Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

General Information

  • Site Name and Address

  • Telephone No:

  • Photograph of Site

  • Email:

  • Type of Site

  • No of Staff Employed

  • Ownership

  • No of Competent Persons (For Assisted Deliveries)

  • Type of Operation

1.0. Administrative Records and Procedures

  • 1.1. Current Petroleum Licence and Conditions available?<br>PCA Section 1

  • 1.2. Expiry date shown?

  • 1.3. Are there special or additional conditions of Licence? PCA Section 2

  • 1.4. Are staff aware of Conditions of Licence? DSEAR Regs 11

  • 1.5. Are there any current site plans available? DSEAR Reg 5, ACoP L136 Control and Mitigation

  • 1.6. Is there a current tank to pump diagram? Best Practice

  • 1.7. No of tanks

  • No of Petrol tanks

  • No of Diesel tanks

  • No of other fuel tanks

  • 1.8. Is there an Electrical Test Certificate that covers the hazardous areas? DSEAR Reg 5; Electricity at Work Regs 1989

  • 1.9. Is there current Hazardous Waste Transfer Notes or Certificate available? Licence Conditions; DSEAR Reg 5; ACoP L137 Safe Maintenance

  • 1.10. Does the Operator maintain a Site Register? Best Practice

  • 1.11. Are wet stock records maintained with delivery certificates? Licensing Conditions; DSEAR Reg 5, ACoP L136 Controls

  • 1.12. Is there any evidence of gains or losses? Licensing Conditions; DSEAR Reg 5, ACoP L136 Controls

  • 1.13. Is there a record of Maintenance visits? DSEAR Reg 5, ACoP L137 Safe Maintenance

  • 1.14. Is there a Site Operating Manual kept? DSEAR Reg 9

  • 1.15. Are there any Staff Training Records? DSEAR Reg 9

  • 1.16 Are training manuals available and up to date? <br>DSEAR Reg 9

  • 1.17. Is there a HS(G) 146 Risk Assessment.<br>Good Practice

  • 1.18. Is there a risk assessment in accordance with DSEAR?<br>DSEAR Reg 5, ACoP L138 General Requirements<br>

  • 1.19. Does the DSEAR Risk Assessment include Tanker Deliveries?<br>DSEAR Reg 5 ACoP L133 Tanker Deliveries

  • 1.20. Is there a competent Person in charge of the site?<br>Licensing Condition; DSEAR Reg 5 & 8<br>

  • 1.21. Has the site installed Stage 2 Vapour Recovery?<br>PPC Regs (Permit Requirements)

  • 1.22. Is there test and installation documentation on site?<br>PPC Regs (Permit Requirements)

  • 1.23. Does the site operate Statistical Inventory Reconciliation?<br>Licensing Conditions; DSEAR Reg 5; ACoP 136 Controls<br>

  • 1.24. Does the site have an Emergency Action/Response Plan?<br>DSEAR Reg 8

  • 1.25. Are there safety procedures in place to protect employees against a Dangerous Substance? (Eg Safety Data Sheets and PPE)<br>DSEAR Reg 8

  • 1.26. Is there a first aid kit on site?<br>DSEAR Reg 8

  • 1.27. Are there records of maintenance of fire fighting equipment?<br>Licensing Condition

  • 1.28. Is there an Accident/Incident Book held on site?<br>DSEAR Reg 8

  • 1.29. Is there a Pollution Response or Restoration Plan in place?<br>DSEAR Reg 8

  • 1.30. Has there been any fire, explosion, leak or spillage on site?<br>Licensing Condition

  • 1.31. Has any request been made to disclose information held on file?<br>Freedom of Information Act 2003

2.0 Storage Tanks, Vents and Vapour Recovery

  • 2.1 Types of tanks known?

  • 2.2. Is there any record of any tank tests?

  • 2.3. Are there discontinued tanks on site?

  • 2.4. Have they been made either permanently or temporarily safe?

  • 2.5. Are there any above ground tanks?

