as found on arrival.

  • Float switch

  • Where applicable, locate and place all automatic control functions to hand/local.

  • Clear switch of weed and other debris attached to it. If necessary; mark position of and lift up to gain access.

  • Check operation of switch by tilting or raising and lowering.

  • Where necessary flush out stilling well to ensure free flow of water. (Entry into any stilling chamber that is designated as a confined space requires a separate and specific risk assessment and safe system of work)

  • Reposition switch and check for security.

  • Place all automatic equipment into operational mode as found on arrival.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Level hydrostatic - S_ILH00_06E_01A

  • S_ILH00_06E_01A - Level hydrostatic 6M maintenance

  • 1. Take careful note of all original settings and switch positions. Where applicable, locate and place all automatic control functions to hand / local.

  • 2. Locate transducer, withdraw from stilling well/disconnect from pipe, wipe and verify sensor details against records, report if not as recorded.

  • 3. Use proprietary cleaning kit to remove any build up on the transducer body or the sensor element. Check physical condition of transducer and cable. Report any item not in an acceptable condition.

  • 4. Where necessary flush out stilling well (ensure sensor is removed) or flush impulse line (entry into any stilling chamber that is designated as a confined space requires a separate and specific risk assessment and safe system of work)

  • 5. Where instrument is loop powered measure voltage and report if out of tolerance

  • 6. Connect the pressure transducer to the calibrated pressure source and carry out a five-point calibration check, referring to manufacturers literature as required. Carry this out for primary and all secondary loops. Adjust as required. Report any problems.

  • 7. Disconnect transducer from test equipment and return it to correct position in stillage well/pipe

  • Verify water level readings in metres ODN, either by reading gauge board or from dipping at a known datum point.

  • Confirm instrument reading is correct, check telemetry reading and adjust/confirm transducer position is correct.

  • Place all automatic equipment into operational mode as found on arrival.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Siren /Motor 3 phase LV annual maintenance - S_QSE00_12E_01

  • PPM Schedule Ref : S_QSE00_12E_01 - Siren /Motor 3 phase LV annual maintenance

  • WORK SCHEDULE

  • 1. If possible (Authorisation must be granted via FIDO or FIM), run siren / motor to check for excessive noise or vibration, hotspots in casing.

  • 2. Isolate the motor and allow any capacitors or other equipment to discharge prior to commencing removal of covers.

  • 3. Clean any accumulation of dust or fibres on the frame or around the cooling fan inlet.

  • 4. Visually inspect the motor for cracking signs of significant damage, corrosion of the lifting lugs/eyebolts and loose fasteners and fixings.

  • 5. Visually inspect all cables to the motor checking for cracking, rips, twisting, degradation and vermin damage. Ensure glanding is correct and tight.

  • 6. Inspect and remove covers for motor terminal box and any other terminal box in the cable run.

  • 7. Check internal cables and terminations for signs:

  • - Cracking or fretting of insulation.

  • - Insulation breakdown.

  • - Flashover.

  • - Tightness.

  • 8. Check and record:

  • - Motor continuity.

  • L1 - L2 (ohms)

  • L1 - L3 (ohms)

  • L2 - L3 (ohms)

  • - Motor Insulation Resistance -

  • L1 - E (M -ohms)

  • L2 - E (M -ohms)

  • L3 - E (M -ohms)

  • 9. If motor heaters are fitted check for operation.

  • 10. Check thermistors (if fitted) check resistance and record

  • 11. Check thermocouples (if fitted) check resistance and record

  • 12. Check RTDs (if fitted) check resistance and record

  • 13. Refit terminal covers and ensure that all seals and glands are complete and correctly fitted.

  • 14. Visually inspect main and supplementary bonding.

  • 15. Rotate rotor / siren and listen to bearings. Inspect for excessive grease on shaft at bearing seals, <br>remove any excessive old grease and regrease as necessary. If rotor is mounted on plumber blocks <br>open and inspect bearings, clean and regrease as necessary . On Siren check for corrosion around <br>edges and sounding area.

  • 16. Confirm correct alignment. Adjust as necessary and record values.

  • 17. Check all holding down bolts and coupling fitting for tightness and that they are complete.

  • 18. Turn the motor isolator back on. (only if driven equipment is available to run)

  • 19. If possible run motor to confirm correct operation

  • 20. Measure running current using test equipment and compare with the panel ammeter. (if fitted) and<br>voltages.

  • 21. Visually inspect and where possible functionally test control and protection equipment (if not part of the MCC / control maintenance)

  •  overload settings

  •  restart timers

  •  thermistors sensors (if fitted)

  •  thermocouple sensors (if fitted)

  •  RTD sensors (if fitted)

  •  voltmeter readings

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Navigation lighting annual maintenance - S_QNL00_12E_01

  • PPM Schedule Ref: S_QNL00_12E_01 - Navigation lighting annual maintenance

Work Schedule

  • Operate the light and confirm the correct operation.

  • Isolate the lighting circuit prior to commencing removal of covers.

  • Clean any accumulation of dust, insects or debris from the frame internal fitting and lighting cover.

  • Visually inspect the light fitting, the reflector (or shield if fitted) and cover for cracking, signs of significant damage and loose fasteners or fixings. Check seals on external covers are sound, replace <br>as necessary

  • Remove lamp(s) from holder(s) and check lamp and contacts for arcing, wear and looseness, if automated lamp changing fitted check the changing mechanism and motor for wear, jamming and signs of overheating. Refit lamps replacing any defunct lamps. Refit all external covers

  • Visually inspect all cables to the light checking for cracking, rips, twisting, degradation and vermin damage. Secure any loose cabling in an appropriate manner. Ensure glanding is correct and tight

  • Inspect and remove covers for lighting control terminal box and any other terminal box in the cable run

  • Check internal cables and terminations for signs

  • cracking or fretting of insulation

  • insulation breakdown

  • flashover

  • tightness

  • Refit terminal covers and ensure that all seals and glands are complete and correctly fitted. In a marine environment protect exposed fixings with Denso tape or grease or equivalent

  • Visually inspect main and supplementary bonding.

  • Turn the lighting isolator back on.

