Title Page

  • Project Name

  • Project Number

  • Conducted on

  • Prepared by

  • Audit number

PPE

  • Required PPE is worn

  • Eye & sun protection is available

  • Hearing protection is available

  • Gloves and dust masks are available

Permits

  • Relevant permits are current

  • Permit conditions are adhered to

Machine Operations

  • Daily plant check has been recorded

  • Seat belt is worn

  • Plant door is closed

  • Plant covers have been removed

  • If not in use, plant is secure

  • Subcontractors' plant records are up to date

Lifting Operations

  • Lifting gear has current test tag

  • Lifting gear is appropriate for the task

  • Personnel is clear of suspended load

Shafts & Trenching

  • Existing services have been located

  • Excavation is secured from traffic

  • Excavation is secured from pedestrians

  • Personnel are within ground supports

  • Barricades are in place

  • Spoil is well away from edge of trench

  • Excavation is adequately supported

  • Means of entry/exit are provided

  • Ladders are secured

  • Fall protection gear is in place

  • Fall protection gear has current test tag

  • CSE gear is available

  • Shafts are covered

Incident Reporting

  • Known incidents are recorded

  • Incidents are reported

General Site Conditions

  • Site is safe and secure

  • Return to work poster is displayed

  • Emergency numbers are displayed

  • Project information sign is displayed

  • Toilet is clean

  • First aid kit is available

  • Spill kit is available

  • Housekeeping is adequate

  • Site traffic is controlled

  • TMP is in place and complied with

  • Site run-off is controlled

  • Sediment controls are as per EMP

  • Erosion controls are as per EMP

  • Flora & fauna management is as per EMP

  • Lighting is available for night work

  • Electrical gear has current test tags

  • Extinguishers have current test tags

  • Parked vehicles have minimal impact on road users, pedestrians and cyclists

Project Documents

  • Site folder is available

  • Latest constructions plans are on site

  • Inductions are up to date

  • Personnel are inducted to SWMS

  • Personnel are inducted to EMP

  • Personnel are inducted to CHMP

  • Daily risk monitoring record is current

  • Chain & Sling register is complete

  • TBM records are complete

  • Subcontractors’ docs are up to date

Pipe Laying

  • Approved materials only are in use

  • Materials are stored correctly

  • Defective materials are isolated

  • Works are as per design

Safety 1st Fundamentals

  • Safety 1st fundamentals are complied with

Comments/summary

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.