Information

  • Audit Title

  • Prepared by:

  • Project / area inspected:

  • Inspectors:

  • Select date

Administration / Program:

  • Workers have attended Safety/cGMP orientation. (Sub)contractor training verification

  • Emergency response, evacuation plans and rescue procedure in place, muster points posted in field.

  • First aid trained personnel on project, mutual aid contacted and verified.

  • Procedure for recording and investigation of incidents, first aid cases and near misses. (Fear factor of reporting is addressed)

  • Incident log (IE OSHA 300 log) being maintained, case management and return-to-work process.

  • Safety bulletin board with safe workdays posted and current safety information.

  • Contractor toolbox safety meetings held weekly, with intermittent Merck/CM participation.

  • Merck/CM led town halls being done.

  • (Sub)Contractors competent persons identified.

  • CM weekly safety meetings held with (Sub)contractors supervision.

  • MSDS provided to Merck, maintain in field office.

  • Job Safety Analyses / risk assessment / method statement completed as needed / required.

  • Distracted working and outside influences are addressed in planning.

  • Daily task safety planning completed, and white board coordination meetings help.

  • Weekly Merck led audits of work area safety done. Audits done with CM/Contractor participation.

  • SOR program in place, & feedback given to craft.

  • Emergency phone numbers posted in office areas and field.

  • Drinking water & wash facilities.

  • Toilet facilities available, accessible and clean.

Housekeeping:

  • Contractors inspect work areas daily.

  • Job site organized, not cluttered

  • Walking surfaces clear, clean, trip hazard eliminated

  • Trash / construction debris emptied regularly, disposal area neat, receptacles available.

  • Nails, scrap metal / wood picked up from previous days

  • Materials storage, proper segregation, stacked properly, chocked, no danger of falling.

  • Rodent, insect & vermin control

  • Site perimeter maintained

Personal Protective Equipment PPE:

  • Hard hats, safety glasses, class II high visibility work vest, safety toe work boot, task appropriate gloves meets GES requirements.

  • Safety glasses with secure side shields being worn.

  • Face shields / goggles worn where appropriate

  • Hearing protection used where appropriate

  • Glove program in effect & meets GES requirements

  • Back injury prevention (material handling)

  • Respirators / dust mask worn where appropriate, program in place, fit test etc

Fall Protection:

  • 100% fall protection used above 6 feet (EU 2 m)

  • Full body harness worn (incl. high reaches) inspection certificates available

  • Fall protection equipment in good shape and inspected

  • Anchorage points for fall arrest meet required ratings

  • Lanyards with shock absorbers and double locking clips

  • Perimeter guarding provided, perimeter cables or wire rope properly installed

Fire Safety & Emergency Procedures:

  • Proper fire extinguishers available and inspected

  • Used rags in labeled metal cans with cover

  • All walkways, stairs, access, egress free of combustibles

  • Trained fire watch on duty during hot work - area monitored after hot work completed

  • Workers know evacuation alarm signals and evacuation routes

  • First aid kit policy established and followed (CM or contractor provided)

  • Eye wash stations provided in field

  • Sprinkler heads unobstructed

  • Temporary heaters, ventilation, dehumidifiers, lighting properly installed

General Safety:

  • Work area barricaded, access limited

  • PPE signs posted near access points, safety posters, signage, banners in field

  • Flaggers for mobile equipment movements

  • Containers, chemical materials labeled (labels legible)

  • Fuels, flammable materials stored properly

  • Temporary lights provided where needed. Adequate task lighting provided as appropriate.

  • Temporary power provided, in good working order

  • Equipment / tools in good working condition

  • Equipment / tool guards in place, where needed

Ladders / Stairs / Scaffolds:

  • Proper types of ladders being used

  • Ladders in good operating condition, inspected and stored properly

  • Conductive (metal) ladders not in use near elec.

  • Extension ladders tied off, and/or footed and secure, extended 36" (EU 1 m) above landing, 4/1 slope maintained

  • Workers not using top two steps on ladders

  • Stairs provided where needed >19" (EU >0.5 m), secured.

  • Stairs greater than 4 Risers equipped with hand rail

  • Scaffolds correct and rollers locked when in use, tagged correctly,inspected daily.