  • Confirm lighting operating correctly. Where an automated lamp changer is fitted rotate the lamps in manual control to ensure all lamps are operational. Return controls to auto after test

  • Visually inspect and where possible functionally test control and protection equipment (if not part of the
    MCC / control maintenance)

  • overload settings

  • voltmeter readings

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Actuation electro-mechanical annual maintenance S_AE&00_12E_01A

  • PPM Schedule Ref: S_AE&00_12E_01A - Actuation electro-mechanical annual maintenance

Work Schedule

  • WORK SCHEDULE

  • If you find any item is not in an acceptable condition please provide full details on report sheet. The range of operating tests is limited to the permitted operation of the equipment, any restrictions are to be noted

  • 1. With the power supply on carry out an external examination including:

  • - general environment and overall condition

  • - fixings and access seals - check cover screws and replace if required

  • - rising stem cover and water ingress to stem tube

  • - cable entries and glanding

  • - indicator glass and lamps

  • - evidence of lubrication to spindle shaft

  • - evidence of oil/ grease leaks

  • 2. Operation of actuator (obtain permission to move) check:

  • - hand wheel operation and condition

  • - local and remote control buttons

  • - auto operation ( by forcing auto control inputs)

  • - check operation of automatic declutching or other manual operation protective devices

  • - accuracy of position indicator devices and gauges

  • With the power supply off and the actuator electrically isolated, carry out an internal examination including :

  • Terminal Section - Pay particular attention to water ingress.

  • Control/ contactors - Check rating of internal fuses

  • For programmable/electronic actuators, some checks are undertaken with the power on.

  • Limit Switches -

  • Check the condition of potentiometer, indicators, and locking nuts of limit switches.

  • check and record the torque trip setting in open and closed positions.

  • Live tests - With the power supply reinstated, measure and record

  • the supply voltage

  • control voltage.

  • Recalibrate positional feedback if necessary and check values with Hydrometry and Telemetry.

  • Running Tests - Check measured values against the site data sheet for the actuator.

  • Monitor noise.

Running Tests

  • Open Time

  • Close Time

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Weedscreen cleaner annual maintenance - S_W&&00_12M_01

  • PPM Schedule Ref: S_W&&00_12M_01A - Weedscreen cleaner annual maintenance

  • Operate weedscreen cleaner check for excessive noise, vibration, ease of travel and operation of brakes. Ensure that weed screen is cleaned of debris before isolating the weedscreen cleaner for Maintenance

  • Inspect the weedscreen checking the bars for straightness, twisting, security, cracks and completeness.

  • Inspect the conditions of any access, supports, ladders, stairs, fixing brackets, anchor points, fasteners and handrails associated with the weedscreen cleaner.

  • Weedscreen cleaner (dependent upon type) :

  • security of holding down bolts.

  • drive chain for wear, distortion, tension, stretch, attachment and lubrication.

  • drive wire ropes. fraying, distortion, tension, stretch, attachment and lubrication

  • wheel wear, corrosion, security of attachment, distortion and completeness and lubrication

  • track / channel for wear, corrosion, security of holding clips, distortion and completeness, for U channels check internally for birds nests and other debris that will interfere with the range of travel

  • rack and pinion drives for wear, corrosion, security of holding clips, distortion and completeness

  • travel stops are complete, secure and in the correct position.

  • travelling carriage frame and covers and component parts for damage, cracks, corrosion, protective coating and security.

  • operate all limit switches and check all striker plates etc for security

  • check grab for alignment and security of tangs

  • lubricate all bearings and greasing points as required.

  • check alignment of gearboxes to driven equipment, adjust as necessary.

  • Hydraulics

  • inspect cylinders checking for leakage, security of fixing and damage.

  • inspect hydraulic pressure relief valves for signs of tampering and report any concerns.

  • inspect and replace filters (as recommended by manufacturer or if pressure differential indicates)

  • inspect pipe, fittings, unions and flexible hoses for leakage, repair or replace as necessary.

  • check the oil level, top up as necessary

  • check that all drains and dump connections are secured with locks and/or plugs.

  • take a sample of oil for analysis, send report to Regional MEICA Engineer.

  • Electrical :

  • visually inspect and record the condition of the panel for general condition of enclosure, signs of water ingress and vermin damage, internal equipment, earth bonding.

  • check operation of MCB's and RCD's.

  • check for correct fuse rating

  • check operation of all switches, pushbuttons, safety interlocks, and indicators.

  • check function of all emergency stop devices.

  • check operation of interlocked isolator / other type of isolator.

  • check operation of motor overloads.

  • inspect catenaries' and cables (if fitted) checking for smooth operation, cable damage and attachment.

  • check cables for vermin damage

  • visually inspect motor casings for damage

  • check operation of motor heaters (if fitted)

  • clean motor cooling fan and vents

  • lubricate motor bearings as required

  • check operation of all brakes, adjust as necessary

  • confirm that motor alignment is correct, adjust as necessary

  • open up and inspect operating pendants, check terminations for security, check pushbutton operators and switch blocks for security

  • Check alignment of gearboxes, motors and brakes, adjust as necessary.

  • Inspect all guards and ensure they are correctly fitted and secure.

  • Check that all safety labels are complete, legible and in place.

  • Travel Motor Test Results

  • Motor Windings L1 – L2 Ω

  • Motor Windings L1 – L3 Ω

  • Motor Windings L2 – L3 Ω

  • IR Phase to Earth L1 MΩ

  • IR Phase to Earth L2 MΩ

  • IR Phase to Earth L3 MΩ

  • Overload Setting (Amps)

  • Motor Running Current (Amps)

  • Hoist Motor Test Results

  • Motor Windings L1 – L2 Ω

  • Motor Windings L1 – L3 Ω

  • Motor Windings L2 – L3 Ω

  • IR Phase to Earth L1 MΩ

  • IR Phase to Earth L2 MΩ

  • IR Phase to Earth L3 MΩ

  • Overload Setting (Amps)

  • Motor Running Current (Amps)

  • HPU Test Results

  • Motor Windings L1 – L2 Ω

  • Motor Windings L1 – L3 Ω

  • Motor Windings L2 – L3 Ω

  • IR Phase to Earth L1 MΩ

  • IR Phase to Earth L2 MΩ

  • IR Phase to Earth L3 MΩ

  • Overload Setting (Amps)

  • Motor Running Current (Amps)

  • Pressure Readings (Bar)

  • Differential Pressure Reading (Bar)

  • New Filter Fitted?

  • Oil Sample Taken?

  • Automated weedscreen cleaners -

  • inspect terminals and any plugs/sockets plug in components i.e. relays, timers etc. are seated correctly and have no visual signs of damage other equipment i.e. heaters, PSU's check mechanical operation of MCB's/ switches supplying the PLC and its associated equipment.

  • visually inspect and check operation of any HMI panel clean HMI display check fuses for correct rating

  • Power the weedscreen back on, for manually operated systems, if permitted operate the system through its full range of operation. Where pendants have more than one operating position, check operation from each pendant station For automated systems initiate a full cleaning cycle and observe that the cycle executes correctly and that trash removed from screen is correctly placed in skip or drying rack. Where automated systems can be operated manually with a pendant repeat as for a manually operated system

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Lifting appliances overhead crane annual electrical & mechanical maintenance - S_LC&00_12EM_01A

  • PPM Schedule Ref: S_LC&00_12EM_01A - Lifting appliances overhead crane annual electrical &mechanical maintenance

  • If you find any item is not in an acceptable condition, please provide full details on report sheet. The range of operating tests is limited to the permitted operation of the equipment, any restrictions are to be noted.

