Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site Documentation
-
1. Current versions of JSEA are on site?
-
2. All employees and (sub)contractor personnel on site completed PES Company & Site-Specific Inductions?
-
4. Site safety inspections are occurring as schedule?
-
5. Daily Pre-starts meetings are occurring every day - Subcontractors are attending Pre-start meetings?
-
7. Do all items of plant have plant risk assessments available?
-
8. Safety issues raised at daily Pre-starts or toolbox meetings have been noted and addressed?
-
9. Toolbox for the site are occurring as schedule - subcontractors are attending addressed?
-
11. NCR or corrective actions from prior internal or external audits have been addressed?
Safety - Environmental
-
12. A site SMP is in place?
-
Safe Work Method Statements
-
13. Project specific for all high risk tasks on site?
-
14. Reviewed, signed and understood by those undertaking tasks?
-
15. Reviewed, checked against SWMS review checklist & signed off by HSE Officer?
-
17. All subcontractor SWMS reviewed by & signed off by HSE Officer?
-
High Risk Tasks on site
-
18. Is there any work in Confined Space?
-
19. Is there any Hot Work being performed? (Welding / spark emitting)
-
20. Work at Heights being performed? (where one could fall >1.8 metre)
-
21. Excavations /Trenching works being performed?
-
22. Underground / Overhead services clearly identified if present prior to work starting?
-
23. All plant operators on site licenced, competent and fit for work?
-
25. Emergency Response Plan in place and understood, have Emergency Assembly Areas been identified?
-
26. Are emergency contact numbers available to personnel on site? (ICE in contacts of phone)
-
28. Have site personnel been made aware of environmental restricted areas and controls?
-
30. Stocked First Aid kits & a minimum of 1 certified first aider on site? (ensure that the kit supplies within "used by date")
-
31. Fire extinguishers on site, well signed and been serviced in the last 6 months? (include plant extinguishers)
-
32. Are spill kits required, available on site with instructions for use and operators trained in their use/application?
-
33. MSDS sheets and register on site?
-
34. Hazardous substances and dangerous goods clearly identified (labels) and correctly stored?
-
36. PPE review - all personnel including subcontractors wearing the minimum and appropriate PPE for the job?
-
38. Evidence of unreported incidents - environmental (spills, emissions, noise, impact on native vegetation or wildlife habitat), property damage or personnel injury?
Site and Facilities
-
39. Site layout effective & allow effective access & egress to site & work zones, crib hut/portable building setup to SEMP?
-
40. Site signage appropriate - visible, accurate?
-
41. Vehicle movement plan, including parking arrangements for plant / equipment, segregation of pedestrians effective?
-
42. Site facilities appropriate - fresh drinking water, toilets, shade, extreme weather protection?
-
43. Company policies, committee meeting minutes, emergency evacuation, etc notices are available?
-
46. Are all plant/equipment fit for purpose, have compliance plates, registered, ROPS, FOPS, audible alarms, flashing lights & are used within manufacturer's requirements? Tag out non complying plant/equipment & remove from use.
-
47. Electrical equipment have been tagged and tested (not expired)?
-
48. Extension leads, cables, hoses, etc are set up appropriately ( off ground and free from potential damage)?
-
49. Temp power box AS3012 compliant, RCD'S in use on portable generations and for portable electrical equipment? VRDS used on arc welders where appropriate?
-
52. Has the fire danger rating been considered and appropriate controls put in place?
-
Other Observations?
-
Signature of person inspecting
-
Signature of supervisor on site