  • Toe boards, railing on scaffolds, where needed

  • Scaffold planking overlaps 12" (EU 0.3 m)

  • Safe access / egress for scaffolds

  • Working platforms at least 2 feet (EU 0.6 m) wide, Safe loading of platform.

  • Workers protected from falls off scaffolds by railing and workers below protect from falling hazards

  • Holes / penetrations protected with secured covers labeled HOLE or barricaded. Hole cover removal / replacement procedure in place.

  • Backup alarms, horns on mechanized equipment

Welding, Cutting:

  • Compressed gas cylinders secured with chain or wire

  • Cylinders capped when not in use

  • Oxygen and flammable gas cylinders kept 20 feet (EU 5 m) apart or approved 1/2 hour fire wall separation.

  • Torch, hoses, Gages, regulators and cables in good condition. Torch equipped with flash-back regulator

  • Hot work permit in use, fire watch established

  • No combustible material in vicinity of hot work.

  • Welding screens used where needed

Lifting / Rigging:

  • Lifting and crane area barricaded, no lifting over personal, rigger and Flagger in place

  • Crane usage approved, pre-lift checklist completed, operator certification on hand. Daily and annual crane inspection documented

  • Tag lines used to control loads

  • Rigging equipment used properly, in good condition

Excavation / Confined Spaces:

  • Trenches / excavations sloped properly or shored and barricaded

  • Adequate access in / out of excavations (max 25') (EU max 7.5 m)

  • Spoils, tools, etc kept 2 feet (EU 0.6 m) back from excavation edge

  • Soil classification identified

  • Ventilation used for confined spaces

  • Confined space; personnel properly trained

  • Confined space; retrieval equipment available and usedropriately

  • Confined space; standby attendant present, communication means available

  • Confined space; air monitoring (including continuous) performed

Motorized Equipment:

  • Mechanized equipment used properly

  • Proper inspections performed / documented

  • Rollover protection in place and maintained

  • Seat belts used by all operators

Electrical Safety:

  • Cords in good condition, no cuts or repairs W / tape cables secured and off floor to minimize trip hazard

  • All electric extension cords inspected within last month (color coding)

  • GFCIs used for lead cords, GFCIs tested monthly

  • Grounding in working order on power tools, equipment

  • Temp electrical panels labeled, grounded

  • Conduit tightly connected to junction / outlet box, all breakers labeled and field outlets w/ circuit#

  • Adequate illumination

  • Temporary wiring; power / lighting isolated from building structure and not presenting trip hazard

  • Precautions taken where overhead lines are present, no work within min 20' (EU 6 m) clear

Hazardous Work (Permits):

  • Required permits completed properly, posted

  • Fire watch present for high energy (class A) hot work

  • Flammable / combustible materials removed from hot work area

  • Hazardous energy sources locked out properly

Environmental:

  • Containment for petroleum products adequate and in good condition (no debris, rainwater accumulated)

  • Petroleum tank / containment inspections and inventory adequately documented

  • Documentation of Asbestos survey with negative results for demolition and renovation.

  • Storm sewers protected

  • Threading machine catch box in place

  • Drip pans in place for equipment such as generators and welders

  • Containers labeled & closed when not in use

  • Chemical storage away from storm sewers and on impervious surface

  • Appropriate environmental training and documentation.

  • Erosion and sedimentation control at project site (silt fences, tarps, mulching, as necessary)

  • Erosion and sedimentation control in soil management area (silt fences, tarps, mulching as necessary)

  • Erosion and sedimentation control inspections being completed and logged.

  • Environmental excavation permit number on excavation permit.

  • Roll-offs labeled (contents, date waste first placed in container, designated non-haz or hazardous waste)

  • Roll offs covered and in good condition.

  • Appropriate residual waste handling, accumulation and disposal

  • Appropriate hazardous waste handling

  • Ensure all hazardous wastes are removed from site by contractor unless otherwise specified.

  • Lay down in appropriate areas (not on unimproved landfill)

  • Truck/Vehicle wash in place. Concrete truck washout procedure followed.

  • Dust generation minimized / controlled

Other / Miscellaneous:

  • Safety culture measurement plan in place. (Hearts and minds)

  • Safety surveys are being done to gain feedback.

  • Safety mentoring program is in place

  • Comments and Notes:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.