  • Equipment details, check and record make, type, model, serial number, year of manufacture. (where applicable)

  • Visually inspect the condition of access walkways, platforms and other structural items associated with access or operation of the overhead hoist.

  • Visually check and record the general external condition of the mechanical equipment, electrical equipment and control panel(s) of the overhead hoist.

  • Identify the overhead hoist control panel and isolate power to the motor(s) and allow any capacitors or other equipment to discharge prior to commencing removal of covers.

  • General condition of the panel

  • general condition of the equipment, i.e. contactors, capacitors and indicators etc.

  • terminals and any plugs/sockets

  • plug in components i.e. relays, timers etc. are seated correctly and have no visual signs of damage.

  • panel heaters and fans.

  • ventilation louvers and filters.

  • covers and seals are complete.

  • presence and condition of labels and warning signs.

  • vermin damage.

  • water ingress.

  • all terminals are adequately shrouded to IP2X and all shrouding is secure.

  • inspect wiring for damage and signs of overheating

  • operation of all switches, pushbuttons, safety interlocks, HMI’s (where fitted) and indicators, replace indicators as necessary.

  • function of all emergency stop devices.

  • all main current carrying terminations and 20% of all other electrical connections. (Check all if any are found faulty).

  • check mechanical operation of MCB’s / switches supplying the control system and its associated equipment.

  • fuses and MCB’s check for damage and check against drawings they are correct size, type, rating.

  • mechanical operation of interlocked isolator / other type of isolator.

  • Contactors - Ensure the below is checked

  • Over heating

  • working freely

  • functioning correctly

  • contacts not showing signs of pitting

  • evidence of excessive wear

  • all components securley fixed

  • Check settings of overload protection devices and record

  • visually inspect all main and supplementary earth bonding to ensure it is mechanically sound, correct, complete and undamaged.

  • Lifting Equipment Electrical

  • long travel drive & bogie for signs of damage, wear and corrosion.

  • control pendant, control stations and / or remote-control unit and check for damage, broken controls, integrity of support wire.

  • long travel catenary / power collector system for signs of damage, wear and corrosion.

  • operate emergency stop and ensure that hoist cannot operate when activated <br>

  • Support Structure -Visually inspect the condition of the following for signs of damage, wear and corrosion If cracks are observed then prevent the hoist from being used and report immediately to the Supra-Area MEICA Team-Leader.

  • any gantry beams, supports and fishplates.

  • interface of gantry beams with structure.

  • long travel runway beam, any jointing plates and fasteners

  • long travel end stops.

  • long travel carriage and wheels.

  • tighten any loose fasteners and replace missing fasteners.

  • Markings - If any of the above are missing then report immediately to the Supra-Area MEICA Team-Leader

  • check the jib hoist is marked with a SWL and a LOLER ID number

  • check any attached lifting accessories are stamped with a SWL and a LOLER ID number.

  • Lubrication - Oil changes / level(s) top ups _ record volume and type used on record sheet.

  • Operating Hoist - Operate hoist using all operating controls / positions and check for: If defective, report immediately to the Supra-Area MEICA Team-Leader.

  • correct operation, direction of travel and that all motors stop at their limits of travel.

  • check hoist and lower functions, fast/slow/inching if fitted

  • motors stop immediately and brakes operate correctly.

  • operate long travel drive and check for crabbing in both directions.

  • operate cross travel drive and check for crabbing in both directions.

  • check movements of catenary cables, lubricate hangers as necessary.

  • noise and excessive vibration.

  • operate emergency stop and ensure that hoist cannot operate when activated.

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Diesel engine annual maintenance - S_E&&00_12M_01A

  • PPM Schedule Ref: S_E&&00_12M_01A - Diesel engine annual maintenance

Work Schedule

  • Visually check and record general condition of the engine.

  • Exhaust System:

  • inspect the condition of exhaust, support bracket(s), pipes / joints and fasteners.

  • inspect the condition of exhaust guarding and thermal insulation. Ensure both are firmly fixed and correctly positioned.

  • inspect the condition of the silencer (if fitted) and drain any liquid present.

  • ensure all fittings / fasteners are secure.

  • remove spark arrestors. (if fitted)

  • tap to loosen any internal deposits and shake to check internal baffles and to remove deposits.

  • refit

  • with diesel running under load, check for sparks. Renew as necessary. (refer to item 13)

  • check for leaks when diesel engine is running. (refer to item 13)

  • inspect condition of exhaust flap (if fitted)

  • 3. Cooling system (if fitted):

  • check water level and antifreeze / inhibitor concentration and replenish if required. Replace coolant at the manufacturers recommended intervals.

  • check all hoses and hose connections

  • visually check condition of water pump, seals, bearings and any weep holes are clear.

  • check operation of water heater (if fitted).

  • inspect the condition of the radiator and ensure it is not blocked. Check all other pipe work is clear and ensure the pressure cap (valve) functions correctly.

  • inspect the condition of fan blades and safety guarding. Look for looseness and cracks on the blades - clean if required. Ensure guarding is firmly fixed and correctly positioned.

  • inspect all fixing brackets, mountings and clips. Repair minor leaks.

  • Lubrication System :

  • check oil level and replenish if required. Replace engine oil at the manufacturers recommended intervals.

  • check oil heater (if fitted).

  • inspect and replace filters (replace at the manufacturers recommended intervals or when pressure differential indicates the need).

  • visually check condition of external oil pump, seals, oil lubricators and pipe work (if fitted).

  • visually inspect condition of breather system. Ensure breather pipe and gauze element are clean and not blocked.

  • repair minor leaks.

  • Fuel System :

  • check fuel tank level and condition of fuel, take sample of existing fuel for analysis - results of sample to be sent to the Regional MEICA Engineer. (Only completed on Major Annual Service)

  • inspect condition of fuel tank, fixing brackets, mountings, valves and filler cap.

  • inspect fuel tank atmospheric vent. Ensure it is clean and not blocked.

  • inspect the fuel filter(s). Clean or replace (at the manufacturers recommended intervals).

  • visually check the fuel injection pump and mountings. Clean fuel pump filter or replace (at the manufacturers recommended intervals) pump filter.

  • inspect all fuel lines and repair minor leaks.

  • inspect condition of any bund areas. Look for cracks or other damage where a spillage of fuel could escape.

  • check function of bund monitoring/alarm system if fitted

  • inspect emergency fuel cut-off system (if fitted). Check cables, counterbalance, pulleys and fusible links.

  • Air System :

  • inspect air filter and clean or replace (at the manufacturers recommended intervals).

  • visually check the condition of air manifold and joints.

