Platt & Reilly Inspection, Test and Approval Plan (ITAP-01) - 2 Grand Canal Quay - Partitions

  • Audit Title

  • Project

  • Main Contractor

  • Prepared by

  • Location

  • Conducted on

Partitions Description

  • Partition Type

  • Fire Rating - in accordance with FCD

  • Acoustic Rating (Rw dB)

  • Type of Floor & Ceiling Channel

  • Type of Stud

  • Gyp liner brackets centres

  • Stud Centers

  • Deflection

  • No of plasterboard layers each side of partition

  • Type of Plasterboard to 1st side

  • Type of Plasterboard to 2nd side

  • Acoustic Sealant Required

  • Insulation Type

Partition 1st fix Construction

Installation of Metal

  • Most current drawings revision for set out partitions

  • Datum & Grid Lines given by Main Contractor

  • Inspection of all gypframe metal approved and CE marked

  • Floor tracks installed as per partition spec including fixings centres

  • Head tracks installed as per partition spec including fixings centres

  • Correct Studs are installed & checked to be level and plumb ensuring deflection tolerance are correct

  • Gyp liner brackets installed as per partition spec including fixing centres

  • Door opes are installed as per door schedule / Door heads set from Datum lines

  • Door jambs sleeved as per manufacturer

  • Retaining channel used for shaft construction

  • Flat strap installed as per manufacturer details at deflection head and horizontal joints

  • Sign off Metal by P&R

Fire and Acoustic Rating

  • Partition head detail checked - Acoustic mastic installed

  • Insulation installed as per partition spec ensuring thickness is right

  • Correct boards are installed to meet fire and acoustic requirements

  • Sign off Fire and Acoustic Rating by P&R

Installation of service and architectural grounds

  • Most current drawing revision showing architectural grounds (RDS) issued

  • All M&E services requiring grounds have been marked on metal stud

  • Grounds are installed level and plumb to the correct height as required

  • Sign off Grounds by P&R

  • Sign off by Sisk

Partition 2nd fix Construction

Installation of Plasterboards

  • Closure cert issued by main contracor

  • Correct boards type used as per partitions spec to both sides of partition

  • Boards are installed to ensure correct deflection requirements are achieved

  • Correct drywall screws length are used for each layer of board installed

  • Boards screwed up @300mm centres

  • External corners and door jambs screwed up @200mm centres

Fire and Acoustic Rating

  • Boards joints are staggered as per manufacturers recommendations

  • Deflection head sealed and any partition abutment details checked

  • Sign off 2nd Fix by P&R

  • Sign off by Sisk

Partition Finishes

  • Corner / Stop beads installed correctly and plumb

  • Plasterboard joints are reinforced with paper tape as per Gyproc specs

  • Tape & Joint / SkimCoat applied in accordance with Gypsum Industries current recommendations

  • Sign off Finishes by P&R

  • Sign off by Sisk

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.