  • 2.6. Are they bunded and free from debris?

  • 2.7. Are there any LPG storage vessels on site?

  • 2.8. Do LPG vessels appear in good condition, free from corrosion?

  • 2.9. Are LPG vessels in a secure compound, and protected against impact collision?

  • 2.10 Method of tank filling satisfactory?

  • 2.11 Off set or Direct Fill

  • 2.12. Are tanks tagged and labelled?

  • 2.13. Are fill pipes securely locked?

  • 2.14. Is a dedicated tanker stand provided?

  • 2.15. Is the tanker stand satisfactory, with dedicated drainage?

  • 2.16. Gauge measurement (or dipsticks) system working?

  • 2.17. Are tank chambers free from surplus water?

  • 2.18. Is all visible pipe/cable ducts sealed in manhole chambers?

  • 2.19. Is all visible pipe work free from excess corrosion and sound?D

  • 2.20. Are manhole lifting key(s) available?

  • 2.21. Are manhole chambers and covers in good condition?

  • 2.22. Are vents and vapour recovery lines secure and free from damage?

  • 2.23. Is there any opening within 1.5 metres with vapour recovery or within 3 metres for natural venting?

  • 2.24. Is vapour pipe work manifolded?

  • 2.25. Are all vent lines tagged and labelled?

  • 2.26. Has a vapour recovery permit been issued?

  • 2.27. Is vapour recovery warning and indication tags provided?

  • 2.28. Is there evidence of any test on the vapour recovery system?

  • 2.29. Has any maintenance taken place on the vapour recovery installation?

  • 2.30. Is stage 2 vapour recovery fitted and monitored and working?

  • 2.31. Is any dedicated tanker stand lighting working?

  • 2.32. Is there an unassisted delivery cabinet provided for the tanker driver?

  • 2.33. Is the phone, print out, high level alarm, spillage control and fire extinguisher provided and working?

  • 2.34. Emergency switch provided in the cabinet?

  • 2.35. Has the the number of drop lines been specified? Sign "Maximum number of tanker compartments to be unloaded simultaneously is x"

  • 2.36. Does the driver check the ullage space before dropping?

3.0 Pumps/Dispensers and Electrical Aspects

  • Make and Model of Pumps

  • No of Pump Islands

  • 3.1. Are all pumps numbered clearly?

  • 3.2. Do all automatic nozzle shut offs operate?

  • 3.3. Are all deliver hoses in good condition and free from leaks?

  • 3.4. Are all joints/couplings free from any signs of wear and leaks?

  • 3.5. Have all trigger latches been removed?

  • 3.6. Are dispenser housings ventilated properly?<br>DSEAR Reg 5, ACoP L134 Design of Plant and Equipment

  • 3.7. Are there any cavities at the base of the pumps (Old types)<br>DSEAR Reg 5, ACoP L134 Design of Plant and Equipment

  • 3.8 Are check valves (Suction System) fitted?<br>DSEAR Reg 5, ACoP L134 Design of Plant and Equipment

  • 3.9. Is a sump system (Pressure System) fitted?<br>DSEAR Reg 5, ACoP L134 Design of Plant and Equipment

  • 3.10. Are lead seals in position on metering devices?<br>DSEAR Reg 5, ACoP L136 Controls

  • 3.11. Are pump operating instructions clearly displayed?<br>DSEAR Reg 5

  • 3.12. Are fuel grades marked clearly?<br>DSEAR Reg 5f

  • 3.13. Does all electrical wiring appear free from damage?<br>Electriciety at Work Regulations 1989

  • 3.14. Are there any obvious signs of leakage?<br>eLicensing Condition; DSEAR Reg 5

  • 3.15. Are all dispensers secure on their mountings?<br>DSEAR Reg 5

  • 3.16. Are spillage control facilities provided for?<br>Licensing Conditions; DSEAR Reg 5