  • at the manufacturers recommended intervals inspect the turbocharger compressor (if fitted) in accordance with manufactures instructions.

  • check air flap valve (if fitted) Do not test with engine running as it may cause oil carry over into the exhaust system and damage the diesel engine.

  • Engine

  • inspect the main engine mountings, anti-vibration mountings, enclosure cover and any additional heat shield covers for signs of wear or corrosion.

  • inspect engine linkages, lubricate if required

  • inspect engine breather (if fitted). Replace if required by manufacturers recommendations.

  • clean and inspect the turbocharger impeller and compressor casings (if fitted).

  • inspect all pulleys wheels, auxiliary drive belt(s) and adjust tension if necessary (replace belt(s) at the manufacturers recommended intervals).

  • check operation of the starter motor(s) electric, hydraulic or pneumatic.

  • inspect governor.

  • check all connectors are undamaged and securely fixed

  • covers are undamaged, secure and complete

  • Mechanical :

  • check all springs, linkages for correct movement. Lubricate as necessary

  • covers are undamaged, secure and complete

  • screw adjusters are secure and locked in position

  • Inspect mechanical over speed trip mechanism (if fitted)

  • Batteries :

  • check that the battery charger is working.

  • check that the charger volt and ammeters (if fitted) are registering the correct readings.

  • inspect batteries for signs of overheating and bulges and vents are clear.

  • check terminal connections for tightness and corrosion

  • check cables for fraying and corrosion.

  • check electrolyte level, top up as necessary

  • Clutch :

  • inspect clutch assembly.

  • lubricate bearings and linkages as necessary

  • clean out clutch housing and clear vent and drain holes

  • operate and adjust clutch as necessary checking for a smooth operation.

  • Acoustic Enclosure (if fitted)

  • inspect enclosure doors for looseness and fit, adjust as necessary

  • inspect door stays and gas springs and check that doors remain open, repair/replace as necessary

  • check ventilation vents are not blocked

  • if fitted check condition of all ventilation louvers and ensure free from obstructions, check operation of automatic louvers and grease if necessary.

  • check acoustic material and protective covering for tears and punctures, repair/replace to prevent accumulation of liquids or oil film within the material.

  • 11. Instrumentation

  • check all instrumentation is undamaged and functional, check against test instrument and replace as necessary. Record readings whilst diesel engine is running. (refer to item 13)

  • inspect all switches and check for correct operation.

  • General

  • visually inspect the condition of any permanent lifting brackets, check for corrosion and comment on any deficiencies.

  • check operation of all emergency stop button positions

  • check operation of pre-heater (if fitted)

  • visually check condition of all electrical cable, glands and conduit

  • inspect condition of all spill trays and check all are secure, drain off any fluid.

  • check condition of all warning and safety signs associated with the equipment.

  • ensure engine room / enclosure is clean and tidy.

  • report any concerns about any piece of equipment.

  • (Item 13) Start Engine & Test Run

  • check that all parts of the engine are functioning correctly and free from leaks.

  • ensure engine operates to manufacturers recommendations, adjust any settings accordingly

  • report any concerns i.e. excess vibration, noise or visual appearance of exhaust emissions.

  • Where possible run for at least 30 minutes and on load

Items Fitted

  • Lubrication Oil Filter

  • Air Filter

  • Engine Breather

  • Drive Belts

Readings

  • Battery Voltage (Volts)

  • Battery Charger Voltage (Volts)

  • Battery Charger Amperage (Amps)

  • Hours Run (Hours)

  • Engine Speed (rpm)

  • Engine Oil Pressure (Bar psi)

  • Engine Oil Temperature (ºC)

  • Engine Cooling Water Temperature (ºC)

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Site safety and operational inspection - S_X&&_6G_02

  • PPM Schedule Ref: S_X&&_6G_02 - Site safety and operational inspection

Work Schedule

  • WORK SCHEDULE

  • 1. Liaise with site operator and check and report on any operational problems over the previous 6 months.

  • 2. Visually inspect MEICA equipment for signs of damage.

  • check external enclosures and equipment housings

  • isolate electrical enclosures and visually check internal cabling and equipment within enclosures for vermin, heat and water damage

  • 3. Check operation of equipment locks and lubricate if required.

  • 4. Check equipment fluid levels and top up if required. Contain and report leaks

  • 5. Check any fuel or lubricating oil storage or other bunded systems. Check overfill alarms and level indication

  • 6. Check internal and external lighting (replace if so instructed by MEICA team). Check that emergency lighting test records are completed as required.

  • Check control panel indication lights (press to test or lamp test)

  • Check machinery guards and equipment barriers for integrity and operation of interlocks

  • Check operation of equipment - test start and stop plant to prove initial operation and functional controls. Operate valves, siphon breakers, and other manual control devices.

  • Check operation of critical safety devices such as emergency stops, interlocks and functional isolators.

  • Check ventilation systems and heating systems

  • Inspect signage and labelling, report if missing or damaged

  • Check the condition of any weed screens, booms or safety screens

  • Check the visible inspection status of equipment subject to the following regulations:

  • EAWR (PEE)

  • LOLER

  • PSSR

  • Check instrumentation level and position readings against the actual values.

Observations

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Gearbox - S_R&&00_12M_01A - Gearbox annual maintenance

  • PPM Schedule Ref: Gearbox - all types annual maintenance

Work Schedule -

  • Operate equipment to check for vibration and noise

  • Inspect input and output shafts and access seals for leakage and if possible adjust to correct or otherwise report the defect

  • Operate any manual or alternative drive input system checking any interlocks or remote indicators that should operate when alternative drives combinations are used. check that any clutches or gear changes are working effectively

  • If oil temperature gauges are fitted check that they are intact and indicate a sensible ambient temperature. Where oil level sight glasses are fitted check for opacity - replace as necessary

  • Forced lubrication systems:

  • check spray heads are clear and oil is discharging as required.

  • inspect and replace filters (replace at the manufacturers recommended intervals or when pressure differential indicates the need)

  • check the operation of any pressure gauges through the normal operation of the equipment.

  • Remove gauges for further "dead weight" testing if they appear faulty.

  • take a sample of the oil for analysis. Report to be sent to the Regional MEICA Engineer

  • check and if required top up the oil level.

  • inspect any sealing devices that prevent dirt and moisture ingress

  • Non-sealed grease lubricated systems

  • clean away any excess grease

  • prove the greasing points are clear and if required apply grease

  • if required replace canister auto greasing units

  • if required top up auto greasing units

  • Splash lubricated systems

  • check the oil level and top up if required

  • inspect the oil reservoir for signs of moisture ingress

  • Inspect any guards and ensure they are correctly fitted and secure

  • Inspect input and output couplings for wear and unacceptable backlash

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Penstock 6M maintenance - S_GP&00_06M_01A

  • PPM Schedule Ref: S_GP&00_06M_01A - Penstock 6M maintenance

Visual Checks

  • Visually inspect to ensure door to spindle attachment is secure and undamaged before attempting to operate.

