Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
1. System Data
-
Chiller Full-Load Capacity (tons):
-
Chiller Full-Load Rating (kW/ton, or 1,000 lb/ton):
-
Equivalent Full-Load Operating Hours (hr):
-
Energy Cost Rate ($/kWh, or $/1,000 lbs):
-
2. Annual Energy Cost - Design Conditions
-
Chiller Capacity (tons)✖️Chiller Rating (kW/ton) or (1,000 lb/ton)✖️Equivalent Full - Load Hours (hr)✖️Energy Rate ($/kWh) or ($/1,000 lb) = ___________ (Design Annual Energy Cost ($) )
-
3. Annual Energy Cost - Actual Conditions
-
Design Annual Energy Cost ($)✖️[1➕Efficiency Loss] = __________ (Improved Annual Energy Cost ($) )
-
4. Annual Energy Cost - Improved Fouling Factor
-
Design Annual Energy Cost ($) ✖️[1➕Efficiency Loss] = __________ Improved Annual Energy Cost ($)
-
5. Annual Energy Savings
-
Actual Annual Energy Cost ($) ➖Improved Annual Energy Cost ($) = Annual Energy Savings ($)