Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Region
-
Contractor/s
-
Audit Date
-
Time
-
LIS No.
-
Equipment No.
-
Notification No.
-
Order No.
-
Date of works completed in the field.
-
Construction Type
-
Voltages
1. LV Crossarm
-
Are cross arm level and size correct?
-
Have phase plates been fitted?
-
Has a N plate been fitted?
-
Have conductor clearances been maintained?
-
Are bridges neat and tidy?
-
Are conductors tied in and secured appropriately?
-
Has the public light been fitted appropriately?
-
Are assets built to approved drawing's?
-
Have LV insulators been changed?
-
Are service tails or pole box leads adequately supported by under arm brackets?
-
Has the switchwire been removed?
-
If the switchwire has been removed has the remaining conductor been terminated correctly.
2. Services
-
Have all non standard services been changed as per opportunistic maintenance guidelines?
-
Are service heights compliant to requirements?
-
Do services have N tags ?
-
Are services terminated to standard requirements?
3. Hardware
-
Have line and PG clamps been replaced with Ampact connections where applicable?
-
Have all obsolete service clamps been removed from conductor?
-
Have obsolete or unapproved pole boxes been removed?
-
Are the newly installed materials approved?
-
Have opportunisitc maintenance been performed?
4. HV Crossarm
-
Are cross arm level and size correct?
-
Have phase plates been fitted?
-
Have conductor clearances been maintained?
-
Are bridges neat and tidy?
-
Are conductors tied in and secured appropriately?
-
Are assets built to approved drawing's?
-
Have HV insulators been changed?
5. Sub T Crossarm
-
Are cross arm level and size correct?
-
Have conductor clearances been maintained?
-
Are bridges neat and tidy?
-
Are conductors tied in and secured appropriately?
-
Are assets built to approved drawing's?
-
Have Sub T insulators been changed?
6. Pole
-
Construction Type
-
Has pole been sunk to required depth?
-
Is the pole straight
-
Are appropiate labels been installed on the pole, eg LIS. ?
-
Has the correct amount of back fill and topsoil been used ?
-
If a stay is attached is it at the correct angle, and constructed as per requirements?
7. Transformer
-
Has the transformer been built to UE standard ?
-
Has correct phasing identifaction been performed?
-
Have Surge diverters been replaced, and attached as per standard?
-
Have HV fuse units been replaced, and attached as per standard?
-
Has the structure had animal proofing installed as per the standard?
-
Have the LV leads been upgraded to the correct standard?
-
Have the HV leads been upgraded to the correct standard?
-
Has the TX been animal proofed to UE standard?
-
Have LV isolators been installed, and to the correct standard ?
-
Are the dressing down insulators preffered items. Ie-no wine glass ?
-
Is the TX installed height complaint?
8. Worksite
-
Has the worksite been left clean and tidy?
-
Has vegetation been cleared to meet compliance?
9. SAP Claims
-
Does the SAP claim match the works conducted on site?
-
Does the service provider claims match the claims in UE sap?
-
Comments
-
Comments
-
Overall Audit Rating
- 1
- 1.5
- 2
- 2.5
- 3
- 3.5
- 4
- 4.5
- 5
- 5.5
- 6
- 6.5
- 7
- 7.5
- 8
- 8.5
- 9
- 9.5
- 10