  • Grease and operate the penstock. Note any backlash, juddering, jumping or noisy operation of moving parts.

  • Check for leakage between frame & structure.

  • Check for leakage between door & frame.

  • Isolate electrics if required according to written procedures.

  • NON- RISING STEM- Badly worn threads may not support the weight of the door and could fail causing the door to fall without warning

  • Lubricate or grease all moving parts as required including the thrust collar using the grease points supplied.

  • Inspect hand wheel / winding handle is fit for purpose (also keyways and splines etc if handle is not permanent)

  • Check power pack/gearbox/extension drive spindles etc are secure and are fit for purpose

  • Check electric actuators and /or gearboxes for excessive noise while operating and test all limits and torque settings.

  • RISING STEM-As for Check 6 above.

  • Check lead screw attachment to gate

  • Check for damage to door guides & to seals on door & frame

  • Report on any visible corrosion, wear & tear on protective coatings, cracks, chips, broken castings

  • On completion of maintenance checks test the operation of penstock using actuator (electric or hydraulic) or manually

Observations

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Vertical mitre gate annual maintenance - S_GM&00_12M_01

  • PPM Schedule Ref: S_GM&00_12M_01 - Vertical mitre gate annual maintenance

Work Schedule

  • Visually inspect the condition of access walkways, platforms and other structural items associated with access or operation of the gate.

  • Visually inspect the gate as far as practicable without removing any operating equipment.

  • Check each gate for impact damage, corrosion and/or wood decay. Report on the condition of the gate, paint system and / or cathodic protection.

  • Check top hinges for looseness, wear, and corrosion and that attachments are complete and secure. Report any abnormalities.

  • Check pintle /bottom bearing if exposed at low water.

  • For counterbalanced gates check that the weight attachment wire ropes/chains are secure and that there are no signs of overstretching or overloading. Inspect wire ropes or chains for defects and report.

  • Check pulley arrangements are complete and fully operable, grease as necessary.

  • For linear actuation such as hydraulic rams, screwed rods or racks, the pivot arrangements are critical to ensure that no bending moments are applied. Check pivot arrangements and ensure that any arrangements are clear and working.

  • Check lubrication points are unblocked and any automatic lubricating arrangements are functioning, top up lubricant if necessary.

  • Inspect all guarding and ensure it is firmly fixed and correctly positioned. If access points are provided for maintenance inside the guarding, ensure they are accessible, and if they incorporate disabling. interlocks test that these work.

  • Operate the gate and check that each gate mitres correctly in the central position and that there is not an excessive vertical gap. Report any abnormalities.

  • Comment on the apparent condition of the gate seals either by visual inspection or assessment of leakage.

  • Inspect and if possible use any equipment designed for latching or locking the gate into a fixed position. In some cases latching pins are actuated and these should be inspected for operation and adjusted as required. Any obvious deterioration in the arrangement that could reduce the effectiveness of the latch to hold the weight must be reported.

  • For gates fitted with accessible buoyancy chambers dip the chamber to check for water leaks.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Gate annual maintenance - S_G&&00_12M_01A

  • PPM Schedule Ref: S_G&&00_12M_01-Gate annual maintenance

Work Schedule

  • Visually inspect the condition of access walkways, platforms and other structural items associated with access or operation of the gate.

  • Check operation of limit switches

  • Visually inspect winding gear drums, support bearings, gearboxes, plumber blocks couplings etc and ensure any oil and grease lubrication points are unblocked and any automatic lubricating arrangements are functioning and charged with lubricant. Inspect and adjust brakes

  • Visually inspect the gate lifting equipment as far as you are able to do so without fully removing any chains, racks or lifting ropes. Lubricate as required and comment on any deficiency in routine operator lubrication.

  • for wire ropes check for evidence of surface corrosion, broken strands and the lay of the rope onto any winding gear. Any separation of the wire rope strands should be reported. Pay particular attention to shackles and other points of connection.

  • for transmission type chains check as far as you are able for general lubrication on all links that are required to be flexible. Report any link that has seized.

  • for racks and screws the wear on the drive nut or drive pinion is important. If possible inspect the wear or assess it by estimating the backlash. Report any concerns

  • for linear actuation such as hydraulic rams, screwed rods or racks the pivot arrangements are critical to ensure no bending moments are applied. Check and inspect pivot arrangements and ensure that any lubrication arrangements are clear and working.

  • Inspect the guarding and ensure it is firmly fixed and correctly positioned.

  • if access points are provided for maintenance inside the guarding, ensure they are accessible and if they incorporate disabling interlocks test that these work.

  • Obtain permission of site responsible officer or FIDO then operate the gate. Inspect and report on the condition of the paint system and / or cathodic protection

  • Comment on the apparent condition of the gate seals either by visual inspection or assessment of leakage, for tilting gates pay particular attention to the lower pivot seal

  • Check and adjust any sealing glands, for some types or torque tube gate the shaft seal is critical to the integrity of the dry well - check the seal and assess the rate of leakage if any.

  • Inspect and if possible, use any equipment designed for latching or locking the gate into a fixed position. In some cases latching pins are actuated and these should be inspected for operation and adjusted as required. Any obvious deterioration in the arrangement that could reduce the effectiveness of the latch to hold the weight must be reported.

  • Inspect any mechanical torque limiting devices, slipping clutches may be present and the adjustment of them is critical to there operating limits. Ensure that any adjustment locking arrangements are secure and report any evidence that torque settings have been tampered with.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Tidal large flap valves / Gate - S_GF&00_12M_01A

  • PPM Schedule Ref: S_GF&00_12M_01A - Tidal large flap valves annual maintenance

Work Schedule

  • WORK SCHEDULE

  • 1. Carry out the following tasks and checks: note any exceptions or any items that cannot be completed due to site conditions

  • 2. Where fitted, visually check the condition of the winch, its wire rope or chain, for mechanical winches check that the locking pawl system works prior to raising the flap. Raise the flap & flush through to clear silt & debris (if required.)

  • NEVER WINCH THE FLAP OPEN AGAINST A POSITIVE HEAD. THE ON & OFF SEATING HEADS MUST BE BALANCED.

  • 3. Hose down the flap to remove silt and debris and allow clear access for inspection. (assess the potential pollution arising from the disturbance of silt and debris and seek advice if there is a notable pollution risk)

  • 4. Inspect the flap lifting equipment

  • check the flap cast/fabricated-lifting eye or screwed eyebolt is fit for the purpose of lifting the flap.

  • check lifting chains, wire ropes & fittings are fit for purpose.

