Title Page
-
Site conducted
-
This document will be used to close down site(s) whereas leaving safe and secure.
-
Site Operators
-
Location
-
Conducted on
-
Closedown performed by?
Selection of Close down required to complete
-
Would you like to close down an External Wall Insulation (EWI) job?
Access Solutions and Security
-
Is access denied with no risk caused to passers-by or to adjoining occupied properties, this includes trap-doors and gates being closed, Warning Signs in place?
-
Provide photo of the scaffold
-
Ladders removed or secured to prevent climbing?
-
SECURE or REMOVE LADDER BEFORE LEAVING
-
Take Photo of access denied
-
Take photo of locked / removed ladder
-
Is the Construction area secured with HERAS anti climb fencing, permanent fencing or Chapter8 barriers - Double clipped?
Site Presentation
-
Has the site been left in a presentable, clean, tidy and safe condition?
-
Photo of issues found
-
Have all access footpaths and roads been cleaned thoroughly?
-
Photos of issues found
Hot works and Lone Working
-
Are all team members accounted for? Nobody left on the construction area and ensure all works have ceased on departure?
-
Team Members must be located or Contacted to ensure their safety before leaving site
-
Have all hot works ceased at least 1 hour prior to leaving site?
-
Observations must stay in place to ensure fire does not start from Hot works
Compound, Waste and Security
-
Has all waste been removed from site and correctly disposed of?
-
Please Ensure waste is fully segregated and secured, confirm with Photo.
-
Have all Skips been taken away, locked or Net Installed and surrounding area is clean and free from over spill or debris?
-
Ensure issues are remedied before leaving
-
Evidential Photo
-
Are all storage areas secured with materials stored internally where possible?
-
Secure area before leaving
-
Evidential Photo
-
Is the compound fully secured and Lit where necessary with all services switched off?
-
Steps must be taken to switch off and secure the compound before leaving
Plant and Machinery
-
Is all Plant and machinery secured and immobilised?
-
Ensure the plant is secured and Immobilised before leaving
-
Are all fuel storage locations or tanks secured
-
Ensure fuel storage is secured before leaving
Selection of Close down required to complete
-
Would you Like to close down a First Time Central Heating (FTCH) Job?
Internal Checks
Site Presentation & Safety
-
Have any tools been left on site?
-
Photo to be taken
-
Ensure the tools are removed and area cleared
-
Have floor boards been reinstated and carpets rolled back?
-
Photo to be taken
-
Action needs to be taken to get floorboards reinstated and carpets back down
-
Have all dust sheets been removed or rolled up preventing trip hazards
-
Take a photo of the area affected
-
Action needs to be taken to remove or roll up dust sheets to prevent trip hazard!
-
Has the working areas been cleared and tidied to the customers standards?
-
Take a photo of the area affected
-
Action must be taken to get the area cleared and tidied to the customers standard!
-
Are all walkways clear of tools/Materials/debris and excess furniture
-
Take a photo of the area affected
-
Action must be taken to clear the walkway
Supplies
-
Has water supply been re-established and customer has running water with Flushing toilet?
-
Action must be taken to have the water connection re-established
-
Is the customer aware they may be without Direct Hot Water (DHW)
-
Explanations must be given to the customer
-
Are all electrical connections made safe and Flex's removed?
-
Photo to be taken
-
Connections must be made safe and Flex removed
-
Has Electrical supply been re-established and Power-On?
-
Action required to re-establish connection and powered on!
-
Has the Loft light been switched off and Loft ladder been retracted (whereas applicable) ?
-
Action required to Switch off the Light and retract the ladder where applicable!
External Checks
-
Have waste Materials been segregated and stored in one place ready for removal?
-
Photo to be taken
-
Materials must be removed and/or segregated and stored securely
-
Have materials not yet used, been stored securely, preventing theft?
-
Photo to be taken
-
Action required to store materials in a safe secure location or remove from site!
-
Have all walkways and public access and egress been cleared of obstructions?
-
Photo to be taken
-
Action required to clear all access and egress of the property!
Summary and Sign off
-
Comments / Issues or actions
-
Person Completing the Closedown procedure
-
Sign
-
Does the Customer have any issues at Closedown?
-
Sign
-
Highlight any issues the customer may have
-
Customer to sign