  • 3.17. Are diesel/LPG dispensers in good order?<br>DSEAR Reg 5

  • 3.18. Is visibility an issue over the dispensing area?<br>DSEAR Reg 5, ACoP L134 Design of Plant and Equipment

  • 3.19. Are vehicle parking arrangements satisfactory?<br>DSEAR Reg 5

  • 3.20. Type of earthing known?<br>Electricity at Work Regulations 1989

  • 3.21. Are all electrical ducts sealed where they enter the building?<br>DSEAR Reg 5

  • 3.22. Can any uncertified electrical equipment equipment be brought into the hazardous area?<br>Licensing Condition; DSEAR Regs 5 & 7; Schedule 3

  • 3.23. If a CCTV is installed as part of the safety arrangements for dispensing, is it working adequately?<br>Licensing Condition; DSEAR Reg 5

  • 3.24. Is the public address system working and sufficiently audible against all background noise?<br>DSEAR Regs 5 & 8

  • 3.25. Is there an emergency isolation switch under the Console?<br>DSEAR Reg 8

  • 3.26. Is there an emergency isolation switch on the fascia of any building suitably marked?<br>DSEAR Reg 8

  • 3.27. Are signs provided for all emergency switches?<br>DSEAR Reg 5 and Schedule 3

  • 3.28. Are all lights and switchgear that are not protected, outside of the hazardous areas?<br>DSEAR Reg 6

  • 3.29. If fitted, are all canopy lights working?<br>DSEAR Reg 6

4.0 Fire Safety, Signage and Drainage

  • 4.1. Are Fire Safety and Warning signs provided and legible?<br>DSEAR Regulation 8

  • 4.2. Is an interceptor or separator provided?<br>Licensing Condition; DSEAR Reg 5, ACoP L136 Controls

  • 4.3. Vent for separator in good order?

  • 4.4. Water act Consent?

  • 4.5. Are the existing arrangements capable of taking up to 9,000 litres of product?<br>Licensing Condition; DSEAR Reg 5, ACoP L136 Controls

  • 4.6. Is the drainage system clear of debris and surplus product?<br>Licensing Condition; DSEAR Reg 5, ACoP L136 Controls

  • 4.7. Are all storm drains clear of debris and fuel? (Surface Water)<br>DSEAR Reg 5, ACoP L136 Controls

  • 4.8. Is there drainage at the entrance/exit /tanker stand?<br>DSEAR Reg 5, ACoP L136 Controls

  • 4.9. Are LPG cylinders stored outside on the forecourt? If so are they secure?<br>DSEAR Reg 5

  • 4.10. Are all fire extinguishers checked and serviced at least once per year?<br>Licensing Condition; DSEAR Reg 5, RR Fire Safety Order 2005

  • 4.11. Are the types of extinguishers appropriate to the risk?<br>Licensing cCondition; DSEAR Reg 8; RR Fire Safety Order 2005

  • 4.12. Is there a written fire procedure displayed or known?<br>Licensing Condition; DSEAR L136 Controls; RR FIre Safety Order 2005

  • 4.13. Has all staff been trained in fire procedures and evacuation?<br>DSEAR Reg 11; RR Fire Safety Order 2005

  • 4.14. Are fire exits clear from obstructions?<br>DSEAR Reg 8; RR Fire Safety Order 2005

  • 4.15. Is the standard of housekeeping satisfactory?<br>DDSEAR Reg 5; RR Fire Safety Order 2005

  • 4.16. Are all panic bolts and escape door devices working?<br>DSEAR Reg 8; RR Fire Safety Order 2005

  • 4.17. Is emergency lighting installed? If so has it been tested within the last 6 months?<br>RR Fire Safety Order 2005

  • 4.18. Is a fire detection and alarm system installed? If so, is it tested each week?<br>RR Fire Safety Order 2005

  • 4.19. Are all promotional signs sited so not causing anobstruction?<br>DSEAR Regulation 6

Actions to be Taken

  • Action to be taken

Details required to:

  • Details required to:

  • Signed:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.