  • if a blind threaded eyebolt is fitted, this is to be removed and checked and comments made on the report. It is advisable that the screwed hole in the flap be drilled through, a suitable backing plate provided and an eye bolt pin passed through & secured using compatible nut and washer. (This modification will require a new job number and you must seek the approval of the Regional MEICA Engineer before proceeding.)

  • undefined

  • 5. Check for damage to seals on flap & frame

  • 6. Check for worn or damaged parts on the operating linkage & for freedom of movement

  • 7. Check all grease lines if fitted for corrosion, kinks, flats, splits & missing pipe clips

  • 8. Lubricate or grease all moving parts as required, checking that grease is reaching all the mechanisms

  • 9. Check for missing or damaged grout between frame & structure. Make good any faults.

  • 10. Check the tightness of all fasteners.

  • 11. Close flap & check for leaks by using the POSITIVE IN head (this may require a return visit when water levels are suitable)

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Mechanical Isolation Valve - S_PXI00_12M_01

  • PPM Schedule Ref: S_PXI00_12M_01 - Mechanical Isolation valve annual

Work Schedules

  • Check outer casing for damage, blistering of surface or corrosion.

  • Check flanges and bolted connections for leakage, damage or corrosion.

  • Check valve stem for leakage, replace any stem packing as necessary. Check valve hand-wheel (or lever) for completeness and security to stem.

  • Check security of any locking mechanism fitted

  • Grease valve if required.

  • Note valve position and if operational conditions permit, move valve through complete range of movement and return to original position. Note any leakage past stem or valve in fully closed position

  • If valve had been secured in a particular position then return to position and secure

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Mechanical siphon breaker annual - S_PXS00_12M_01A

  • PPM Schedule Ref: S_PXS00_12M_01A - Mechanical siphon breaker annual

Work Schedule

  • Inspect structure, checking for corrosion and security of attachment bolts.

  • Ensure valve positioning is correct.

  • Check bend and flange assembly is free of debris.

  • Operate paddle flap manually and ensure free moving, apply grease if necessary. Check any counterbalance weight is complete, secure and unhindered in its movement

  • Check mesh over vents is complete, secure and free from debris

  • Check that any external guarding is complete and secure

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Mechanical Non-Return Valve annual - S_PXN00_12M_01A

  • PPM Schedule Ref: S_PXN00_12M_01A - Mechanical Non-Return Valve annual

Work Schedule -

  • If you find any item is not in an acceptable condition please provide full details on report sheet. The range of operating tests is limited to the permitted operation of the equipment, any restrictions are to be noted. Pump must be isolated electrically before commencing checks

  • Check outer casing for damage, blistering of surface or corrosion.

  • Check flanges and bolted connections for leakage, damage or corrosion.

  • Check valve shaft for leakage, damage or corrosion. Check bonnet seals for leakage.

  • Check valve lever and/or weight for completeness and security to shaft. Check security of any lever.

  • cage or protection

  • Grease valve if required.

  • Note valve position and if operational conditions permit, start and stop pumps to test the operation of the valve. Check valve seating position and note any leakage past valve in fully closed position

  • Replace all levers, cages, fittings and secure.

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Pedestrian or Vehicular Gate annual maintenance - S_GW&00_12M_01A

  • PPM Schedule Ref: S_GW&00_12M_01A- Pedestrian or Vehicular Gate annual maintenance

Work Schedule

  • Sweep clear of all debris on gate sill, plates, rails and hinges

  • Inspect sill, plates, rails etc checking for completeness, condition of protective coating (paint), corrosion, wear, distortion, cracking, and security. Report defects.

  • Inspect gate(s) checking for security, completeness, condition of protective coating (paint), corrosion distortion and cracking and security. Report defects.

  • Inspect attachments to the flood wall (including guide roller if fitted) checking for completeness, condition of protective coating, corrosion, distortion, cracking and security. Report defects.

  • Sliding gates

  • inspect rails and wheels checking for completeness, bearing wear, damage, blockages, alignment and security. Lubricate wheels as necessary

  • inspect gate buffer blocks (if fitted) checking for completeness, distortion and security.

  • inspect gate location tapers and/or rubbing strips checking for completeness, distortion and security.

  • inspect integral winches (where fitted) for completeness, wear, corrosion, security and distortion.

  • inspect gate pulling points, shackles and ropes checking for completeness, wear, corrosion, security and distortion

  • check securing mechanisms

  • 6. Hinged gates

  • inspect hinges checking for smooth operation, wear, damage and alignment. Lubricate as necessary

  • inspect hinge alignment mechanism (if fitted) checking for completeness, condition of protective coating (paint), distortion, cracking and security.

  • if gate is fitted with hinge lifting mechanisms to assist closure check for completeness, wear,

  • damage and functionality.

  • check securing and dogging mechanisms, lubricate as necessary

  • Inspect seals, seal covers and operating mechanisms (if fitted) checking for completeness, wear, damage and alignment. Lubricate as necessary and report defects.

  • Close gate in accordance with operating procedures and check for smooth operation, support / guide

  • Wheel functions correctly and seals fit. Check hazard warning markings, signs and hazard reflectors where fitted Report defects.

  • Check integrity of collision bollards and other defences , report defects

  • If necessary adjust hinge alignment mechanism (if fitted) to align gate to ensure correct operation.

  • If necessary adjust seals.

  • Inspect gate locking mechanism checking for completeness, wear and damage. Report defects.

  • Grease all greasing points and exposed threads.

  • Open gate in line with operating procedures and lock in position.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Gate stoplogs and lasherboards annual maintenance - S GL&00 12M 01A

  • PPM Schedule Ref: S GL&00 12M 01A - Gate stoplogs and lasherboards annual maintenance

Work Schedule

  • Stop logs:- metal

  • 1. Inspect stop log checking for damage, distortion corrosion and completeness. Report and rectify as necessary

  • 2. Inspect guides checking for security, smooth rotation, corrosion. Lubricate bearings (if fitted). Report and rectify as necessary

  • 3. Inspect all rubber seals, (if fitted) checking for rips, tears, distortion and for firm attachment. Rectify as necessary

  • 4. Inspect all wooden bearers (if fitted) checking for distortion, rot, completeness, correct positioning and for firm attachment. Rectify as necessary

  • 5. Inspect lifting points checking for excessive wear. Distortion and damage to welds.

  • 6. Inspect guide cones (if fitted). Checking for completeness, damaged and attachment to stop log.

  • 7. Check protective coating. Repair minor damage as necessary. Report severe damage.

