LOCATION / ITEM / ACTIVITY
Audit of Building / Area for Compliance
Documentation Checks
-
Check progress on Statutory Checks
-
Area Checked?
-
Follow up outstanding work orders
-
Review sign in book to check for unauthorised electrical workers
-
Check Electrical Authorisation Matrix for current
-
Check shift reports are completed correctly
-
Check for emailing of shift reports
-
Check for filing of shift reports
-
Address any shift report questions
-
Building or Area Inspected?
-
RCD Tag in date
-
Appliance test and tag in date
-
Appliances in good condition
-
Visual inspection of conduits, plugs, power points, switches
-
Isolation switches for air conditioners in good condition
-
Isolation switches for air conditioners in good condition
-
Check progress on Statutory Checks
-
Area Checked?
Documentation Checks
-
Commissioning documentation completed and correct
-
Are commissioning sheets filed for record keeping
-
Area Checked?
-
Check Pronto for backlog of work <br><br>
-
Check for filing of shift reports
-
Address any shift report questions
Review of Electrical Work Orders
Work Order Review 1
-
Work Order Number
-
Work Completed
-
Physical Check of Work
-
Work Conducted By
-
Work Recorded on Electrical Shift Report
-
Work not completed reason recorded
Work Order Review 2
-
Work Order Number
-
Work Conducted By
-
Work Completed
-
Work Recorded on Electrical Shift Report
-
Physical Check of Work
-
Work not completed reason recorded
Work Order Review 3
-
Work Order Number
-
Work Conducted By
-
Work Completed
-
Physical Check of Work
-
Work Recorded on Electrical Shift Report
Inspection of Electrical Installations
-
Check for emailing of commissioning documentation
-
Earthing
-
Additional Comments
-
Were Any Non-Conformances Identified?
-