  • 8. Check storage rack (if used) for damage, corrosion security and completeness. Rectify as necessary

  • Stop logs:- wooden

  • 1. Inspect stop log checking for damage, rot, distortion, warping

  • 2. Inspect guides (if fitted), checking for security, smooth rotation, corrosion. Lubricate bearings (if fitted). Report and rectify as necessary

  • 3. Inspect lifting points checking for secure attachment, corrosion and completeness

  • 4. Inspect all rubber seals, (if fitted) checking for rips, tears, distortion and for firm attachment. Rectify as necessary

  • 5. Check general dimensions to ensure no unauthorized modifications have been made

  • 6. Apply wood preservation material as necessary. Allow to fully penetrate and dry before using stop log in water course

  • 7. Check storage rack (if used) for damage, corrosion, security, and completeness. Rectify as necessary

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Navigation booms,Wire Ropes & Chains annual maintenance - S_QNB00_12M_01

  • PPM Schedule Ref: S_QNB00_12M_01 - Navigation booms,Wire Ropes & Chains annual maintenance -

Work Schedule -

  • Access boom by agreed method

  • Clear boom of any build up of debris and marine life

  • Inspect anchor posts; checking for

  • - Corrosion

  • - Excessive wear

  • - Completeness and security of attachment bolts.

  • Check wire ropes (if fitted) for

  • - Corrosion

  • - Broken strands

  • - Integrity of end fittings

  • Check chains (if fitted) for

  • - Corrosion

  • - Excessive wear

  • - Areas of weakness and necking

  • Check floats for

  • Impact damage

  • Attachment points are complete and secure

  • Tears and holes

  • Sharp edges

  • Buoyancy

  • Inspect grab ropes for

  • Security

  • Completeness

  • Wear and material breakdown

  • Leakage

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Drive Chains and Sprockets - S_RDC00_12M_01

  • PPM Schedule Ref: S_RDC00_12M_01A - Drive Chains and Sprockets Annual Maintenance

Work Schedule

  • 1. Inspect structure, checking for corrosion and security of attachment bolts.

  • 2. Check chains for damage, elongation of links, and any signs of stretching.

  • 3. Check chain guides.

  • 4. Lubricate chains.

  • 5. Check sprockets for damage, missing teeth, and corrosion.

  • 6. Check sprockets fixing to driveshaft, keyway, and securing bolts for signs of damage and wear.

  • 7. Lubricate sprockets.

  • 8. Check chain securing links, lugs, and points for damage, elongation, and any signs of stretching.

  • 9. If grease nipples are located remote to equipment. Check grease nipples, associated piping and couplings for damage, fractures and leakage. Check for delivery of lubricant at equipment

  • 10. Check that all associated guards are in place and undamaged.

  • 11. Test operate the gate.

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

Ropes and Pulleys S_LF&00_12M_02A

  • PPM Schedule Ref: Ropes & pullies Annual maintenance

Visual Checks

  • Support Structure

  • Covers and Guards

  • Lifting equipment

  • Wire ropes and pullies

  • Lifting Chains

  • Gears

  • Sprockets

  • Markings

  • Lubricate

  • Tightness of Fasteners

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Lifting Ropes and Drums

  • PPM Schedule Ref: Wire Rope Annual Maintenance

Visual Checks

  • Visual Inspection

  • Operation of limit switches

  • Winding gear

  • Lifting equipment

  • Wire ropes and pullies

  • Lifting Chains

  • Racks and screws

  • Guarding

  • Gears

  • Sprockets

  • Markings

  • Lubricate

  • Latching and locking

  • Tightness of Fasteners

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Winches Mechanical - S_LF&00_12M-01A

  • PPM Schedule Ref: Winches Annual maintenance

Visual Checks

  • Visually check and record general condition of the winch.

  • Winch frame inspect the following for signs of damage, wear and corrosion:

  • - fixing brackets

  • - anchor points

  • - fasteners

  • - tighten any loose fasteners found

  • - replace any missing fasteners

  • Covers and guards visually inspect for:

  • - indications of impact damage

  • - areas of rubbing on moving parts

  • - completeness

  • - security

  • - if interlocks are fitted check these work

  • Gears:

  • - remove all hardened grease from the gears

  • - inspect gears checking for cracks broken teeth, looseness and misalignment

  • - lubricate gears

  • inspect bearings / bushes for wear, cracks, corrosion.

  • inspect brackets for cracks, corrosion and damage.

  • ensure any oil and grease lubrication points are unblocked.

  • lubricate bearings /bushes

  • Winch drum visually inspect -

  • lubricate where necessary

  • inspect bearings / bushes for wear, cracks, corrosion.

  • inspect brackets for cracks, corrosion and damage.

  • ensure any oil and grease lubrication points are unblocked.

  • lubricate bearings /bushes

  • Operating handle(s) -

  • inspect handle, checking for cracks, excessive wear, and completeness.

  • inspect shaft drive - ensure full engagement of handle to all drives shafts (if more than one option)

  • operate the winch to evenly distribute the new grease on the gears.

  • Pawl mechanism (if fitted) -

  • inspect pawl for completeness, damage, broken teeth, corrosion and freedom of movement.

  • inspect ratchet for completeness, damage, broken teeth, corrosion and freedom of movement.

  • check operation of pawl and ratchet, ensure full engagement when under load.

  • Brake (if fitted) -

  • brush clean any rust from the brake.

  • adjust brake band to suit.

  • turn winch to check for adequate friction.

  • Attachment -

  • inspect rope/chain attachment for damage, looseness and corrosion.

  • inspect shackles for completeness, distortion and corrosion.

  • Wire ropes (if fitted) visually -

  • inspect rope, checking for surface corrosion, fraying, broken strands, separation of strands and distortion.

  • check that rope is correctly attached to the drum.

  • check that the lay of the rope is evenly located on the drum

  • lubricate chain as necessary.

  • Chains (if fitted) visually -

  • inspect chain, checking for fraying wear, elongation, necking distortion and security of fixings.

  • check that the chain is correctly attached to the drum.

  • check that chain is evenly located on the drum.

  • lubricate chain as necessary.

  • Fairlead (if fitted) -

  • inspect for completeness and damage.

  • ensure guide wheel moves and rotates freely.

  • lubricate as necessary.

  • Check the wire lifting rope is stamped with a SWL and LOLER ID number. Report immediately to the Regional MEICA Engineer if either is missing.

  • Manually operate winch system to ensure free and easy movement.

  • Inspect and record condition of any access walkways, supports, fixing brackets, fastenings and handrails associated with the winch system. Tighten any loose fasteners.

  • Check the condition of all warning and safety signs associated with the equipment.

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Lifting appliances davit annual maintenance - S_LD&00_12M_01

  • PPM Schedule Ref: Lifting appliances davit annual maintenance - S_LD&00_12M_01

Work Schedule

  • 1. Visually check and record general condition of the davit.

  • 2. Support structure. Inspect the following for signs of damage, wear and corrosion

  • - anchor points

  • - fasteners

  • - tighten loose fasteners

  • 3. Davit sockets the site may have more than one socket for each davit

  • - inspect and clean debris from all davit sockets

  • - where davit sockets have covers ensure they are intact and free to move lubricate as necessary

  • - clear davit socket drain holes

  • - proof load test davit sockets

  • - check the davit socket is stamped with a SWL and a LOLER ID number

  • 4. Davit assemblies - disassemble all davit sections and visually inspect for

  • indications of impact damage

  • - cracks defective welds.

  • - areas of excessive rubbing on moving parts.

  • - completeness

  • - corrosion

  •  check that all removable parts and safety fittings are fitted, undamaged and complete.

  • Reassemble

  •  lubricate sections and fittings as necessary

  •  ensure correct fit into all sockets

  •  manually move davit through the full arc of travel to ensure free and easy movement

  • 5. Lifting equipment (manual operation)

  • inspect the condition of the following for damage, wear, distortion and corrosion

  •  davit

  •  overhead trolley (including wheels and gears)

  •  inspect hoist operating chain for wear, elongation, necking and distortion.

  •  operate and check for smooth operation and correct alignment of chain to gear drive wheel.

  • If defective, report immediately to the Regional MEICA Engineer

  • 6. Lifting accessories

  •  inspect for condition and completeness

  •  check for damage and corrosion.

  • If defective report immediately to the Regional MEICA Engineer.

  • 7. Markings

  • check the davit arm is marked with a SWL and a LOLER ID number

  •  check any attached lifting accessories are stamped with a SWL and a LOLER ID number.

  • If any of the above is missing then report immediately to the Regional MEICA Engineer

  • 8. Walkways

  •  inspect the conditions of any access, supports, fixing brackets, anchor points, fasteners <br>and handrails associated with the davit arm/jib.

  • 9. Report on the condition of the paint /protection system for the structure

  • 10. Check the condition of all warning and safety signs associated with the equipment

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Hydraulic Systems - S_Y&&00_12M_01

  • PPM Schedule Ref: Hydraulic Actuator - all types annual maintenance

Visual Checks

  • Inspect any guards and ensure they are correctly fitted and secure

  • Where systems contain accumulators – check that PSSR inspection labels are in date.

  • Check the operation of manually operable system valves

  • Check the operation of automatic and control valves

  • Inspect hydraulic pressure relief valves

  • Operate equipment to check for vibration and noise

  • Inspect extending ram gaiters

  • Operate manual/alternative drives

  • Replace filters

  • Operation of pressure gauges

  • Oil sample / Oil level

  • Grease points clear

  • Replace/top up grease units

  • Oil Level

  • Moisture ingress

  • Drain any water from the oil reservoir

Observations

  • Observations Report

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Basic Steel Structure Maintenance - S_BS&00_12M_01A

  • PPM Schedule Ref: S_BS&00_12M_01A - Basic Steel Structure Maintenance

Work Schedule

  • WORK SCHEDULE

  • 1. Access of steel structure by agreed method

  • 2. Clear structure of any build up of debris.

  • 3. Inspect metal fixing components; checking for

  • Corrosion,

  • Excessive wear,

  • Completeness and security of attachment bolts.

  • If required, coat metal objects with a suitable protective barrier.

  • 4. Inspect anchor posts; checking for

  • Corrosion

  • Excessive wear.

  • Completeness and security of attachment bolts.

  • For all of the structures; check for

  • - Corrosion

  • - Excessive wear

  • - Completeness and security of attachment bolts

  • For Piled structures; check

  • - Pile Brackets should be checked for the connections to the structure. Any walkway hinge brackets should be checked & greased with a suitable product.

  • - Check any bolts holding any cleats to make sure they are tight. If there are any power/water connections make sure that the cables & pipes are still secured in the saddles under the gangway and make sure that there are no loose connections to taps & power points

  • For Strut structures; check

  • - Check that the Strut & Walkway hinge connections are greased with a suitable product and that there are no loose bolts or pins. Also ensure that cables are tight by adjusting them at the turnbuckles. Turnbuckles should be coated with a suitable lubricant.

  • Handrailing

  • Undertake a visual inspection on the handrailing; checking that the railing is secure, undamaged and no parts are missing. Tighten any loose rails and replace any missing rails you notice.

  • - Check the anchor points for security, check mounting bolts. Tighten any loose mounting bolts noted.

  • Steel Walkways

  • Undertake a visual inspection of the walkway to ensure that no plates are missing / damaged. Replace any damaged / missing plates. Check the overall security of the walkway identifying any loose plates. If plates are loose then check the tie downs are tight and not missing. If necessary tighten and / or replace tie downs.

  • - Check the security of any kickboards present and undertake remedial action if necessary.

  • - If the walkways are bolted to a subface, check bolts/ nuts for corrosion and tightness. Replace any missing / corroded bolts and tighten bolts / nuts if necessary.

  • - Undertake visual inspection on all vertical uprights used to support the walkways, check any securing bolts for tightness and completeness. Tighten loose bolts and replace any missing bolts.

  • - Check for missing or damaged grout and packing between the frame and structure. Make good any faults.

  • Vertical Ladders

  • Undertake a visual inspection of the ladder to ensure it is complete, no rungs are broken and that it is securely attached to the subface. Also check for any corrosion that may be visible on the ladder.

  • - Check the security of the mounting brackets and check the tightness of all mounting bolts / nuts. If necessary tighten.

  • Steel Stairs

  • Visually inspect the stairs looking for damage and security. Repair any damage you notice and tighten all joints you notice.

  • Check any attached handrailing for security and undertake remedial action if railing is not secure.

  • Visually inspect the weedscreen to ensure it is mechanically secure, complete and the bars are evenly spaced and straight.

  • Check cables (if fitted) for

  • corrosion,

  • wear,

  • broken strands,

  • deformation,

  • heat influence,

  • elongation,

  • necking,

  • distortion,

  • and integrity of end fittings.

  • Check chains (if fitted)

  • for corrosion,

  • excessive wear,

  • areas of weakness, and necking.

Observations

  • Cause

  • Effect

  • Likelihood of Failure

  • Add Time to Repair

  • Status

  • Outcome of PPM inspection

  • Asset Condition and Comments

  • undefined

Operational Functional Testing

  • Test and prove winches, penstocks, flaps and pumps on completion of maintenance.

  • Site left proved and working

  • Auto operation available - system healthy

  • Site has recently been under water

Building and Grounds

  • Heating functioning, building dry

  • Compound secure, cabinets locked

  • All safety notices clearly displayed

  • Building and assets clean & tidy

  • Filters cleaned and no vermin

New assets identified

  • Any new assets identified?

  • Enter asset information

  • Asset
  • Description

  • Asset Condition

  • undefined

  • PPM Asset Type

Sign and send

  • Overall Site Condition

  • Site Photos

  • Asbestos

  • I have inspected the above assets to the conditions specified in the referenced PPM schedules, and this report accurately reflects the condition of the site.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.